PMT Hps Honeywell Enraf Small Volume Prover Installation Operation Service Manual 005 025
PMT Hps Honeywell Enraf Small Volume Prover Installation Operation Service Manual 005 025
PMT Hps Honeywell Enraf Small Volume Prover Installation Operation Service Manual 005 025
Honeywell Enraf
Small Volume Prover Installation,
Operation & Service Manual
HONEYWELL ENRAF
SMALL VOLUME PROVER INSTALLATION,
OPERATION & SERVICE MANUAL
FOR
MODEL 05, 15, 25
3rd Edition
Released March 2016
Table of Contents
LIST OF FIGURES
Figure 1-1 Prover in Stand-By Mode. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-14
Figure 1-2 Prover During Prove Run - Mid-Run. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-14
Figure 2-1 Process Connections and General Arrangement . . . . . . . . . . . . . . . . . . . . . 2-2
Figure 2-2 Prover Lifting Diagram . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-3
Figure 2-3 Prover Service Clearance Diagram . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-4
Figure 2-4 Designated anchor points (plates) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .2-5
located on the bottom side of the prover frame
Figure 2-5 Electrical Enclosures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-6
Figure 2-6 Customer Connection Box . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-7
Figure 2-7 Power Box. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-7
Figure 2-8 SVP Controller Box with LAD. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-8
Figure 3-1 The Local Access Device (LAD) and its system overview. . . . . . . . . . . . . . . 3-2
Figure 3-2 Main Menu. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-3
Figure 3-3 Text Input Screen . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-4
Figure 3-4 Numeric Input Screen . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-4
Figure 3-5 Enumeration Input Screen . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-5
Figure 3-6 Status Bar . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-5
Figure 3-7 Menu Structure. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-6
Figure 3-8 Device Locking Menu. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-7
Figure 3-9 Password Input Screen. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-7
Figure 3-10 Configuration Menu. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-9
Figure 3-11 Configuration Menu Tree. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-10
Figure 3-12 Prover Calibration. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-14
Figure 3-13 System Information. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-14
Figure 3-14 System Information Menu Tree. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-15
Figure 3-15 Logs. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-16
LIST OF TABLES
Table 1 Environmental Configuration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-3
Table 1 Environmental Configuration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-3
Table 2 Prover Flow Range. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-3
Table 3 Wetted Parts. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-4
Table 4 Pressure Condition Ranges . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-4
Table 5 Inlet and Outlet Configuration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-5
Table 6 Motor Voltage Supply. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-5
Table 6 Motor Voltage Supply. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-6
Table 7 Electrical hazardous classification. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-6
Table 8 Flow Tube Finish. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-6
Table 9 Ambient temperature . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-7
Table 10 Process temperature. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-7
Table 11 Optical switch. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-7
Table 12 Nitrogen purge. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-7
Table 13 Insulation. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-8
Table 14 Pullers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-8
Table 15 Seals . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-8
Table 16 Controller. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-8
Table 17 Transmitters. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-9
Table 18 PED/PMI . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-9
Table 19 NACE and water draw. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-9
Table 20 Maximum allowable inlet and outlet flange loads . . . . . . . . . . . . . . . . . . . 1-11
Table 21 Prover Dimensions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-12
Table 22 Maximum pressure drop per prover size. . . . . . . . . . . . . . . . . . . . . . . . . . . 1-13
Table 23 Volumetric Water Draw Data Sheet . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-11
Table 24 Gravimetric Water Draw Data Sheet . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-18
Preface
The Honeywell Enraf (HE) SVP (Small Volume Prover) is a high precision
instrument for verification of calibration of flow metering equipment. The
SVP Controller and the Fusion4 Local Access Device (LAD) form the
control aspects of the SVP. The LAD is a hand held controller used to
interface to the SVP Controller allowing tasks such as the adjustment of
parameters, resetting of alarms and calibration. The LAD facilitates two way
data communications between the SVP Controller and the LAD, allowing
the rapid transfer of transaction data, configuration files and calibration
records and even upgrading of firmware in the field. The following warnings
apply to all components of the SVP.
Warning
Only use the instrument for its intended purpose.
EC declaration of conformity
Installation
Warning
For information on the dimensions of the flameproof joints, contact
Honeywell Enraf.
Commissioning
Operation
Additional information
Environmental conditions:
Ambient pressure : atmospheric
Relative humidity : 5 – 95 %
Ingress Protection : IP56
(IP rating)
Ambient temperature : ATEX Approval
Standard Temperature: -20°C to +40°C
(-4°F to +104°F)
Extended Temperature Options: As broad as
-40°C to +40°C (-40°F to +104°F) or -20°C to
+60°C (-4°F to +140°F)
CSA Approval
Standard Temperature: -20°C to +40°C
(-4°F to +104°F)
Extended Temperature Options: As broad
as -40°C to +40°C (-40°F to +104°F)
IECEx Approval
Standard Temperature: -20°C to +40°C
(-4°F to +104°F)
Extended Temperature Options: As broad as
-40°C to +40°C (-40°F to +104°F) or -20°C to
+60°C (-4°F to +140°F)
Special Approvals : up to 60°C (140°F)
Approvals :
ATEX: II 2 G Ex d [ia] IIB T6 Gb IECEx: Ex d [ia] IIB T6 Gb
Certificates:
Approval Certificate number
ATEX 12ATEX0101 X
IECEx DEK 12.0021X
CSA 11.2370409
Approvals :
II 2 G Ex ia IIB T4 Gb
Ex ia IIB T4 Gb
Certificates:
Approval Certificate number
ATEX KEMA 10ATEX0152
IECEx IECEx KEM 10.0070
CSA 11.2395571
Warning
1.
Before performing any operations with the Honeywell Enraf small
volume prover read this operation manual completely! Also read API
MPMS 4.8 “Operation of Prover Systems”, Current Edition. If there are
any uncertainties please consult your Honeywell Enraf representative
or the factory directly.
2. The Honeywell Enraf small volume prover has been designed to meet
certain operational conditions. Using the prover outside of these
boundaries may cause permanent damage and will void warranty
(ref. Section 1.3)
3. All provers are designed as per pressure standard ANSI B16.5. For
process temperatures above 37.8°C (100°F), pressure must be
de-rated, following the above mentioned standard.
4. Each Honeywell Enraf small volume prover is functionally tested at
different flow rates starting from the lowest to the maximum flow rates,
pressure tested (hydrostatic pressure test) and water draw calibrated
at the factory prior to shipment. When the equipment is received,
inspect the outside of the packing case(s) for damage. Any visible
damage should be reported to the carrier immediately, for the purpose
of liability. If anything is missing or incorrect from your shipment,
please contact your local Honeywell Enraf sales representative or
sales office. Have the serial number and sales order number available
to help expedite any assistance needed.
5. The Honeywell Enraf small volume prover has been designed to be
used as either a portable or stationary mounted flow prover. The
Honeywell Enraf small volume prover may be installed upstream
or downstream of the meter under test, as the displaced volumes
are equal.
Warning
For proper operation of the SVPs it is mandatory to properly vent the
prover and to make sure that fluid vapor is removed from the SVP. SVPs
can fully function when proving fluids are in the liquid form only.
It is the responsibility of the user to satisfy the relevant electrical code
requirements on connections made to the Honeywell Enraf small
volume prover.
18. Covers must be in place on all explosion-proof electrical enclosures
at all times when prover is energized. If it is necessary to troubleshoot
electrical components, it must be done in a “safe” area following
site procedure.
19. All drive covers must be in place during operation or anytime electrical
power is applied to the prover to avoid personal injury.
20. Shaft cover located on the downstream side of the flow tube must be
in place during prover operation to avoid personal injury.
21. Do not alter or modify the Honeywell Enraf small volume prover
without prior written consent from the factory. Honeywell Enraf will
not be responsible for possible damages, loss, or injury as a result of
unauthorized use or modification.
22. Ensure that the unit is fully depressurized and drained prior to
disassembly or service.
23. Prover frame must be correctly earth grounded prior to electrical
service. Grounding connector is located on the prover frame.
