Microsoft Project 2007
Microsoft Project 2007
Table of Contents
Copyright © 2008. Carlson School of Management, Office of Information Technology, University of Minnesota.
Duplication of material without prior written consent is forbidden. September, 2008
MS Project 2007 Overview
Course Objectives:
At the end of this course, participants will be able to:
Terminology
The following terms are frequently used in project management.
Gantt Chart: A graphical representation of information in a project. It is the view most
frequently used in Project; a combination spreadsheet/bar chart.
Project: A set of tasks to achieve an objective. Usually must be completed in a specific
order and requires resources.
Resources: Can be people, equipment, materials or services that are needed to
complete various tasks. The amount of resources affects the scope and time of any
project.
Schedule: Time and sequence of tasks in a project.
Tasks: A division of the work that needs to be completed in order to accomplish the
project goals.
Predecessor: A task that must be accomplished before some other task (a
successor) can be started.
Successor: A task that can be accomplished only after a predecessor, or
prerequisite task, has been completed.
Summary task: A task that is made up of subordinate tasks.
Copyright © 2008. Carlson School of Management, Office of Information Technology, University of Minnesota.
Duplication of material without prior written consent is forbidden. September, 2008
MS Project 2007 Overview
Click
and drag
to resize
windows
Toolbars
By default the Standard and Formatting toolbars display on one row. To modify that,
select View, Toolbars, Customize. Activate the Options tab and select Show Standard
and Formatting Toolbars on two rows.
View Bar
The View Bar is a convenient way to switch between several views. Select View, View
Bar.
Views
Microsoft Project has multiple views available. These will be discussed in more detail
later in this class. The Gantt Chart view is the most frequently used when creating the
project. To select alternate views, select View; then select the desired option. These
instructions use the View menu to change views.
There are also multiple Table views. Select View, Table, and then select the appropriate
option. Instructions in this course will use multiple Table views.
Identifying Dates
If you do not define the dates, Project saves the current date as the start date for your
project. Follow these steps to identify the project start or finish dates.
1. From the main menu, select Project, Project Information. The following dialog box
displays.
2. To schedule the project from the Start date, verify that Project Start Date is selected
in the Schedule from: field, and select the appropriate start date by clicking the drop-
down arrow in the Start date: field.
or
To schedule the project from the Finish date, select Project Finish Date in the
Schedule from: field. Select the appropriate finish date by clicking the drop-down
arrow in the Finish date: field.
3. In the Calendar: field, select a different calendar, if desired.
4. Click OK to enter the date and close the dialog box.
Saving Changes
You can save changes by selecting File, Save, or clicking the Save button on
the toolbar.
Detailing Tasks
Each of the task areas can be further expanded into a series of tasks and subordinate
tasks. These tasks could be performed by one or more people. The numbered items
would be summary tasks.
1. Select a location
1. Determine budget for location
2. Research locations
3. Visit locations
4. Decide location
5. Reserve location
2. Activities/entertainment
1. Determine budget for activities/entertainment
2. Research activities/entertainment
3. Decide activities/entertainment
4. Arrange activities/entertainment
3. Menu/refreshments
1. Determine budget for menu/refreshments
2. Research menu/refreshments
3. Decide menu/refreshments
4. Arrange menu/refreshments
4. Guests
1. Determine guest list
2. Order invitations
3. Address invitations
4. Send invitations
Note: Column widths can be adjusted by selecting the line dividing the column headings.
When a two-headed arrow displays, click and drag to the desired width.
2. In the Task Name cell, type the task description; then press Tab to move to the
Duration field. By default, the Duration field displays 1 day?.
3. In the Duration field, enter the estimated duration for the task.
Note: We will not enter dates in the Start and Finish fields for each task at this time.
Microsoft Project can do this for us, depending upon how the tasks are related.
Note: You can click and drag the bars on the Gantt Chart to modify dates quickly.
Note: If you enter a time of “0” Project defines that task as a “Milestone.” See page
15 for more information.
