Emesb-Msa-Mtn-002 MTN CLM R1
Emesb-Msa-Mtn-002 MTN CLM R1
Emesb-Msa-Mtn-002 MTN CLM R1
: EMESB-MSA-MTN-002
EPIC MUSHTARI ENGINEERING DATE : 28 MARCH 2018
SDN BHD REV. : 0
PAGE : 01 OF 02
(COLUMN)
CLIENT PETRONAS
TENDER TITLE MASTER SERVICE AGREEMENT (MSA) FOR TURNAROUND (TA) AND DAILY MAINTENANCE WORK FOR
MAIN MECHANICAL WORKS
TENDER NO. CTC/HC-GP/2017/131
DOC NO. : EMESB-MSA-MTN-002
EPIC MUSHTARI ENGINEERING DATE : 28 MARCH 2018
SDN BHD REV. : 0
PAGE : 02 OF 02
TABLE OF CONTENTS
ITEM DESCRIPTION
PROJECT MASTER SERVICE AGREEMENT (MSA) FOR TURNAROUND (TA) AND DAILY MAINTENANCE WORK FOR DOC. NO. EMESB-MSA-MTN-002
PAGE NO. 01 OF 03
EPIC MUSHTARI ENGINEERING SDN BHD
(COLUMN)
INSPECTION PARTY
NO QUALITY RELATED ACTIVITY SPECIFICATION/ REFERENCE REPORTING EVIDENCE CONTROL PROCEDURE/ DOCUMENTS REMARK
EMESB 3RD. PARTY PETRONAS
1.2 APPROVAL OF WORK PROCEDURE ASME / API / PTS WORK PROCEDURE, JMS, WCS & EJIS P N/A R
1.3 APPROVAL OF QC PROCEDURE ASME / API / PTS WPS, WQT, QC & NDT PROCEDURE P N/A R
2.1 SITE VERIFICATION SITE SURVEY REPORT (SSR) AFC & LAY OUT DRAWING W N/A R
2.2 VERIFY LOCATION FOR REPAIR/MODIFICATION INSPECTION REPORT & SSR AFC & LAY OUT DRAWING W N/A R
2.3 VERIFY SPARE PART FOR REPLACEMENT INSPECTION REPORT & SSR AFC & LAY OUT DRAWING W N/A R
3.2 REVIEW MATERIAL CERTIFICATES ASME IX, ASME II MILL CERTIFICATE / DO W N/A R
5.1 EQUIPMENT BLINDING & ISOLATION APPROVED JMS, WCS & EJIS H N/A W
5.4 PRE-INSPECTION ASME / API / PTS PRE-INSPECTION REPORT APPROVED JMS & WCS W N/A R
01 OF 03
CLIENT PETRONAS PREPARED BY MOHD FIRDAUS
PROJECT MASTER SERVICE AGREEMENT (MSA) FOR TURNAROUND (TA) AND DAILY MAINTENANCE WORK FOR DOC. NO. EMESB-MSA-MTN-002
PAGE NO. 02 OF 03
EPIC MUSHTARI ENGINEERING SDN BHD
(COLUMN)
INSPECTION PARTY
NO QUALITY RELATED ACTIVITY SPECIFICATION/ REFERENCE REPORTING EVIDENCE CONTROL PROCEDURE/ DOCUMENTS REMARK
EMESB 3RD. PARTY PETRONAS
6.1.1 MANUAL / POWER TOOL BRUSHING * APPROVED JMS & WCS W N/A M * IF APPLICABLE
6.1.2 SHOT JET CLEANER * APPROVED JMS & WCS W N/A M * IF APPLICABLE
6.1.3 HP WATER JET / HYDROLANCING APPROVED JMS & WCS W N/A M * IF APPLICABLE
7.2 PERFORM REPAIR WORK WPS, WQT CERTIFICATE, JMS & WCS W N/A W
8.0 SPARE PART REPLACEMENT ASME / API / PTS CHECKLIST MANUFACTURER DATA REPORT (MDR) W N/A W
9.1 PNEUMATIC LEAK TEST LEAK TEST REPORT PNEUMATIC LEAK TEST PROCEDURE H N/A H
02 OF 03
CLIENT PETRONAS PREPARED BY MOHD FIRDAUS
PROJECT MASTER SERVICE AGREEMENT (MSA) FOR TURNAROUND (TA) AND DAILY MAINTENANCE WORK FOR DOC. NO. EMESB-MSA-MTN-002
PAGE NO. 03 OF 03
EPIC MUSHTARI ENGINEERING SDN BHD
(COLUMN)
INSPECTION PARTY
NO QUALITY RELATED ACTIVITY SPECIFICATION/ REFERENCE REPORTING EVIDENCE CONTROL PROCEDURE/ DOCUMENTS REMARK
EMESB 3RD. PARTY PETRONAS
10.2 BUBLE CAP TIGHTENING CHECK CHECKLIST APPROVED JMS & WCS W N/A M
10.3 RE-INSTALL ALL NOZZLE & MANWAY FLANGES CHECKLIST APPROVED JMS & WCS W N/A M
11.0 FINAL MECHANICAL COMPLETION INSPECTION ASME / TEMA / PTS CHECKLIST & BOX UP CERTIFICATE H N/A W
P PREPARE Documentation to be prepared for review and approval prior work commence
H HOLD POINT Hold point indicate mandotary compliance in any area of inspection that requires inspection.
W WITNESS POINT Inspection activity that require EMESB inspection personnel full attendance and endorsement before proceeding to the next activities.
M MONITORING Identified surveilance of work activity in the manufacturing process on random basis of which the production shall continue without interruption.