24. Follow all hazardous warning stickers! Pinch and crush points are
present on this equipment in addition to electrical shock hazards.
1.1 Overview
This manual provides the necessary information and procedures for the
proper operation of the Honeywell Enraf small volume prover manufactured
by Honeywell Enraf Americas, Inc.
The Honeywell Enraf small volume prover uses a wear and corrosion
resistant precisely honed flow tube. Contained within the flow tube is the
piston/bypass valve arrangement. Piston/bypass valve arrangement has
been designed in such a way that during the proving runs disturbance to
the flow is minimal. The free flowing piston has an inherent fail-safe feature
that will not cause disruption to the flowing fluid in case that the poppet
actuator shaft becomes disconnected or otherwise fails. The poppet
valve is coaxially mounted within the free moving piston. At the time a
calibration run is initiated by the operator, the piston assembly is moved
to the upstream end of the flow tube by a mechanical drive driven by an
explosion-proof electric motor. When upstream position has been reached,
the poppet valve actuator shaft is released by the return mechanism,
allowing the poppet valve to close and the flowing fluid to move the piston
through the measurement cylinder.
Slotted precision optical switches are utilized to define volume
displaced. These switches are reliable, fast (5 X 10-6s), and precise,
showing a maximum deviation of +/- 0.0005 % on repeatability of linear
measurement. For maximum fluid compatibility the only seals in contact
with the flowing fluid in the Honeywell Enraf small volume prover are filled
PTFE. A static leak detector is provided with the prover. This consists of
a device to generate a differential pressure across the piston. When filled
with fluid, and the blocking valves closed, the operator simply provides
a differential pressure gauge or transmitter to monitor any leakage while
differential is applied. (Refer to static seal leak test). The latest version of
the Honeywell Enraf small volume prover incorporates a hazardous area,
intelligent controller, utilizing state-of-the-art microprocessor technology
and a display to provide a window to the operation of the prover. When
used with its associated Local Access Device (LAD) you are able to view
the status of the calibration and perform diagnostics.
The contents of this manual provide general information and operational
characteristics for the Honeywell Enraf small volume prover. This
manual does not include information regarding auxiliary equipment for
unique applications. Consult your factory approved service center for
this information.
Offshore prover: 316 Stainless Steel for wetted parts and for drive end mechanical components (chains, bars,
O
sprockets etc)
Operating flow range: The operating flow range depends of the meter
type as stated in the Table 2 below. (Please Note: Below mentioned
maximum flow rates must be de-rated when the fluids with viscosity above
100 cSt are used.)
C 304 Stainless Steel flow tube with chrome plated bore. 304SS piston assembly, end flanges & shafts
316 Stainless Steel flow tube with chrome plated bore. 316SS piston assembly, flanges, & shafts
E
(Required for ‘O’ Models)
ANSI B16.5 Flange Rating (Position 6) 005 015 025 035 050 085 120
"*" : available
"#" reduced lead time
D 24 VDC Y Y Y Y
A 120 VAC, 60 Hz Y1 Y1 Y1 Y1 Y1
B 220 VAC, 60 Hz Y1 Y1 Y1 Y1 Y1 Y1
D 24 VDC Z2 Z2 Z2 Z2
C 220 VAC, 50 Hz Z Z Z Z Z
B Painted (White)
Options Extra optical switch: This switch reduces the volume signal to
a lower displaced volume to reduce the calibration runtime on low flow
rates. The smaller stroke volume is selected via a menu option. Position of
the third optical switch depends on the application : Please contact your
nearest sales office.
Nitrogen purge system: The purge covers consist of both a cover on the
downstream shaft and a cover for the drive end and are needed to prevent
icing of the shaft that can occur when the product temperature is below
0 °C (32 °F) when in operation. Covers are made of stainless steel and
will have O-ring sealing. The kit includes a pressure relief valve. The drive
end will also be purged via a purge control system. Purge system may be
manual or automatic, but the automatic purge is not available below
-20 °C (-4 °F) ambient temperature.
Insulation
This option is for applications on process fluid temperatures low or high
(above 60 °C - 140°F). It consist of two parts:
1. An insulation plate between the drive unit and flow tube.
2. An insulation jacket for the flow tube. This is model-dependent and not
suited for tracing. –– For low temperature applications the insulation
plate is a minimum requirement to protect the drive end.
0 Without insulation
1 Insulation plate
Pullers: Models 35, 85 or 120 come with one puller as standard on the
chain drive pulling system. Adding an additional puller decreases the idle
time between runs and increases the frequency of the proving runs.
Seal material: Standard seals are made of Ekonol® filled PTFE. For crude
oil applications it is advisable to use carbon-reinforced seals to increase
their lifetime.
1 Other transmitters
2 No transmitters
0 No approval
3 PMI +PED
(Position 23)
Top Nozzle Fy = 747 N 168 lbf Each Nozzle My = 503 Nm 371 lbf•ft
Top Nozzle Fy = 1744 N 392 lbf Each Nozzle My = 1234 Nm 910 lbf•ft
Top Nozzle Fy = 2647 N 595 lbf Each Nozzle My = 2577 Nm 1901 lbf•ft
Top Nozzle Fy = 4671N 1050 lbf Each Nozzle My = 3227 Nm 2380 lbf•ft
S/O/P120 – Inlet/Outlet Nozzle Nominal Diameter: 16 inch
Top Nozzle Fy = 5916 N 1330 lbf Each Nozzle My = 3796 Nm 2800 lbf•ft
Dimension
005 015 & 025 035 050 085 120
Description MODEL
ANSI 600 ANSI 150 ANSI 150 ANSI 150 ANSI 150 ANSI 150
mm [inches]
2756 4089 4089 4572 5258 5576
Length A
[108.5''] [161.0''] [161.0''] [180.0''] [207.0''] [219.5'']
Width at Frame B 813 [32.0''] 986 [38.8''] 1092 [43.0''] 1245 [49.0''] 1448 [57.0''] 1549 [61.0'']
Width at Feet C 947 [37.3''] 1118 [44.0''] 1227 [48.3''] 1378 [54.3''] 1588 [62.5''] 1702 [67.0'']
Inlet & Outlet
D 424 [16.7''] 513 [20.2''] 565 [22.3''] 673 [26.5''] 756 [29.8''] 840 [33.1'']
Height**
Inlet & Outlet
E 780 [30.7''] 1369 [53.9''] 1299 [51.2''] 1473 [58.0''] 1930 [76.0''] 2045 [80.5'']
Separation**
Inlet Distance
F 955 [37.6''] 1499 [59.0''] 1534 [60.4''] 1873 [73.7''] 2106 [82.9''] 2244 [88.4'']
from End**
Highest Point** G 1207 [47.5'']* 1257 [49.5'']* 1257 [49.5'']* 1308 [51.5'']* 1316 [51.8''] 1481 [58.3'']
Inlet & Outlet
3 Inch 6 Inch 8 Inch 8 Inch 12 Inch 16 Inch
Flange Size
NOTES:
1. All dimensions are in mm (inches)
2. Dimensions 'D', 'E', 'F' and 'G' may vary according to
model type/configuration
3. All dimensions vary according to pressure rating
4. All dimensions are subject to change
Table 21: Prover Dimensions
Pressure drop: Pressure drop measured between inlet and outlet of the
prover is specified in the Table 12 (see below). The drop is obtained at
maximum flow rate using water as a fluid.
After the piston has been released and synchronized with the fluid flow, the
precision optical start of volume switch is actuated, which sends a signal
to the flow computer to start the timing sequence. The piston continues
downstream with the flow. Upon reaching the end of volume switch, a
signal is sent to the flow computer to stop the timing sequence. After
passing the end of volume switch, the piston shaft is stopped mechanically.
The fluid pressure in the prover pushes the perimeter of the piston further
downstream, opening the flow-thru poppet valve, allowing the flow to
continue with little to no pulsation or surge in line pressure. The return drive
motor is started electronically to pull the piston back upstream if the flow
computer requires more passes and the above sequence is repeated.