4. To add a note about a task, select the task name, then click the Task Notes button
. Type your information in the Notes box and click OK.
Note: To view a note, rest your mouse over the note indicator.
Outlining Tasks
Outlining helps you organize your tasks into manageable chunks. It is easy to indent
related tasks under a more general task (summary task) to create a hierarchy. The
indented tasks are called subtasks.
You will use the Indent and Outdent buttons on your toolbar to organize the
outline.
1. If necessary, select View, Gantt Chart.
2. Select View, Table, Entry.
3. Select the task(s) you want to make a subtask.
4. Click the Intent button to make the task(s) a subtask.
As you enter durations for subtasks, the Summary task displays the date of the longest
duration.
Recurring Tasks
Recurring tasks repeat regularly, such as weekly meetings. These can occur daily,
weekly, monthly, or yearly. You can indicate the duration of each occurrence, when it
occurs, for how long, and how many times. For our practice project, we can create a
recurring task to receive and log RSVPs.
1. In the Task Name field of the Gantt Chart view, select the row beneath where you
want the recurring task to display.
2. Select Insert, Recurring Task. The Recurring Task Information dialog box
displays.
3. In the Task Name: field, enter the name for your task.
4. In the Duration: field, enter the duration for a single occurrence of the task.
7. Click OK. The task displays in the list as shown in the example below.
Indicates
Recurring
Task
Click + to view
individual tasks.
Shaded tasks
impacted by
schedule
changes.
1. From the menu, select Project, Task Drivers. The Task Drivers pane displays on the
left side of the Project screen.
2. Click the name of the task (shown with blue text) to view more information about the
impact of the change.
3. Click the X of the Task Drivers pane to close it. The highlighting is removed from
the task list of your project.
Splitting Tasks
If work is interrupted on a task, you can split it. The task can resume at another time.
Follow these steps to split a task.
1. Select View, Gantt Chart.
2. Select the task you want to split.
3. Click the Split Task button on the toolbar.
.
5. Click in the date where you want the split to occur.
6. Drag the second part of the bar to the date that you want work to begin again. A
dotted line displays where the task was split.
1. Select the ID field (leftmost gray field) of the task you want to copy, move, or delete.
This selects the entire row.
To select contiguous tasks, select the first task, press and hold Shift, and then
click the last task.
To select several non-contiguous tasks, press and hold Ctrl and select the
individual tasks.
2. Copy, move, or delete the task. (You can also right-click to select the desired option.)
3. To paste the copied or cut tasks, select the row beneath where you want the task to
display. Click the Paste button . If there is information in the destination row, the
new rows are inserted above.
1. Select the entire project by clicking the Select All button. This is the gray button
above the ID numbers on the far left column.
Hide
Subtasks
Button
Select All
Button
Note: You can also display an outline option to display specific outline levels, by clicking
and selecting the desired outline level.
Creating a Schedule
Once you have created your task list and outlined the tasks appropriately, you should
enter the task durations and indicate how the tasks relate to each other and to specific
dates. For instance, your project may have one task that should start as soon as
another is completed. This is called a task dependency. Microsoft Project automatically
determines the start and finish dates for tasks that have dependencies to other tasks. If
a task is changed, linked tasks are automatically rescheduled.
Many inexperienced Project users do not use these features correctly. However, to make
Project work effectively for project management, you should link tasks and create the
dependencies, thus allowing Project to create the schedule for you.
Microsoft Project creates a finish-to-start dependency by default. You can modify this to
a start-to-start, finish-to-finish, or start-to-finish link, as appropriate for your project. Use
links whenever possible to take full advantage of Project’s scheduling features.
Linking Tasks
1. If necessary, select View, Gantt Chart.
3. In the Task Name field, select the tasks you want to link, in the order you want them
linked.
Hint: Press and hold Ctrl while selecting non-contiguous tasks.
4. Click the Link Tasks button . Link lines display between the linked tasks.
Microsoft Project enters finish dates based upon the duration information entered
previously. The default dependency assumes that one task needs to be completed
before another can begin.