R REVIEW OF DOCUMENTS Review and acceptance of documents, reports, radiography film, charts etc.
03 OF 03
WORK CONTROL SHEET (WCS)
COLUMN
EQUIPMENT TAG : C-204 EQUIPMENT NAME : PROPYLENE PROPANE SPLITTER
PERFORMED BY VERIFIED BY
NO. JOB STAGE APPLICABLE SUPPORTING DOCUMENT
NAME DATE SIGN NAME DATE SIGN
1 ISOLATION / BLINDING / LOTO COMPLETED AS PER EJIS EJIS / LOTO TAGGING
2 MANHOLE OPENING & LEL CHECK
3 CSE PREPARATION & ENTRANCE
4 PRE-INSPECTION PRE-INSPECTION REPORT
5 TRAYS REMOVAL
6 PERFORM MECHANICAL AND / OR CHEMICAL CLEANING
7 INSPECTION UPON COMPLETION OF CLEANING WORK VISUAL & NDT INSPECTION REPORT
8 PERFORM REPAIR WORK (IF REQUIRED)
9 INSPECTION UPON COMPLETION OF REPAIR WORK VISUAL & NDT INSPECTION REPORT
10 REPLACE DAMAGED SPARE PART MANUFACTURER DATA REPORT & CHECKLIST
11 PRESSURE TEST PRESSURE TEST REPORT
12 REINSTATEMENT WORK
13 DE-ISOLATION / DE-BLINDING / REMOVE LOTO AS PER EJIS EJIS / LOTO TAGGING
14 FINAL MECHANICAL INSPECTION & COMPLETION BOX UP CERTIFICATE
DEFECT WORK DETAILS ACTUAL MANHOURS ACTUAL EQUIPMENT EMESB (INITIAL) PETRONAS (INITIAL)
1
2
3
4
FINAL ACCEPTANCE
WORK COMPLETION REMARKS : WORK COMPLETION ACCEPTANCE :
EMESB INSPECTION 3RD. PARTY INSPECTION PETRONAS INSPECTION
PETRONAS TURNAROUND
WORK ID A2103 UNIT 200 AREA 200 TECHNICAL DATA DIMENSION ELEVATION AND WEIGHT
EQUIP. NO C-204 PLANT MTBE P&ID NO. 64-D-8021 APPL. CODE ASME SEC. VIII DIV.1 1989 ED. MAIN DIMENSION ( iD x TL ) (mm) 2150 X 14630 / 1200 X 4180 F-T
EQUIP. NAME PROPYLENE PROPANE SPLITTER SERVICE COLUMN INTERNAL TYPE NA ELEVATION FRM PLATFORM (mm)YES
JOB DESC. OPEN,CLEAN & DOSH INSPECTION. SHELL SA-240 TP-304 FRM GROUND (mm) NA
MATERIAL INTERNAL NA POSITION VERTICAL
INST/ELEC
OPN/TSD
CRANE
RG/SF
INSP.
INSL
PTW
DUR
MH
NO ACTIVITY DESCRIPTION REMARKS INSULATION 200mm DEMISTER PAD YES
FT
HJ
D
DESIGN /OPR PRESS KPA (G) GENERAL PACKING NA
PRE-SHUTDOWN WORK DESIGN /OPR TEMP ( DEG C ) TRAY NA
1 ERECT EXTERNAL SCAFFOLDING ACTIVITY PRIOR TO MANHOLE OPENING 4 4 16 1
TESTING DATA
SHUTDOWN WORK SHELL PRESS.
2 ISOLATE / BLINDING / LOTO ACTIVITY AS PER EJIS 1 1 2 1 4 1 TESTING MEDIUM
3 OPENING MANHOLE 3 2 1
4 CSE PREPARATION 2 3 3 15 1 WORKING DATA
5 FIRST ENTRY ACTIVITY AND LEL CHECK 2 1.5 3 1 EXT. SCAFF. VOL ( M3 ) YES BOLT TENSIONING YES
6 CSE ENTRY FOR PRE-INSPECTION 1 2 3 9 1 INT. SCAFF. VOL ( M3 ) YES HOT BOLTING YES
7 ERECTION OF INTERNAL SCAFFOLDING 4 0.5 INSULATION MANHOLE ( # x SIZE ) YES VENTILATOR YES
8 PRE-INSPECTION 1 2 5 1 REMOVAL/ NOZZLE ( Dia - inch ) YES LIGHTING YES
9 TRAY REMOVAL 2 3 0.5 2.5 REFIT OPEN MANWAY TRAY YES
10 MECHANICAL / CHEMICAL CLEANING 2 2 10 40 1 OPEN / CLOSE
11 INSPECTION 1 2 1 3 1
12 CONTIGENCY FOR REPAIR (IF ANY) 2 1 2 4 16 1
13 INSPECTION ACTIVITY FOR REPAIR WORK (IF ANY) 1 1 1 3 9 1
14 REPLACE DAMAGE SPARE PARTS 2 2 2 8 1 OPEN / MANHOLE ( # x SIZE ) YES CLEANING METHOD WATERJET / POWER BRUSH
15 PRESSURE TEST 1 2 2 6 1 CLOSE HANDHOLE ( # x SIZE ) YES INSPECTION METHOD VISUAL / DPI / RT /UT
16 REMOVE INTERNAL SCAFFOLDING 4 0.5 2 1
17 REINSTATEMENT WORK 2 3
18 DE-ISOLATION / DE-BLINDING / REMOVE LOTO AS PER EJIS 2
19 FINAL INSPECTION & BOX UP 1 1 1 2
PTW = Permit to Work CSE = Confine Space Entry CW = Cold Work HW = Hot Work LFT = Lifting EIC - Electrical Isolation Certificate