CONTROL &
VOLUME SIGNAL
POWER SUPPLY
FLOW
T
PROVING T
Enraf Small Volume Prover
COMPUTER
P
DRIVE END
OPEN INLET OPEN OUTLET
VALVE VALVE
Warning
Do not exceed the maximum working pressure of the prover as detailed on
the nameplates.
It is the customer’s responsibility to install the prover in a system that is
protected by correctly sized over-pressure protection.
Caution: Be certain that all flanges, bolts, dry break couplers, hammerlock
fittings, hoses/loading arms, and pressure containing components have
sufficient pressure rating. Also be absolutely certain that the flow direction
through the prover is correct!
Enraf
B B
A A
FLOW
MODEL A B C D E F
05 610 (2) 610 (2) 610 (2) 1220 (4) 1520 (5) 1520 (5)
15 610 (2) 610 (2) 610 (2) 2140 (7) 1520 (5) 1830 (6)
25 610 (2) 610 (2) 610 (2) 2140 (7) 1520 (5) 1830 (6)
35 610 (2) 610 (2) 610 (2) 2140 (7) 1520 (5) 1830 (6)
50 920 (3) 920 (3) 920 (3) 2750 (9) 1830 (6) 2140 (7)
85 920 (3) 920 (3) 920 (3) 3050 (10) 2140 (7) 2140 (7)
120 1220 (4) 1220 (4) 1220 (4) 3360 (11) 2440 (8) 2440 (8)
NOTES:
1. The lettered dims represent a minimum recommended service
clerance around the prover
2. All dimensions are in mm (ft)
3. Clearance must be provided by customer
Figure 2-3: Prover Service Clearance Diagram
Figure 2-4: Designated anchor points (plates) located on the bottom side of the prover frame.
The Honeywell Enraf small volume prover is fitted with transit seals in both
the up & downstream shaft seal retainers upon its shipment from the
factory. It is important to replace these seals during the commissioning
procedure and prior to the process fluid being introduced into the unit.
An additional set of seals are supplied with every prover for this purpose.
2.4.2 Breaker
A readily accessible disconnecting/breaker device shall be incorporated
external to the equipment.
2.4.3 Enclosures
The picture below shows the three electrical enclosures mounted on the
Small Volume Prover. The connections to the SVP Controller Box are made
at the factory and must not be modified. All of your connections are to be
made in the Power Box and the Customer Connection Box.
SVP
ENCLOSURE
CUSTOMER
POWER CONNECTION
BOX BOX
3.2.2 General
The SVP Controller can be configured through the wired Ex i interface with
a Local Access Device (LAD).
The LAD (Local Access Device) is a hand held controller used to interface
with the Fusion4 product family, allowing tasks such as parameter
adjustment, alarm resetting, and calibration. The device facilitates two-way
data communications between the SVP Controller and the LAD, allowing
the rapid transfer of transaction data, configuration files and calibration
records, and even firmware upgrading while in the field.
Figure 3-1: The Local Access Device (LAD) and its system overview
3.2.3 Commissioning
The LAD is used to commission the SVP Controller by configuring entities
(or parameters) to the desired specific values. This is done by using the
LAD to navigate through the Menu functions of the SVP Controller
(See 3.3.4).
3.3.1 General
Title
Selected item
(focus rectangle)
Only available
if LAD is connected
Title bar
Single line edit field
Selected letter
Action message
Numbers grouped
Letters grouped
Scrollbar
Focus rectangle
Action message
For a high level overview of the entities and parameters, see the
following diagram (Figure 3-7).
For a detailed view of all menu items, see the individual section.
Within this screen, the user can lock and unlock the SVP Controller.
A single password is used to lock the controller from further
configuration via HMI.
Password is alphanumeric
• Only capital letters
• A-Z, 0-9, _, and ’.’
• No spaces
• Maximum of 6 characters
Device remains unlocked until explicitly locked again
The "lock status" is shown at the status bar in the bottom right corner
(padlock) as seen in the following screen.
To unlock the controller, the user must enter the password as entered
during the locking of the controller. The password will be stored in
non-volatile memory.
Note that the locking feature is not infallible as the password is visible to
any user with a LAD connected to the controller. It is intended to keep
the uninformed user from accidentally changing configuration settings.
Changing the configuration parameters will not affect the performance of
the prover although caution must be used if changing the Motor parameters
or the Sensor Pair. Changing of the Sensor Pair is only applicable if you
have the optional third optical switch installed.
Changing of the Motor parameters should only be done after consultation
with Honeywell Enraf experts as damage to the drive end could occur;
the Motor parameters are set at the factory for the specific model of
your prover.
3.3.6 Configuration
3.3.6.2 Device
3.3.6.2.1 Identification
[Device name] The name of the SVP itself. In order to have Can be a text string of maximum
a unique identification of the device by a 20 characters
text string
Will be shown in the running screens.
3.3.6.2.2 Units
3.3.6.2.3 Display
3.3.6.2.4 Time
3.3.6.2.5 Motor
These parameters are set at the factory and must not be changed without
consulting Honeywell Enraf experts or damage to the prover may occur.
3.3.6.4 Alarms
The following alarm entity applies to Service Due Reminder and Machine Fault.
The Service Due Reminder alarm is activated when the cycle count
reaches the threshold value programmed by the user at the Cycle Count
Threshold menu. The default setting for the Cycle Count Threshold
is 1000.
The menu screens for Prover Calibration are shown in the diagram below
(Figure 3-12). See Chapter 5 for detailed calibration procedures.
The menu tree below shows how the information menus are accessed.
3.3.9 Logs
The log memory will be a rolling memory file with the oldest data being
overwritten first when the memory is full. Note that the log will be simply
overwritten without issuing a warning message.
The transaction log will contain the following data for each Prover run:
Date and time
Sweep time in seconds
Number of prover cycles
There are no units displayed for the average volume as they will be
known by the user and to avoid complications if the units specified in the
Configuration/Device/Units menu are changed.
The Alarm log forms a permanent record of the same information that
can be viewed while an alarm is active from the Diagnostics/Active
Alarms screen. This information consists of the date and time stamp and
descriptive text.
3.3.10 Diagnostics
Within this screen, the user can view the diagnostics about the
following subjects:
Overview of all I/O (Dashboard)
Overview of system health
Overview of all active alarms
Overview of device tasks such as clearing tasks, clearing alarms, and
running prover test task
Overview of available memory storage space for data logs and total
number of available logs
The diagram below shows all of the information available to you. Note that
the parameters marked with an * are not relevant for the first release of the
SVP Controller. They are reserved for future use or for internal testing.
3.3.11 Transfer
Events/logs (alarms)
Calibration records
1. Firstly, carry out the removal and replacement of transit seals with
the operation seals (as supplied) prior to introducing liquid into the
Honeywell Enraf small volume prover.
2. Open fluid inlet valve slowly. After the inlet valve is completely open,
open fluid outlet valve, connecting the prover to the process line,
Figure 2-1.
3. Vent trapped air from the prover by opening the vent valves located at
the top of the prover flow tube.
4. Close process diverter valve, Figure 2-1, slowly to divert the flow
through the prover.
5. The Honeywell Enraf small volume prover is now ready for meter
proving. Refer to the appropriate proving computer manual for
procedures for performing meter proving runs.
6. After meter proving runs have been completed, open process diverter
valve, and slowly close the prover connection valves.
If you have the optional third optical switch installed on your prover refer to
Chapter 3 section 3.3.6.2.6 for Sensor Pair configuration prior to operating
your prover in any of the following three modes of operation.
On the first power up and after any machine fault alarm, the piston position
will be unknown and one proving run needs to be successfully completed
in order to initialize the piston position status. Upon sending the signal
from the PROVEit software or the other flow computers, the prover motor
will retract the piston assembly and the proving run will start. At the end of
the proving run the flow rate will be displayed on the screen and the next
proving run can be initiated.
During the return and proving mode different piston positions and
the motor status will be displayed on the SVP controller screen.
At the end of the proving run the sweep time, cycle count and the
stop time will be updated. If any errors occur during the proving
run the error will be reported on the screen and will need to be
cleared via the LAD (Main menu/Diagnostics/Dashboard/Alarm Clear –
see Chapter 6 - Troubleshooting).