Deadline
Constraint
Constraint Date
Type
4. Click OK.
Note: If you add constraint dates, a calendar displays in the Indicators field to the
left of the task on the Gantt chart indicating that date constraints have been added. If
the date you indicate causes a conflict with your schedule, a warning message displays.
Creating Milestones
A milestone is a task used to identify significant events in a project schedule,
such as completion of a major phase. Often milestones don’t require work but
are significant points within the project schedule. To create a milestone, do one
of the following:
When creating a task, enter a duration of zero (0) days. Microsoft displays
the milestone symbol on the Gantt Chart at the start of that day.
or
Select the task you want to be a milestone. Click the Task Information button
. From the Advanced tab, select Mark task as milestone and click OK.
This allows the task to have more than zero days in the schedule.
Deadlines
You can also add a deadline to a task. This does not affect task scheduling, but
does provide an indication that you have a target date for completion of the task.
If you add a deadline to a task, a displays on the Gantt chart to indicate the
deadline date. If you add a deadline that is earlier than the date the project task
requires, Microsoft Project displays an indicator that the task is scheduled to
finish after the deadline. Note: Deadlines don’t affect how Project schedules
tasks. However, it is a way for Project to inform you that a task will finish past its
deadline. You may then wish to adjust the schedule to meet that deadline.
The illustration which follows indicates added deadlines and calendar constraints.
Note
indicator
Milestone
Date
constraint
added to task Deadline
Deadline
earlier than
project
schedule
Follow the steps below to add a task deadline. Tasks with deadlines applied that
are on or before the date determined by Project display when viewing the critical
path.
1. Select the task to which you want to add a deadline.
2. Click the Task Information button . The Task Information dialog box displays.
3. Activate the Advanced tab and enter the desired date in the Deadline field.
4. Click OK.
Assigning Resources
You should assign resources if you want to track work done by people or equipment
assigned to tasks or to monitor materials used. If you don’t enter resource information,
Microsoft Project calculates the project schedule using only task duration and
dependencies. As you assign resources, the resource information displays on the Gantt
Chart. Work resources are people or equipment. Material resources are items such as
concrete, lumber, paper. Think of material resources as things that can be “used up” in
the project. Lumber would be a material resource, while carpenters, hammers, saws,
and drills would be work resources.
3. In the Type field, select Work if the resource is a worker or equipment. This is the
most typical resource used in business.
or
Select Material, if the resource is material or supplies (paper, fuel, lumber, etc.)
Think of material as something that can be “used up.”
or
New Option – Cost. For instance, if your speaker charged air fare, you could include
that as a project cost. However, there would be no time assigned to this resource.
4. Press Enter.
5. Continue the steps above for each resource you want to add.
Note: When you add more than one resource to a task, Project may display
a next to the task. When you click the the following options display.
4. Scroll or resize the Gantt Chart window to view the Resource Names column.
5. In the Resource Names cell, type the name of the resource. Separate multiple
resources with commas. (Hint: Type names, e.g., Alice, Tom, etc. For many
names type first initial, last name, e.g., Knelson, Sborda)
Note: If resources have already been entered into the Resource Sheet, you can
select a resource from a drop-down list.
6. Repeat this procedure for each task to which you want to assign a resource.
Removing Resources
Follow these steps to remove a resource you no longer need for the project.
1. Select the task for which you want to remove a resource.
2. Click the Assign Resources button on the toolbar. The Assign Resources
dialog box displays.
3. Select the resource you want to remove.
5. Click Close.
Another duration is fixed duration (specific amount of time). Fixed duration tasks
indicate that a passage of time is required. For instance, if it takes two weeks for new
sod to take root, adding resources will not change that.
A third duration type is fixed work (hybrid of time and effort) duration. This means that
you can’t or don’t accelerate the task completion by adding resources, but you can
reduce the percentage of the resource devoted to the task. If a task has a duration of
three days, it will require 100% of one person’s time. However, if it is assigned to two
people, it will require 50% of their time for three days; four people, 25% of their time for
three days, etc.
