JHA On Bar Bending Machine - Cutting Machine
JHA On Bar Bending Machine - Cutting Machine
JHA On Bar Bending Machine - Cutting Machine
Above JHA on Bar Bending & Cutting machine has been reviewed by us and found
confirming to specifications and relevant codes and hence accepted by us
REGISTRATION No.
Date:
REVIEWED BY:
CONCURRED
BY
APPROVED BY
INDIRA GANDHI CENTRE FOR ATOMIC RESEARCH
CONSTRUCTION OF BUILDINGS 302, 306, 307 AND ALLIED STRUCTURES Procedure No :
INCLUDING CIVIL, ELECTRICAL AND MECHANICAL WORKS FOR FRFCF AT FRFCF- TPL-JHA
KALPAKKAM
Page 2 of 8
INDIRA GANDHI CENTRE FOR ATOMIC RESEARCH
CONSTRUCTION OF BUILDINGS 302, 306, 307 AND ALLIED STRUCTURES Procedure No :
INCLUDING CIVIL, ELECTRICAL AND MECHANICAL WORKS FOR FRFCF AT FRFCF- TPL-JHA
KALPAKKAM
PREPARED BY :
ENGINEER-CIVIL
REVIEWED BY :
SAFETY OFFICER
APPROVED BY :
PROJECT MANAGER
Page 3 of 8
INDIRA GANDHI CENTRE FOR ATOMIC RESEARCH
CONSTRUCTION OF BUILDINGS 302, 306, 307 AND ALLIED STRUCTURES Procedure No :
INCLUDING CIVIL, ELECTRICAL AND MECHANICAL WORKS FOR FRFCF AT FRFCF- TPL-JHA
KALPAKKAM
ISSUE
Page 4 of 8
INDIRA GANDHI CENTRE FOR ATOMIC RESEARCH
CONSTRUCTION OF BUILDINGS 302, 306, 307 AND ALLIED STRUCTURES Procedure No :
INCLUDING CIVIL, ELECTRICAL AND MECHANICAL WORKS FOR FRFCF AT FRFCF- TPL-JHA
KALPAKKAM
1. Tools and tackles required : Reinforcement bars & bundles, Bar bending & cutting machine.
2. PPE's required : Helmet, Hand gloves, Shoulder pads, Goggle, Shoes, and
Reflective Jacket etc.
3. Authorization required : Work Permit.
1. Section-Head : Mr. Jois Sridhar Manager
SL.
STATUS REMARKS
NO DESCRIPTION
01 Whether trained operators are deployed for operating bending and YES NO
cutting machine?
Page 6 of 8
INDIRA GANDHI CENTRE FOR ATOMIC RESEARCH
CONSTRUCTION OF BUILDINGS 302, 306, 307 AND ALLIED STRUCTURES Procedure No :
INCLUDING CIVIL, ELECTRICAL AND MECHANICAL WORKS FOR FRFCF AT FRFCF- TPL-JHA
KALPAKKAM
04 Are Workmen wearing necessary PPE’s like helmet, gloves, Safety YES NO
shoe?
06 Is the place secured where the cut pieces fall instantly? YES NO
07 Whether cut pieces removed after finishing the whole cutting YES NO
process?
08 Is all the moving parts in the machines were closed properly? YES NO
10 Machine shall be inspected and certified for its fitness in regular YES NO
intervals and inspection tag to be ensured?
11 Is Double earthing provided for the Machine and ensured before YES NO
starting the machine?
13 Whether all cables are routed properly to avoid accidental damage YES NO
during material handling?
16 Whether Emergency Stop button provided for the Cutting & Bending YES NO
machine?
18 Whether access to reach the barbending and cutting machine free YES NO
from obstruction?
Page 7 of 8
INDIRA GANDHI CENTRE FOR ATOMIC RESEARCH
CONSTRUCTION OF BUILDINGS 302, 306, 307 AND ALLIED STRUCTURES Procedure No :
INCLUDING CIVIL, ELECTRICAL AND MECHANICAL WORKS FOR FRFCF AT FRFCF- TPL-JHA
KALPAKKAM
20 Whether all cutoff pins provided before initiating the barbending and YES NO
cutting process.
Name: Name:
Signature: Signature:
(P&M Engineer) (Safety Engineer)
Page 8 of 8