Daily Construction Report Rev2

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 7

REPORT

DAILY CONSTRUCTION STATUS REPORT No Date


CAVITE-LAGUNA EXPRESSWAY PROJECT (Cavite Segment) 30-Dec-99

1. Contract Details
Owner MPCala Holdings Inc. Principal Contractor E.C. de Luna Construction Construction Manager (ECDLCC) Antonio P. Aguilar
Corp.
Designer DCCD Engineering Corporatio Grantor DPWH NTP 24-Aug-20

Independent Consultant UTCP/FDSC Client Representative Danilo R. Ignacio Finish Date 30-Dec-99

2. Manpower 3. Other Details

Designation No No of Hours Weather Legend:


Fair
15
Project Manager Date
Road Manager Shower
1
Field Engineer Night
Time Cloudy
Material Engineer Work Shift NORMAL OT
Safety Officer
Surveyor Working Hours 8:00AM - Day Rain/
Time Storm
Survey Aides 5:00PM -
HE Operators
Mason/Carpenter
Steelman
Welder
Mechanics/Electricians 4. Materials Testing and Quality Control Activities
Dump Truck Driver 1 None
Plant Clerk 2
Labor 3
Utility
Service Driver
Security Guard 5. Special Events/ Delay & Downtime
Office Staff & Support 1 None
2
Total Manpower 3

6. Description of Work Performed

Stations
Pay Item Description Location Length (m) Area (m²) Volume (m³) Remarks
From To

TOTAL 0.00

7. Equipment 8. Environment, Health and Safety

Equipment Description Active Idle Total Remarks 1

1 Crushing/Screening Plants 150 t/hr 0 0 2

2 Screening/Washing Plant 150 t/hr 0 0 3

3 Concrete Batch Plant 60 cu. m/hr 0 0 4

4 Asphalt Batching Plant 120 t/hr 5

5 Bulldozer Crawler 302 hp

6 Motor Grader 155 hp-195 hp

7 Crawler Backhoe

8 Wheel-type Backhoe 9. Site Issues and Concerns


9 Vibratory Roller 1

10 Concrete Paver 2

11 Concrete Vibratory 3

12 Payloader 4

13 Plate Compactor 5

14 Dump Truck
15 Fuel Truck

16 Water Truck

17 Welding Machine

18 Tower Light

19 Generator Set
20 Service Vehicle

Total

F-CON-002a Rev 2 Dec 12, 2020 Page 1 of 7


REPORT
DAILY CONSTRUCTION STATUS REPORT No Date
CAVITE-LAGUNA EXPRESSWAY PROJECT (Cavite Segment) 30-Dec-99

10. Site Photos

Consolidated by: Checked by: Noted By:


Office Engineer Quantity Engineer Project Manager MPCala

F-CON-002a Rev 2 Dec 12, 2020 Page 2 of 7


REPORT
DAILY CONSTRUCTION STATUS REPORT No Date
CAVITE-LAGUNA EXPRESSWAY PROJECT (Cavite Segment) 30-Dec-99

F-CON-002a Rev 2 Dec 12, 2020 Page 3 of 7


CONTRACT STATUS REPORT - Err:508

CAVITE-LAGUNA EXPRESSWAY PROJECT (Cavite Segment) Page 1 of 2

1. Contract Details
Design Manager: DPWH Package Manager: UTCP/FDSC Design Consultant: E.C. de Luna
Construction Corp.
Contract Admin: Antonio P. Aguilar Finish Date $0
Project Controls: Danilo R. Ignacio 0 $0 Sub-Contrator:
2. Key Dates Contract Target Wks Achieved 3. Possession Status
### #REF! #REF! #REF! #REF! #REF! ###
### #REF! #REF! #REF! #REF! #REF!
### #REF! #REF! #REF! #REF! #REF! ###
### #REF! #REF! #REF! #REF! #REF! ###
### #REF! #REF! #REF! #REF! #REF! ###
### #REF! #REF! #REF! #REF! #REF! ###
### #REF! #REF! #REF! #REF! #REF! ###
4. Significant Events 5. Trend/Change Control Status
####REF! Trends raised this week: 2

####REF! Overall Trend Status (Post Period 5):

####REF! Raised to date: 13

####REF! Approved: 11

####REF! Pending: 2

6. Key Quantity Tracking

Yards/No. Series1 Series2 Series3 Resource


1.2

0.8

0.6

0.4

0.2

0
1

6a. Key Quantity Tracking Charts

Signalling - Signalling - Signalling - Signalling - Signalling - Signalling -


Move Signals Reprofile Co-Acting Signal Veg' Claerance TPWS OSS AWS

Signalling - Signalling - Signalling - Signalling - Signalling -


TPWS TSS AWI Magnet Data mods Banner Repeaters IBJ Move

Ver. 02a
CONTRACT STATUS REPORT - Week ?

CAVITE-LAGUNA EXPRESSWAY PROJECT (Cavite Segment) Page 2 of 2

7. AFC by Resource Code

Signalling - New Signals


Signalling - Move Signals

Note: AFC Period 8 £2,665,161


AFC includes Birse Structure and Murphys AFC Period 7 £2,665,161 Difference £0.00

8. WIP Current Week


Scope Poss'
Ref. No.
Total Description Location Qty

#REF! #REF! #REF! #REF!


#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!

Look Forward - Next Week


Scope Poss'
Ref. No.
Total Description Location Qty

#REF! #REF! #REF! #REF!


#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!

11. CIAR
Prev' Wks
Item Description Reference
Late
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!

12. Actions
Description Action By
#REF! #REF! #REF!
#REF! #REF! #REF!
#REF! #REF! #REF!
#REF! #REF! #REF!
#REF! #REF! #REF!
Ver. 02a
#REF! #REF! #REF!
#REF! #REF! #REF!

Ver. 02a
Click here for
Instructions & Menu

You might also like