When you add more than one resource to a task, Project may display a button next to
the task. When you click the the following options display.
5. In the Effort driven checkbox, select the appropriate option. (It should always be
selected for a fixed-work task.)
If selected, it specifies that Microsoft Project will keep the total task effort at its
current value. The duration of a task is shortened or lengthened as resources are
added or removed from a task while the amount of effort necessary to complete a
task remains unchanged.
6. Click OK.
Note: Task duration and percent of time per resource for a task may be impacted by
changing to a different type of duration. If necessary, adjust resource assignments as
desired.
Overallocated Resources
Overallocated resources display in red from several views. Add other resources or
reassign tasks as needed. Advanced users can use resource leveling.
Resource Leveling
Resource Leveling is a complex feature, which is for more advanced users. If
you have over-allocated resources, Project may display that information from
some of the resource views. Sometimes over-allocation will not cause a problem
with the project schedule. However, if over-allocation is not acceptable, you can
add more resources, or tell Project to level resources. Consult Help for more
information.
1. Select Tools, Level Resources. The Resource Leveling dialog box displays.
To have
Project adjust
the schedule
as resources
are assigned,
click here.
NOT If you click Manual, it
recommended spreads tasks over
for beginners. additional days to
allow sufficient time
for the tasks to be
completed.
4. For a Work resource, in the Std. Rate, Ovt. Rate, or Cost/Use fields, type the
resource rates.
For instance, employees would have hourly rates and perhaps overtime rates. Some
employees and/or equipment resources may have a flat charge; e.g., a projector may
be charged at a per-day rate.
or
For a material resource, type a measurement unit for the material resource in the
Material Label field, such as gallons, tons, reams, etc.; then in the Std. Rate or
Cost/Use field, type a rate.
or
For costs such as airfare, which require no time, but which add to the project cost,
enter the resource, and select the Cost resource type.
5. Press Enter.
2. Type in the appropriate (budgeted) cost in the Fixed Cost field. After saving a
baseline (see page 26) you can update the cost in that field. Project will track the
variance from the baseline.
3. Click OK.
Updating Tasks
As you complete tasks, you will want to indicate that in your project. You can use the
Tracking toolbar, or you can select Tools, Tracking, Update Tasks.
2. In the Task Name field, select the task(s) you want to update.
If the task is on schedule, select the task, and click the Update as scheduled
button on the Tracking Toolbar.
If the task is not on schedule, enter the start and finish dates as described below,
or update progress as a percentage.
4. To enter a start and/or finish dates, click the Update tasks button on the Tracking
toolbar. The Update Tasks dialog box displays.
5. Enter a date in the Start: or Finish: box. If you enter a finish date, be sure to enter
that the task is 100% complete. Microsoft Project will reschedule tasks accordingly.
6. Click OK.
3. To view the variance fields in the table, scroll, tab, or resize the panes.
Note: You must have saved a baseline in order to have variance information.
2. Select View, Table, Cost. Project displays the tasks and the estimated costs of
each.
Using Filters
You can use predefined filters within Microsoft Project. The default is All Tasks. Select
the desired filter by selecting it from the drop down list. For instance, you can filter to
view only incomplete tasks, or those over budget, etc.
Filter button
Viewing Reports
Project 2007 has some great new options for creating reports. Data can be exported to
Excel and Visio.
Note: As these new reports require knowledge of Pivot Tables, etc. this is outside the
scope of this class. If you are familiar with Pivot Tables and charts, you can explore the
options available. A brief description is provided below.
1. From the menu, select Report. The first two options are outside the scope of this
class.
Visual reports provide a wide array of options with report templates available
from Excel and Visio. Users can also customize templates.
Copy Picture may require installing an additional feature of Project that was not
part of the standard installation. After installing, you could use this option to
copy the current view to a .gif image, for example.
2. Select the type of report you want and click Select. Another screen displays from
which you can select the style of report you want.
3. Select the desired option and click Select. A print preview of the report displays.
4. To modify the printout, click Page Setup and make the appropriate changes.
5. Click Print.