The Prover Test mode can be useful to become familiar with your prover
and to verify proper operation. This mode is accessed by navigating with
the LAD through the following menus: Main Menu/Diagnostics/Prover
Service Test/Run Prover Test.
Pressing OK on the LAD at Run Prover Test causes a prover run cycle to
be executed, and the SVP Controller display will appear as shown below.
With the piston at the extreme downstream position, the Parked Position,
the motor will pull the piston upstream and the piston position will be
shown on the Prover Status screen as the associated optical sensor flag
passes through the Downstream sensor and the Upstream sensor until
the motor stop switch is activated. Run Prover Test can be executed
repeatedly while the liquid flows through the prover pushing the piston
towards the downstream side. This test will only run in the absence of
a Flow Computer run permissive signal; it will not be executed if the run
permissive has been asserted by a Flow Computer.
See Chapter 6 - Troubleshooting if an error status is indicated.
To exit this operating mode use the LAD to navigate to Main Menu/
Diagnostics/Prover Service Test/Exit Prover Test
The third operating mode of the controller is Prover Calibration and will be
described in more detail in the next chapter.
5.1 General
It is recommended that prior to doing any volumetric calibration that
the personnel involved read the API Manual of Petroleum Measurement
Standards (MPMS) Chapter 4 – Proving Systems sec 4.8, and the MPMS
Chapters 4.9, and 12.2.4 – pertaining to the calculation for the volume of
provers.
Although the prover may be calibrated with procedures traceable
to the National Institute of Standards and Technology (NIST) by a
number of techniques, only two techniques for volume determination
will be described here, a volumetric calibration and a gravimetric
(mass) calibration.
The gravimetric calibration method requires collecting the volume of water
displaced by the prover during a prove pass and determining its mass by
weighing it with a precision scale or balance. Corrections are made for the
density of the water and the buoyancy of the air displaced by the volume
of water per API 14.6, and applying various other correction factors such
as the temperature and pressure effects on the flow tube and the volume
switch position. De-ionized or distilled water should be utilized for the
gravimetric method. API 4.9.4 is the API standard used for the density
determination of water.
The displaced volume has been calibrated as described in the MPMS API
chapters,: 4.2, 4.9 and 12.2.4.
The Honeywell Enraf small volume prover base volume has been
determined at the factory. Recalibration is recommended either at 1 year
intervals, or as determined by the authorities and parties responsible for
the measurement. Recalibration is also required after any maintenance
which may affect the base volume, i.e.: complete switch bar replacement.
Honeywell Enraf small volume prover optical switches are field replaceable
and adjusted to an extremely high degree of precision. Individual switch
replacement does not necessitate re-calibration. See Section 6.7 for more
information on optical switches.
5.2.1 Equipment
1. Block all inlet and outlet ports on the prover (including drains).
2. Refer to Figure 5-1, 5-2 & 5-4 below and install the differential
pressure gauge (1) between the inlet and outlet ends of the prover.
3. Fill the prover with liquid and vent off all air from the system.
4. Determine there are not leaks from the prover ports.
5. If necessary, blind the inlet, outlet and drain lines with blind flanges.
6. Power up the proving computer and the Honeywell Enraf prover.
7. From the proving computer, initiate a proving run to pull the
piston upstream.
8. Remove the plug from the drive cover end panel.
9. Install the differential pressure creator (2) in the threaded hole provided
in the drive system end plate and hand tighten, refer to Figure 5-3.
10.Rotate the adjustment screw (3) Figure 5-4 clockwise to push the
plunger out to apply force to the piston shaft and create a differential
pressure between the inlet and the outlet of the prover. Rotate the
adjustment screw until a differential pressure of 6 psid has been
created. Pressurize the unit slowly and watch the pressure gauge.
In some cases it might happen that applied pressure of 6 psid will
be significantly lost in the first couple of minutes. The reason is
that the poppet valve will need short period of time to fully close
and stabilize.
Therefore, it is our recommendation to allow at least 5 minutes
between the applied pressure and actual data recording.
11. Look the prover over for any obvious external leaks.
12. Start observing the differential pressure gauge for a period of 20
minutes. If the pressure has not dropped by more than 25% of the
starting differential pressure, it may be assumed that there are no
piston seal leaks. If the pressure has dropped to lower levels, it should
be assumed that there is a seal leak, and the prover piston seals
should be replaced. Refer to Figure 5-5.
Figure 5-1: Static Leak Detection Set-up Figure 5-2: Gauge with HI & LOW markings
Figure 5-3: D
ifferential pressure creator inserted in drive end plate.
ADJUSTMENT SCREW 3
FLOW
+ -
PN #44100375
CABLE FROM
SOLENOID VALVES
TO ENCLOSURE
POWER ENCLOSURE
POWER SUPPLY CONNECTION
PN #10601197
WATER DRAW
PLUMBING ASSY
TUBING TO
TUBING TO WASTEWATER
TEST CATCH CONTAINER
MEASURE
Procedure
Water draw notes:
Perform steps 12-17 at least twice prior to taking data to purge the system of
air, assure the temperature is stable, and to get familiar with the procedure.
Repeat the water draw procedure until at least 3 consecutive draws
repeat within 0.02% or other repeatability criteria that the certifying parties
agree upon. The flow rate on at least one run must vary by 25% to assure
integrity of prover seals and absence of leakage.
Failure to achieve the necessary repeatability may be caused by leaking
valves, air in the system, varying pressure, leaking seals, or faulty
calibration technique.
1. Be certain that all maintenance that needs to be done to the prover
has been accomplished before starting the volumetric calibration. It
is advisable to perform a static leak test prior to performing a water
draw, see Section 5.2. Replace the seals on the prover if there is any
doubt as to their integrity.
2. Block prover inlet and outlet by using a blind flanges or double block
and bleed valves.
3. Refer to Honeywell Enraf water draw configuration, Figure 5-7, and
install Honeywell Enraf available water draw kit, see Figure 5-6. Install
certified thermometers and certified pressure gauge, even if the prover
is equipped with P&T transmitters.
If using Honeywell Enraf Water Draw P&T kit, remove the plug in the
wafer spacer and connect the pressure gauge P1 to the opening (see
Figure 5-7 for reference).
The thermometer used to monitor prover fluid temperature T1 is
supposed to be installed into the spare thermowell located on the
downstream side of the flow tube (see Figure 5-7 for reference).
The thermometer used to monitor switch bar temperature T2 is
supposed to be installed on top of the switch bar close to the center
line between two optical switches (see Figure 5-7 for reference).
The thermometer used to monitor test measure temperature T3
is supposed to be installed on the test measure (see Figure 5-7
for reference).
Have available Table 13 to record data from prover calibration using
volumetric water draw technique.
4. Connect water supply to prover, (refer to Figure 5-7).
5. Make sure that the water draw kit is wired to the customer connection
enclosure as specified in the Figure 5-6.
6. Turn water supply on, and open valves V1, V2, and V3. After all air is
bled off, close V2 and V3. Open V5 valve and allow water to circulate
until the temperature has stabilized and is not changing.
Prover Calibration
Enter Calibration Mode
Run Calibration
Exit Calibration Mode
Enter Average Volume
Abort Calibration
11. Bypass valve (SV2) will be turned ON immediately after entering the
prover calibration mode and the water from the prover will be drained
into the wastewater catch container.
12. Select “Run Calibration” which will cause the prover piston to be
returned to the upstream position and start the draw sequence.
See resulting Prover Status screen as shown below.
After selecting Run Calibration following screen appears.
13. Water should now be draining into the wastewater container until the
flag reaches the first optical (volume) switch. When the first optical
switch is reached, the signal will be sent to the SVP controller to switch
the valves (turn the SV2 valve OFF and turn the SV1 valve ON). At that
time the water will start flowing into the Test Measure.
14. Record the prover pressure (Pp) at P1 while only the water draw
valve is open (SV1). Valves V5 and V6 must be closed while recording
this pressure, which is the pressure at the start and the end of
volume switching.
15. Record temperature (Td) at T2, which is the detector temperature,
by opening the drive cover and placing the thermometer midway
between volume switches, which is the location of the switch bar
temperature transmitter thermowell.
