Daily Construction Report Rev2
Daily Construction Report Rev2
Daily Construction Report Rev2
1. Contract Details
Owner MPCala Holdings Inc. Principal Contractor E.C. de Luna Construction Construction Manager (ECDLCC) Antonio P. Aguilar
Corp.
Designer DCCD Engineering Corporatio Grantor DPWH NTP 24-Aug-20
Independent Consultant UTCP/FDSC Client Representative Danilo R. Ignacio Finish Date 30-Dec-99
Stations
Pay Item Description Location Length (m) Area (m²) Volume (m³) Remarks
From To
TOTAL 0.00
7 Crawler Backhoe
10 Concrete Paver 2
11 Concrete Vibratory 3
12 Payloader 4
13 Plate Compactor 5
14 Dump Truck
15 Fuel Truck
16 Water Truck
17 Welding Machine
18 Tower Light
19 Generator Set
20 Service Vehicle
Total
1. Contract Details
Design Manager: DPWH Package Manager: UTCP/FDSC Design Consultant: E.C. de Luna
Construction Corp.
Contract Admin: Antonio P. Aguilar Finish Date $0
Project Controls: Danilo R. Ignacio 0 $0 Sub-Contrator:
2. Key Dates Contract Target Wks Achieved 3. Possession Status
### #REF! #REF! #REF! #REF! #REF! ###
### #REF! #REF! #REF! #REF! #REF!
### #REF! #REF! #REF! #REF! #REF! ###
### #REF! #REF! #REF! #REF! #REF! ###
### #REF! #REF! #REF! #REF! #REF! ###
### #REF! #REF! #REF! #REF! #REF! ###
### #REF! #REF! #REF! #REF! #REF! ###
4. Significant Events 5. Trend/Change Control Status
####REF! Trends raised this week: 2
####REF! Approved: 11
####REF! Pending: 2
0.8
0.6
0.4
0.2
0
1
Ver. 02a
CONTRACT STATUS REPORT - Week ?
11. CIAR
Prev' Wks
Item Description Reference
Late
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
12. Actions
Description Action By
#REF! #REF! #REF!
#REF! #REF! #REF!
#REF! #REF! #REF!
#REF! #REF! #REF!
#REF! #REF! #REF!
Ver. 02a
#REF! #REF! #REF!
#REF! #REF! #REF!
Ver. 02a
Click here for
Instructions & Menu