Project Management Presentation FRAMEWORK - New
Project Management Presentation FRAMEWORK - New
Project Management Presentation FRAMEWORK - New
Introduction
PMI & PMP
• Introduction
• Project Life Cycle and Organization
• Project Management Process for a Project
INTRODUCTION- PMBOK GUIDE-1
• A project:
• Has a unique purpose
• Is temporary
• Is developed using progressive elaboration
PROJECT ATTRIBUTES 2
Progressive Elaboration
•
Continuously improving and detailing a plan as
more detailed and specific information and
more accurate estimates become available as
the project progresses,
•
PROJECT MANAGEMENT KNOWLEDGE AREAS
• Project Management
• Program Management
• Portfolio Management
Portfolio
PMO
Projects & Operation
WHAT IS A PROGRAM?
A program is:
• “a group of related projects managed in a
coordinated way to obtain benefits and control not
available from managing them individually.”
•
• ADVANTAGES
• Decreased risk
• Economies of Scale
PORTFOLIOS AND PORTFOLIO MANAGEMENT
• Project Expediter
• acts primarily as a staff assistant
• as communications coordinator.
• cannot personally make or enforce
decisions.
• Project Coordinator
• has some power to make decisions
• Has some authority
• reports to a higher-level manager
STAKEHOLDERS
• Refer to both internal & external environmental factors that surround or influence a project’s success
• As an input in almost all project management process
• May enhance or constrain project management options
• May have positive or negative influence on the outcome
• Examples:
Projectized
• Entire company is organized
by projects
• Personnel are assigned and
report to a project manager
TYPES OF ORGANIZATIONAL STRUCTURES (2)
Weak Matrix
• Power rest with the
functional manager
• Power of project manager =
coordinator or expediter
Balanced Matrix
• Power is shared between
the project manager and the
functional manager
TYPES OF ORGANIZATIONAL STRUCTURES (3)
Strong Matrix
• Power rest with the project
manager
• Composite
ORGANIZATIONAL STRUCTURE
Monitoring &
Controlling Processes
Planning
Processes
Executing
Processes
Project
Boundaries
PROCESS INTERACTION
I P • Project management
E processes are
represented as discrete
elements with well-
defined interface
M&C C
• ▶ Responsibility,
• ▶ Respect,
• ▶ Fairness, and
• ▶ Honesty.
PROJECT MANAGEMENT PRINCIPLES
• 9, Navigate complexity
• 10, Optimize risk responses
• 11, Embrace adaptability and resiliency
• 12, Enable change to achieve the
envisioned future state
MEDIA SNAT SHOT
• Berlin Brandenburg Airport
• Failed projects, Germany airport
• Germany may be known for its efficiency, but the
Berlin Brandenburg Airport has been anything
but. The Germans had hoped this airport would
put Berlin on the map as a centre of commerce.
After 15 years of planning, construction started
on the airport in 2006.
• The original opening date was supposed to be in
2011, but this date has come and gone. It is now
scheduled to be opened on 31st October 2020, in
the middle of the global COVID-19 pandemic, the
irony is certainly not lost on us!
MEDIA SNAT SHOT-2
• Berlin Brandenburg Airport
• Many of the issues with the Berlin airport
stem from having too many stakeholders
with conflicting visions. By allowing the
common goal to become diluted, it has
made it impossible to progress as a
normal rate. Ambition and scope creep
are primarily to blame for the delays.
77
Scope Mgt Processes
• Verify scope
Formalizing the acceptance of the
completed project deliverables
• Control Scope
Monitoring the status of the project
and product scope and managing
changes to the scope baseline
Project
Scope
Process • Helps the Project Manager
and Team :
• A deliverable-oriented hierarchical
decomposition of the work to be
executed by the project team to
accomplish the project objectives
and create the required deliverables.
• DEPENDENCY
• A series of tasks that are interrelated. There are
several different types of dependencies in project
management:
KEY TERMS
TYPES
• Mandatory dependencies –
legally/contractually required or inherent in
the nature of work
Analogous estimating
a technique for estimating the duration of cost using
historical data from a similar activity/project.
It uses parameter from previous similar project such
as duration, budget, size, weight, & complexity.
KEY TERMS
ACTIVITY DURATION ESTIMATES
Parametric estimating
Three-point estimating
Reserve analysis
CRITICAL PATH
a critical path is the sequence activities that represents the
longest path through a project, which determines the shortest
possible project duration.
KEY TERMS
CRUSHING
FAST-TRACKING
KEY TERMS
Ford Edsel
Ford spent a long time conducting research into
what the consumer wanted from a car. But by the
time Ford was ready to release the Edsel, the
market had already moved on to compact cars
and the Edsel was a flop.
While market research can be powerful, it is only
useful if it is also timely. Being quick to market with
fresh new ideas is essential or you run the risk of
being left behind. This is all the more relevant
today when public opinion and trends are moving
at breakneck speed
COST MANAGEMENT
PROJECT COST MANAGEMENT
Project Cost Management includes the processes involved in
Planning, Estimating, Budgeting, Financing, Funding, Managing,
and Controlling costs so that projects can be completed within
budget
• Units of Measure
• Level of Precision
• Level of Accuracy
• Organizational Procedures Links
• Control Thresholds
• Reporting Formats
• Process Descriptions
• Additional details such as description of strategic funding choices, procedure to
account for fluctuation in currency exchange & cost reporting
DETERMINE BUDGET: INPUTS
1. Cost Management Plan – describes how project costs are managed & controlled
2. Scope Baseline:
Project Scope Statement; WBS; & WBS Dictionary.
3. Activity Cost Estimates – each activity in a work package are aggregated to get the cost estimate
4. Basis of Estimates – must specify basic assumptions related to inclusion, exclusion of indirect or other costs
5. Project Schedule – planned start & finish dates of activities, milestones, work packages & control accounts
6. Resource Calendars * – provide info on which resources are assigned and when they are assigned
7. Risk Register * – must be reviewed to consider how to aggregate the risk response cost.
8. Agreements *
Applicable agreement information and cost relating to products, services, or results that have been or will be purchased are included when
determining the budget.