16. Record fluid temperature (Tp) at T1.
17. When the flag reaches the second optical (volume) switch, the draw
valve (SV1) is turned OFF and the bypass valve (SV2) is turned ON.
Carefully record scale reading (SR) and test measure temperature
(Ttm) at T3.
18. After all data is collected, drain the test measure.
19. Repeat steps 12 through 18 as necessary to obtain the required
number of well repeating runs (including one run at 25% flow
rate variance).
Please note that a log will be saved with start time and sweep time
after each calibration run.
20. Once you have completed the calibration, select the “Exit Calibration”
menu which will turn the bypass valve (SV2) OFF.
5.37000
7 8 9 Backspace
4 5 6 Confirm
1 2 3
0 - .
23. After the Average Volume has been entered and confirmed the
following screen is displayed to enter the Repeatability in percent (%).
The entered average volume and the repeatability values will be stored
in the log with a timestamp of the entry.
After selecting Enter Average Volume following screen appears
Enter Repeatability
0.00200 %
7 8 9 Backspace
4 5 6 Confirm
1 2 3
0 - .
Selecting “Abort Calibration” will stop the calibration process. This action
will stop the motor if in running state, bypass value (SV2) will be turned ON
and draw valve (SV1) will be turned OFF. If the Prover is in sweep mode
with the piston moving downstream no action will be taken for upstream
and downstream sensor inputs. Calibration log entry will not be made.
VENT VENT T1 Tp
T2 Td V2 V3 P1 Pp
FLOW
SVP
CONTROLLER
V1 V4
WATER
SUPPLY
Ta
T4
S S
V6 SV1 SV2 V5
Ttm WASTEWATER
CATCH
T3 CONTAINER
TEST MEASURE
Figure 5-7: Water Draw Plumbing Diagram
Report Number:
Location:
Procedure
Water draw notes:
Perform steps 14 – 21 at least twice prior to taking data to purge the
system of air, assure the temperature is stable, and to get familiar with
the procedure.
Repeat water draw procedure until at least 3 consecutive draws repeat
within 0.02% or other repeatability criteria that the certifying parties agree
upon. The flow rate on at least one run must vary by 25% to assure
integrity of prover seals and absence of leakage.
Failure to achieve the necessary repeatability may be caused by leaking
valves, air in the system, varying pressure, leaking seals, or faulty
calibration technique.
1. Be certain that all maintenance that needs to be done to the prover
has been accomplished before starting the gravimetric calibration. It
is advisable to perform a static leak test prior to performing a water
draw, see Section 5.2. Replace the seals on the prover if there is any
doubt as to their integrity.
2. Block prover inlet and outlet by using a blind flanges or double block
and bleed valves.
3. Refer to Honeywell Enraf water draw configuration, Figure 5-7, and
install Honeywell Enraf available water draw kit, see Figure 5-6. Install
certified thermometers and certified pressure gauge, even if the prover
is equipped with P&T transmitters.
If using Honeywell Enraf Water Draw P&T kit, remove the plug in the
wafer spacer and connect the pressure gauge P1 to the opening (see
Figure 5-7 for reference).
The thermometer used to monitor prover fluid temperature T1 is
supposed to be installed into the spare thermowell located on the
downstream side of the flow tube (see Figure 5-7 for reference).
The thermometer used to monitor switch bar temperature T2 is
supposed to be installed on top of the switch bar close to the center
line between two optical switches (see Figure 5-7 for reference).
The thermometer T4 is supposed to be used to monitor ambient
temperature (see Figure 5-7 for reference).
Have available Table 14 to record data from prover calibration using
gravimetric water draw technique.
4. Calibrate the scale as specified in API 4.9.4.
5. Connect water supply to prover, (refer to Figure 5-7)
6. Make sure that the water draw kit is wired to the customer connection
enclosure as specified in the Figure 5-6.
7. Turn water supply on, and open valves V1, V2, V3. After all air is bled
off, close V2 and V3. Open V5 valve and allow water to circulate until
the temperature has stabilized and is not changing.
8. Valve V2 may be opened slightly to allow just a very small stream of
water to flow; this will bleed off air, which may be in the water supply.
9. Calibrate scales with test weights totaling +/- 10% of draw weight per
API 4.9.4.
10. With volume catch container on the scales and under water draw
valve, tare scales.
Prover Calibration
Enter Calibration Mode
Run Calibration
Exit Calibration Mode
Enter Average Volume
Abort Calibration
12. E
nter the prover calibration mode using “Enter Calibration Mode” submenu.
Notification to user after selecting Enter Calibration Mode will show up on the
SVP Controller screen (see below).
Please note that permissive signal from the flow computer will be
ignored while in prover calibration mode.
13. Bypass valve (SV2) will be turned ON immediately after entering the
prover calibration mode and the water from the prover will be drained
into the wastewater catch container.
14. Select “Run Calibration” which will cause the prover piston to be
returned to the upstream position and start the draw sequence.
See resulting Prover Status screen as shown below.
15. Water should now be draining into the wastewater container until
the flag reaches the first optical (volume) switch. Note: To decrease
the time necessary to reach the first volume switch, valve V5 may be
opened until just before the first volume switch has been reached.
16. When the first optical switch is reached, the signal will be sent to the
SVP controller to switch the valves (turn the bypass valve SV2 OFF and
turn the draw valve SV1 ON). At that time the water will start flowing
into the Test Measure.
17. Record the prover pressure (Pp) at P1 while only the water draw valve is
open (SV1). Valves V5 and V6 must be closed while recording this pressure,
which is the pressure at the start and the end of volume switching. Note:
The draw can be sped up by opening valve V6 after the valves have
switched to flowing into the Test Measure located on the scale and the
prover pressure (Pp) is recorded. Again close V6 at least 13mm or 2L
(1/2" or 1/2 gal) prior to solenoid draw valve switching.
18. Record ambient temperature (Ta) at T4.
19. R
ecord temperature (Td) at T2, which is the detector temperature, by
opening the drive cover and placing the thermometer midway between
volume switches, which is the location of the switch bar temperature
transmitter thermowell.
20. Record fluid temperature (Tp) at T1 (at prover).
21. A
llow Test Measure located on the scale to fill until the second volume
switch (downstream sensor) is reached resulting in the draw valve (SV1)
turning OFF and bypass valve (SV2) turning ON. Carefully record scale
reading (Ww).
22. After all data is collected, drain the catch container and tare scales.
23. Repeat steps 14 through 22 as necessary to obtain the required
number of well repeating runs (including one run at 25% flow rate
variance).
Please note that a log will be saved with start time and sweep time
after each calibration run.
24. Once you have completed the calibration, select the “Exit Calibration”
menu which will turn the bypass valve (SV2) OFF.
25. Calculate prover volume per Section 5.5.
26. Please Note: A copy of Table 14 for gravimetric calibration can be
used to enter water draw data. An Excel readable file is available from
Honeywell Enraf which will calculate the corrected prover volume using
the gravimetric method.
After selecting Enter Average Volume following screen appears
5.37000
7 8 9 Backspace
4 5 6 Confirm
1 2 3
0 - .
Enter Repeatability
0.00200 %
7 8 9 Backspace
4 5 6 Confirm
1 2 3
0 - .
Selecting “Abort Calibration” will stop the calibration process. This action
will stop the motor if in running state, bypass value (SV2) will be turned ON
and draw valve (SV1) will be turned OFF. If the Prover is in sweep mode
with the piston moving downstream no action will be taken for upstream
and downstream sensor inputs. Calibration log entry will not be made.
In calibration mode alarms will be generated as per the configuration, and
the run permissive signal from the flow computer or the run prover test
signal will be ignored.
The operating mode of the prover will be saved in NVM so that the mode
will be restored if power is turned off while in Prover Calibration mode.
To exit calibration mode navigate to the Exit Calibration Mode menu and
press OK.
A copy of Table 14 can be used to enter water draw data.
