The document provides a progress report for a Cafe Management System project being developed by two students. It summarizes the work completed so far, including planning, research, analysis, and frontend and backend design. The design phase is currently in progress, with the login form sample user interface shown. Implementation will begin following the project timeline. Overall, more than 50% of the work has been completed according to the plan outlined in the Gantt chart.

Uploaded by

Sofia Sharma
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
44 views3 pages

Progress Report

The document provides a progress report for a Cafe Management System project being developed by two students. It summarizes the work completed so far, including planning, research, analysis, and frontend and backend design. The design phase is currently in progress, with the login form sample user interface shown. Implementation will begin following the project timeline. Overall, more than 50% of the work has been completed according to the plan outlined in the Gantt chart.

Uploaded by

Sofia Sharma
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

Tribhuvan University

Faculty of Humanities and Social Science

“CAFE MANAGEMENT SYSTEM”


A PROJECT PROGRESS REPORT

Submitted to:

Department of BCA
Mahendra Morang Adarsh Multiple Campus
Biratnagar, Morang, Nepal

Submitted by:

Ram Pukar Ray (TU Registration no: 6-2-0003-0116-2019)


Adarsh Kumar Mandal (TU Registration no: 6-2-0003-0091-2019)
A Progress Report

The following summary of the project includes development progress from 2078 Chaitra 1 st
week to 3rd week of Baisakh 2079. A detailed summary of the above-mentioned dates is
provided below along with descriptions. Additionally, upcoming plans and works to do are also
mentioned in the report below.

Table 1: Gantt Chart

Weeks
1 2 3 4 5 6 7 8 9 10 11 12
Activities
Planning
Research
Designing
Implementation
Testing
Documentation

Progress:

Following the above Gantt Chart of our project currently, we are in the design phase of our
project. We divided our progress statement into the following different topics as below:

1. Analysis
 We specified the requirement that is associated with the project as clearly as
possible
 We did planning based on our project and its concept.
 We did a small research on the relevant topics through different mediums.
 We analyzed the relevant topics of our project.
 We analyzed the research apart from relevant topics.
 We submitted and presented the proposal which contained the description of the
above-mentioned matters.
2. Design
 Appropriate analysis and acceptance of the proposal helped us to move ahead
towards designing.
 Design of Frontend is done along with Backend, connection to the databases,
and other required contexts.
 We have divided the project into different modules and working with it using
JAVA, HTML, CSS, and MY SQL for our project.

A small sample UI of our project is shown in the picture below:

Pic1: Login form of Cafe Management System

3. Implementation
 We are looking forward to implementing our project as soon as possible
following the timeline.

o Conclusion:
After the detailed progress report of our project, we conclude that we have
completed approximately more than 50% of our task and working accordingly
to complete it within the mentioned timeline following the guidelines.