Date:
Prover Serial Number:
Prover Model Number:
Report Number:
Location:
Standard Temperature (Tb):
Standard Pressure (Pb)
Elevation (h)
Field Test Weight Density
Reference Test Weight Density
Compressibility Factor (water) (CPL):
Flow Tube Area Thermal Expansion Coefficient (Ga):
Detector Linear Thermal Expansion Coefficient (Gl):
Modulus of Elasticity of flow tube (E):
Flow Tube Inside Diameter (inches) (ID):
Flow Tube Wall Thickness (inches) (WT):
Fill 1 Fill 2 Fill 3 Fill 4 Fill 5
Fill Time (minutes) =
Temperature Air (Ta) =
Temperature Prover (Tp) =
Temperature Detector (Td) =
Prover Pressure (Pp) =
Water Electrical Conductivity =
Total Mass of Water (Ww) =
Density of Air ( ρA) =
Calculated Density of Water ( ρw) =
Correction of Air Buoyancy of Weighing (CBW) =
Corrected Mass of Water (Mw) =
Volume of Water (Vw) =
Effect of Pressure on Water (CPL) =
Temperature Correction on Prover (CTS) =
Pressure Correction on Prover (CPS) =
Corrected Water Volume (WD) =
Table 24: Gravimetric Water Draw Data Sheet
5.5 Calculations
Volumetric Water Draw Calculations
Given:
RHOtm = Density of liquid (water) in test measure. (API 12.2.4)
RHOp = Density of liquid (water) in prover. (API 12.2.4)
CPL = Correction for the compressibility of liquid. (For water 3.2E-6)
Tb = Base calibration temperature. (60 deg. F. in US)
Ga = Area coefficient of expansion for flow tube. (API 12.2.1.11.2.1)
Gl = Linear coefficient of expansion for detector. (API 12.2.1.11.2.1)
Gc = Coefficient of expansion for the test measure
(from calibration certificate)
E = Modulus of elasticity for flow tube material (from API 12.2 Appendix A)
WT = Thickness of flow tube wall. (inches)
ID = Diameter of flow tube. (inches)
Calculate:
BMVa = Base Measured Volume adjusted for scale reading.
= BMV + SR
CTDW = Correction for prover/test measure liquid temperature difference.
= RHOtm ÷ RHOp
CTStm = Correction for effect of temperature on test measure.
= 1 + (Ttm - 60) × (Gc)
CTSp = Correction for effect of temperature on prover.
= {(1+[(Tp-Tb)*Ga]) * (1+[(Td-Tb)*Gl])}
CCTs = Correction for prover/test measure steel temperature difference
= (CTStm)/(CTSp)
WD = Adjusted Base Volume of Draw
= BMVa*CTDW*CCTs
CPSp = Correction for the effect of pressure on prover
= 1 + [(Pp*ID)/(E*WT)]
Running the prover in the Prover Test operating mode is a good way to
verify proper operation. See Section 4.3 for more information.
This error message means that the proving sequence was not completed
successfully. In order to clear the error check if:
the optical switches are functioning (using the dashboard function –
see 6.3.1),
motor stop switch is functioning (using the dashboard function –
see 6.3.1),
the ramp (located on the guide block) is adjusted properly,
the flag (located on the guide block) is correctly positioned.
This error message means that the signal from the motor stop has not
been sent. To clear the error check if:
motor stop switch is functioning (using the dashboard function –
see 6.3.1),
the ramp (located on the guide block) is adjusted properly,
or any part of the drive mechanism is broken (such as main driving
chain, etc.)
This error message means that one of the sensors is triggered and is
sending the signal to controller at the beginning of the proving run. To clear
the error check if:
theoptical switches are functioning (using the dashboard function –
see 6.3.1),
ensuring that the flag is not triggering one of the optical switches
(if repositioning is required user can use dashboard function – “Motor
run command” to relocate the piston assembly),
motor stop switch is functioning (using the dashboard function –
see 6.3.1),
The prover is due for service as determined by the entry at Main Menu/
Configuration/Alarms/Service Due Reminder.
6.3 Diagnostics
There are several screens inside the Main Menu/Diagnostics menu to aid
in troubleshooting.
6.3.1 Dashboard
The dashboard screen allows you to verify the status of the inputs and
outputs of the SVP Controller. Each output function can be tested by
selecting it and activating it.
Dashboard
Down Sensor High Alarm Output Inactive
Middle Sensor High Alarm Clear High
Up Sensor High
Motor Stop Switch High
Motor Run Inactive
Optical Pulse Inactive
Run Permissive High
Handheld (OK/?)
Bypass Valve Inactive
Draw Valve Inactive
To check if the motor stop switch is working properly you should select
“Motor stop switch” and trigger the motor stop. The state should change
from “High” to “Low”.
To check if the motor is working you should scroll down to the “Motor run
command” and press OK. The state of the motor will be changed from
“Inactive” to “Active”. You will need to press OK again in order to stop
the motor.
The System Health screen allows you to check the status of the various
assemblies that are contained in the SVP Controller. Contact Honeywell
support if there are errors.
The Active Alarms screen allows you to see if any alarms have been
activated and to re-enable the device.
This section contains various electrical schematics and drawings for the
Honeywell Enraf small volume prover. If there are electrical questions not
addressed by these figures contact your nearest Honeywell Enraf
representative or the factory directly.
Shown below are diagrams showing how to connect the SVP Controller
via the Customer Connection Box to various models of flow computers.
Note that the first diagram shows a simplified representation of the
Run Permissive Input and the Volume Pulse Output circuits in the SVP
Controller. The 1500 ohm current limiting resistor shown in the diagrams
is required with operating voltages from 12 to 24 volts DC. For operating
voltages from 6 up to 12 volts, the 1500 ohm resistor must be replaced
with a zero ohm jumper. The resistor and jumper must be connected to the
terminals in the Customer Connection Box.
7.2.1 Omni
The Condat Interface Unit (CIU aka PIU) connects to the SVP controller
using cable (Honeywell PN 44108889). The cable features a connector
that attaches to the CIU at the connector labeled “Control”. The opposite
end of the cable has colored leads for connection in the terminals in the
Customer Connect Box. Please refer to the PROVEit Manuals for further
connection instructions.
Note: The pin numbers listed adjacent to the colors signify the pin
locations on the CIUs “Control” connector.
Within the Customer Connection Box, the terminals 12 and 15 are
provided to securely land customer provided voltage or ground leads
as needed. For the CIU the ground (earth) reference is Black (Customer
Connection Box Terminal 17) and the nominal 15VDC supply is Red
(Customer Connection Box Terminal 12).
While idle, Green (Customer Connection Box Terminal 14) will read nominal
15VDC and White (Customer Connection Box Terminal 16) will read
nominally 5 VDC. When the run command is given, the CIU will drop Green
to ground (earth) and the SVP controller starts the proving run. When either
optical switch is triggered on the downstream pass, the SVP controller will
drop White to 0VDC for 25mS and the CIU will instruct the proving program
to start or stop recording meter pulses. After the run is complete the CIU
will return to idle conditions until the next run command is sent.
7.2.3 Daniels
Actual terminal locations for the Daniel flow computer is dependent upon
the application software being used in the Daniel flow computer. See the
appropriate Daniel manual and software information for more information.
Warning
Due to scan speed, the 2500 has limitations in flow rate when used
with small volume flow provers due to short time period between
volume detectors.
7.2.4 Dynamic
B - Monthly:
1. All items in A.
2. Remove Return Drive Assembly Side Panels. Visually examine return
drive assembly (i.e.: conveyor shaft assemblies with bearings and
pullers/chains, motor and speed reducer, drive end plates and anchor
bolts, guide bars, guide block assembly including optical switch and
ground assembly, switch bar assembly) for any loose fasteners or signs
of adverse wear and/or damage. Repair or replace any suspect items.
3. Visually inspect all electrical cabling for signs of wear or damage.
C – Semi-Annually:
1. All items in B.
2. Remove upstream and downstream bleed manifolds. Insert boroscope
with flashlight attachment into both upstream and downstream vent
flanges. Visually inspect both upstream and downstream piston seals for
and signs of damage or wear. Inspect poppet valve seal for any signs
of damage or wear. Inspect flow tube calibrated surface for damage to
chrome plating. Repair or replace any suspect items.
3. Verify prover anchor bolts are tight.
This maintenance section covers most of the routine maintenance
procedures to be performed on your prover. Trouble shooting information
is contained in Section 6 while wiring diagrams and schematics common
to all Honeywell Enraf small volume models are found in Section 7.
Please contact the Honeywell Enraf factory for information on problems or
repairs not covered by Honeywell Enraf small volume Operation Manual.
53002
HOLE FOR LIFTING (1X OR 3X)
53001
53003
53109
53110
53108
53101
53107
1 2 4 5
Figure 8-3: Guide Block Assembly
6. Remove the guide block Figure 8-3 position 2 and the mechanical
stop Figure 8-3 position 4 with the rubber bumper Figure 8-3 position
5 from the upstream piston shaft.
7. Remove the upstream seal retainer assembly, Figure 8-7 #52101, from
the upstream flange by first removing the shock absorbers, Figure 8-7
#52108, and then removing the hex socket cap screws, Figure 8-7
#52107 holding the seal retainer to the end flange. Then remove the
upstream seal retainer assembly.
8. With sufficient personnel and/or a hoist or crane at the downstream
end of the prover, lift the piston assembly and pull it out of the flow
tube, see Figure 8-4. Be extremely careful to remove the piston
assembly in such a manner to not cause damage to the piston or to
the precision bore flow tube. Note: Lift the piston assembly with a
nylon strap wrapped through piston support to prevent damage or
injury. NEVER lift the piston assembly with the strap positioned far
away from the piston support, Figure 8-5 #54002.
9. For piston disassembly on most models, use procedure 9a, for older
models, use 9b.
9a. Referring to Figure 8-5, disassemble the piston, by first removing
the downstream shaft #54005 from the poppet valve #54003. Then
remove the piston support #54002 from the piston body by placing
the piston body #54001 face down on a clean surface and hold
pressure to keep the spring #54009 compressed and removing the
#54020 hex head cap screws. The poppet assembly may now be
removed from the piston body. Remove poppet seal #54014 from
piston body #54001. Remove the main piston seals #54013 and
riders #54008 very carefully so as not to damage the seal surfaces on
the piston.
54018 54003
54010 4X(SEE DETAIL A)
54006
54017
54005 54009 54002
54021
54013
54020
54008
54001 54018 54021
54013 54011
54014
54011
pipe over the threaded rod will prevent the threads from hanging up
in the upstream flange. Install a large flat washer and a nut on to the
threaded rod and pull the piston into the flow tube while wiggling the
downstream shaft to be certain of correct alignment with the seals and
the flow tube bore.
Figure 8-6: P
iston Insertion into Flow Tube – Pulling Method
Notes: R
efer to Table 16 for bolt torque values for assembling flow prover.
Upstream flange to flow tube seal does not usually need replacement during normal
maintenance, nor is it necessary to remove upstream flange, Figure 8-7 #52201.
15. Put a new o-ring seal, Figure 8-1 #53002, onto downstream end
flange, Figure 8-1 #53001, carefully re-install flange into flow tube.
Re-install hex socket bolts, Figure 8-1 #53003, securing the
downstream end flange, Figure 8-1 #53001, to the flow tube. Snug
bolts evenly, using a cross pattern, so as to not damage the seal or
distort the flange.
Refer to Table 16 for bolt torque specifications, and carefully tighten
bolts evenly, using a cross pattern, and moving in increments to the full
torque value.
16. With downstream seal retainer assembled to the downstream
stop (refer to Section 8.4 steps 11 & 12), finish re-assembly of the
downstream side of the prover using the reverse of the procedure
from # 1 through # 4 making sure that critical bolts are tightend as per
torque specification, see Table 16.
1. Make sure that the steps from 2 thru 4 mentioned in the Section 8.4
and the steps from 5 thru 7 mentioned in the Section 8.5 are
fully completed.
2. Remove the retaining rings, seals and washers from the upstream seal
retainer, Figure 8-7 #52101.
3. Clean and inspect seal retainer.
4. Check seal surfaces for scratches and a surface finish of 12rms. If
necessary, polish the seal surfaces.
5. Carefully install new seals and washers in proper orientation (see
Figure 8-7 for correct installation). Note the direction of the seal lips for
correct installation of the new seals. In a case of cracked or broken
washers they need to be replaced when new seals are installed.
6. Install the upstream seal retainer, Figure 8-7 #52101, in the upstream
flange, Figure 8-7 #52201.
7. Re-install hex socket bolts, Figure 8-7 #52107 in order to secure
the upstream seal retainer to the upstream end flange. Snug bolts
evenly, using a cross pattern, so as to not damage the seal or distort
the flange.
Refer to Table 16 for bolt torque specifications, and carefully tighten
bolts evenly, using a cross pattern, and moving in increments to the full
torque value.
8. Re-install the shock absorbers, Figure 8-7 #52108. Make sure to
adjust the setting on all four shock absorbers at the same setting
number (see instructions in Section 8.8.10).
9. Install the mechanical stop, Figure 8-3 position 4 with the rubber
bumper, Figure 8-3 position 5 on the upstream piston shaft. Note: It is
recommended to replace existing rubber bumper with the new one at
this time. Make sure to clean the surface on the mechanical stop prior
to gluing the rubber bumper to it. Use Loctite 422 or equivalent.
10. Carefully slide the guide block, Figure 8-3 position 2 over the threads
of the dimple stud and secure it using the washer, standard hexagonal
nut and locking nut, Figure 8-3 position 1. Note: Make sure to clean
the threads on the dimple stud and be careful not to damage the
optic switches.
Prover Model Item# Item# Item# Item# Item# Item# Item# Item#
Number 52206 52107 53003 53107 53110 54018 54020 See Note 1
05X3C 163 Nm 203 Nm 163 Nm 203 Nm 9 Nm 9 Nm 26 Nm 203 Nm
15X1A 163 Nm 203 Nm 163 Nm 203 Nm 9 Nm 9 Nm 61 Nm 203 Nm
15X2B 163 Nm 203 Nm 163 Nm 203 Nm 9 Nm 9 Nm 61 Nm 203 Nm
25X1A 163 Nm 203 Nm 163 Nm 203 Nm 9 Nm 9 Nm 61 Nm 203 Nm
25X2B 163 Nm 203 Nm 163 Nm 203 Nm 9 Nm 9 Nm 61 Nm 203 Nm
25X3C 678 Nm 203 Nm 678 Nm 203 Nm 9 Nm 9 Nm 61 Nm 203 Nm
25X4 and 5 678 Nm 203 Nm 678 Nm 203 Nm 9 Nm 9 Nm 61 Nm 203 Nm
35X1 thru 5 678 Nm 203 Nm 678 Nm 203 Nm 9 Nm 9 Nm 61 Nm 203 Nm
50X1A 230 Nm 203 Nm 230 Nm 203 Nm 15 Nm 15 Nm 230 Nm 340 Nm
50X2B 230 Nm 203 Nm 230 Nm 203 Nm 15 Nm 15 Nm 230 Nm 340 Nm
50X3 thru 5 1630 Nm 203 Nm 1630 Nm 203 Nm 15 Nm 15 Nm 230 Nm 340 Nm
85X1A 400 Nm 203 Nm 400 Nm 203 Nm 9 Nm 15 Nm 230 Nm 340 Nm
85X2B 400 Nm 203 Nm 400 Nm 203 Nm 9 Nm 15 Nm 230 Nm 340 Nm
85X3C 1630 Nm 203 Nm 1630 Nm 203 Nm 9 Nm 15 Nm 230 Nm 340 Nm
85X4D 1900 Nm 203 Nm 1900 Nm 203 Nm 9 Nm 15 Nm 230 Nm 340 Nm
120X1A 678 Nm 203 Nm 678 Nm 203 Nm 15 Nm 15 Nm 230 Nm 340 Nm
120X2B 678 Nm 203 Nm 678 Nm 203 Nm 15 Nm 15 Nm 230 Nm 340 Nm
120X3C 1630 Nm 203 Nm 1630 Nm 203 Nm 15 Nm 15 Nm 230 Nm 340 Nm
Table 26: Bolt Torque Specifications
Note 1: Hexagonal standard nut, Figure 8-3 position1, holding guide block, Figure 8-3 position 2, to upstream shaft.
5 4.0 Nm 35 lbf•in 5
15 15
11 Nm 95 lbf•in
25 25
1.1 Nm 2.2 Nm 3.6 Nm
35 28 Nm 250 lbf•in 35
9.6 lbf•in 19.8 lbf•in 31.7 lbf•in
50 28 Nm 250 lbf•in 73 Nm 650 lbf•in 50
85 73 Nm 650 lbf•in 85
Warning
Do not lubricate chains with normal oils which collect dirt and cause wear.
c. Check to see if all six pins have been installed Figure 8-10.
d. When checking alignment, loosen bolt on end of guide bar and use a
wrench to check that the guide bar is tight to the flange Figure 8-11.
WRENCH FLATS
e. Check the ground spring to ensure it is in contact with the ground bar.
In the case of larger provers, check that the ground cable is connected
to both the ground strap and frame Figure 8-12
c. Check that the Dimple Stud is straight and square in all direction to the
end of the piston.
are should be taken to ensure that the hole in the guide block aligns
C
with the Dimple stud in the piston shaft. If the hole does not align with
the stud, adjust shims accordingly. Slide the guide block upstream and
check the side play. If side play is too tight upstream, you will have to
readjust shims, remembering that the guide block MUST always align
with the Dimple stud in the downstream position see Figure 8-14
f. Use a wrench on the hub of the large drive sprocket and move the
piston to the position that you want. Remove nut, slide guide block off
the Dimple stud, and check alignment with the guide block.
g. The hole in the guide block should be aligned side to side with the
Dimple stud and the shaft should have .8 to 1.6mm (1/32 to 1/16") sag
when upstream see Figure 8-14.
h. If the Dimple stud is not aligned properly, adjust the upstream plate by
loosening the respective bolts and removing the M6 (1/4") spring pins
used to maintain alignment. Once you remove the alignment pins you
must drill and tap new holes, after all adjustments have been made
see Section 8.8.9. Adjust the upstream drive end plate so that the side
of the plate is perpendicular to the frame. Tighten all the bolts, and
check the alignment again.
i. To avoid a twist on the drive system, squareness between the two
plates in the drive end must be maintained.
Figure 8-15: Correctly Seated Optical Switch Bottom and Side View
b. Position the flag with the guide block in the opening of the downstream
optical switch and check the alignment. The flag should be centered as
showed in the Figure 8-16. This can be observed through the hole in
the upstream drive end plate or using a mirror positioned close to the
optical switch.
1/4-20 BOLT
THREADED ROD
SWITCH BAR
SHIM
PLATE
PROPERLY
CENTERED FLAG
e. If adjusting the flag does not provide centering of the flag on both
switches, the switch bar may not be aligned with the piston assembly.
a. First confirm that the guide block is aligned with the piston shaft see
Section 8.8.3.
b. Use a pipe clamp and pull the switch bar, if possible, in the direction
needed being careful not to affect other adjustments. You may have
to move both ends see Figure 8-17.
c. The drag should be the same at both cam followers (see Figure 8-18).
If the drag is not the same, adjust pillow blocks to get the correct
clearance of the cam followers (see Figure 8-19).
d. When you are making the above adjustments you need to check the
chain to be sure that it does not climb on the side of the sprocket as
the puller approaches the sprockets. If this occurs, adjust the sprockets
to eliminate the problem. Sprocket adjustment must be checked both
downstream and upstream.
If the sprockets are loosened or are loose from the shaft they must be
fastened with #290 Green Loctite after all adjustments have been made
(see Figure 8-20).
e. On models where the sprocket shafts are not set at a fixed distance
(S05, S15, S25) the chain must have 19mm (¾") play, checked at the
bottom. Any adjustments made for this purpose should be done with
the downstream pillow blocks, as this will not affect the adjustment
of the puller (see the next section, UHMW Chain Rail Adjustment, for
more details).
c. Loctite the adjustment bolts with #242 Blue Loctite. If the adjustment
blocks are missing install new ones as needed.
b. If you push down on the shock and it bottoms out check the
adjustment. Almost all of the shocks are adjustable. All shocks must
be on the same setting.
c. If after adjusting and retesting the shock it still does not perform
correctly, the shock needs replacement.
d. The shocks depth must also be adjusted on the prover itself see Figure
8-23. This insertion depth must be correct and the same on all four shocks.
Figure 8-26, Figure 8-27, and Figure 8-28 below show an improper
installation. To maintain correct installation, the optical switch must be
pushed tightly to the inner corner of the L-bracket and must be seated
entirely in the machined pocket of the switch bar. Finally, before installing
any optical switches, be sure that the machined pockets of the switch bar
and inner faces of the L-brackets are free of any debris.
Figure 8-26: Improper Optical Figure 8-27: Improper Optical Figure 8-28: Improper Optical
Switch Installation Side View Switch Installation Bottom View 1 Switch Installation Bottom View 2
8.12 F
requently asked questions.
What type of prover is the Honeywell Enraf? The Honeywell Enraf prover is classified as a Small Volume
Unidirectional Piston Displacement Prover.
Why is the Honeywell Enraf prover considered to be The small volume classification is based on the volume displaced
small volume when it can hold up to 350 gallons in relationship to the number of flow meter pulses collected. A
of fluid? large volume prover requires greater than 10,000 meter pulses
be collected to generate a meter factor (typically a pipe prover). A
small volume prover in conjunction with ‘Double chronometry’ can
generate a meter factor in less than 10,000 meter pulses.
How can the Honeywell Enraf flow prover be used on By slowing the prover down to allow for longer run up time, the
Corriolis and UltraSonic meters? flow disturbance caused by the internal valve closure will have had
enough time to stabilize and generate accurate repeatable readings.
What is ‘Run up time’? The run up time is the time it takes from the release of the piston to
reach the start measurement switch. (1st Optical Switch)
Why is the upstream and downstream volume The Honeywell Enraf flow Prover has a piston shaft on both sides
the same? of piston body therefore the displaced volume is the same.
How does the flow prover measure volume pulses? The Honeywell Enraf prover does not measure anything. It is a very
accurate, but simple instrument that waits for a start signal from
the flow computer and sends back the pulses as it passes the
volume switches.
Can the fluid flow through the prover all the time? Yes, many Honeywell Enraf provers are installed in “Standby
Mode”, but it is recommended to consider the more durable
elastomer option when operating a prover in this way. This is the
best practice for fluids that are at temperatures higher or lower
than ambient continuous to allow for faster warm up time.
How much pressure drop does the Honeywell Enraf Under normal operating conditions the prover will generate 28 - 69
Flow Prover Have? kPa (4 – 10 psi) pressure drop at maximum flow rate. This is based
on water and is applicable to refined products such as diesel,
jet, gasoline, etc. Products such as heavy crude oil can generate
pressure drops of up to 20psi in some cases.
What motor sizes are used on Honeywell It depends on the prover model but in general an 05 uses
Enraf provers? 0.5hp/.35kW electric motor; 15, 25, 35, & 50 use a 1hp/.75kW
electric motor; 85 uses a 2hp/1.5kW electric motor; 120 uses
5hp/3.7kW electric motor.
What are the installation considerations for a Correct installation of the Honeywell Enraf prover is vital to a long
Honeywell Enraf prover? and trouble-free operation. Critical elements include suitable
foundations, pipe stress and load analysis on provers inlet and
outlet ports, adequate upstream filtration and thermal pressure
relief. If you have any questions, please consult the factory.
How is the installed base of Honeywell Enraf Honeywell Global Technical Support (GTS) is the focal point for
provers supported? all Honeywell Enraf related after-sales support questions and
GTS is supported by a network of Honeywell service centers and
strategically positioned service partners.
How can I receive information and support for the Contact your local sales specialist. There is a Honeywell Enraf
Honeywell Enraf prover? specialist located in each global region (Americas, Asia Pacific and
Europe Middle-East & Africa - EMEA).
Table 28: Frequently Asked Questions.