How To Set Up Grid Code Compliance Features in The DECS-250
How To Set Up Grid Code Compliance Features in The DECS-250
About Basler
Basler Electric is a manufacturer of excitation systems, voltage regulators, genset controls, protective
relays, custom transformers, and injection molded plastic components. Basler also offers turnkey
engineering services through their Basler Services, LLC subsidiary. Basler products control and manage
the delivery of electricity and are commonly found in applications such as power plants, substations,
hydro dams, agricultural facilities, airports, refineries, telecom facilities, factories, marine applications, and
many others. Basler has been in business since 1942 and our products are in operation in over 145
countries around the world.
1.1 Configure
When configuring steady-state operation, pay attention to the measurement units as the frequency
disconnect time delay is expressed in minutes and the voltage disconnect and grid disconnect time
delays are expressed in seconds. The default DECS-250 setting values are taken from VDE 4110 but can
be adjusted as requested by the grid operator. Grid code Configure tab settings are illustrated in Figure 1.
1
Continuous operation is the nominal state and is defined by the following settings:
• Max Frequency for Continuous Operation (Hz)
• Min Frequency for Continuous Operation (Hz)
• Max Voltage for Continuous Operation (pu)
• Min Voltage for Continuous Operation (pu)
When the generator frequency or voltage leaves these operating windows, a timer starts. These operating
windows are illustrated in Figure 2.
2
1.2.1 LVRT Configure
The Low Voltage Ride Through configuration settings (Figure 4) serve as the master control for all
reactive control modes as required by VDE 4110. When enabled and the DECS-250 is operating in var
mode, the reactive power reference that var mode uses is replaced by the reactive power reference as
calculated by the control mode selected.
1.2.2 Q(PF)
Q(PF) controls reactive power (Q) to maintain a constant ratio of active power (P) to apparent power (|S|).
This differs from traditional power factor (PF) control in that PF is not measured or used as the error
signal. P is calculated based on the measured voltage and current. The calculated value of P is used in
combination with the power factor setting to calculate Q(PF)REF as seen in the following equation.
1
𝑄𝑄(𝑃𝑃𝑃𝑃)𝑅𝑅𝑅𝑅𝑅𝑅 = 𝑃𝑃 � 2 − 1
𝑃𝑃𝑃𝑃
Q(PF)REF is used as the reference and is compared to the calculated reactive power, Q, to create the
error signal. The setpoint may be set directly or through an auxiliary source by way of the DECS-250
auxiliary input.
Q(PF) aids grid stability by virtue of increasing the export of reactive power as active power increases.
However, it will also decrease reactive power by the same fashion and potentially lead to a voltage sag
on the grid.
3
Figure 5. Q(Voltage Limit) Curve Example, Without Bus
A bias may be used to shift the midline (as defined as the segment between points 2 and 3) up and down.
See Figure 6.
4
1.2.4 Q(U)
Q(U) adjusts reactive power based on the bus voltage. A slope, illustrated in Figure 7, governs how
reactive power will increase or decrease when the bus voltage deviates from nominal. A voltage dead
band provides stability in the reactive power. When the dead band is active, Q(U) has an envelope where
the reactive power setpoint does not change with respect to bus voltage. If the bus voltage strays outside
the dead band, the reactive power will shift the minimum amount to establish a new dead band that
includes the bus voltage level. A bias may be used to increase or decrease the reference voltage where
the reactive power exchange is zero.
1.2.5 Q(P)
Q(P) controls reactive power to stay on a segmented line defined by a 10-point graph where the x axis is
real power (P) and the y axis is reactive power (Q). The example of Figure 8 shows only five points for
clarity. This control algorithm does not support biasing.
5
0.44
0.33
P4 0.9, 0.22 P5 1.0, 0.22
0.22
0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1.0 1.1
-0.11
-0.22
-0.33
-0.44
P/Pn in per unit
6
2. Onlining Procedure
If the var controller is using a control algorithm as detailed above, the DECS-250 will annunciate this by
showing the unit mode as LVRT on the BESTCOMSPlus Metering Summary tab. To achieve that control,
a custom BESTlogic™Plus scheme is recommended where Grid Code and LVRT are enabled while
offline so that the reconnect timing flags may be of use. Use the VAR/PF enable block to control the
change from voltage matching or AVR mode to LVRT mode.
As shown in Figure 10, two changes to the standard BESTlogic™Plus scheme are recommended. The
first is that the GCC_DISCONNECTED should be connected to a contact input. This contact output
should wire into either opening the 52 breaker or be used for signaling to the SCADA system that the
DECS-250 has timed out and has met the conditions that allow it to break offline. The second change is
that the GCC_DISABLED status should be used as a block for going offline.
Using those two flags as described will ensure compliance with VDE 4110 by commanding the DECS-250
to go offline and remain offline for the entirety of reconnect timing.
To Learn More
To learn more, please email [email protected] or call 618.654.2341 to speak with a Basler
representative.
References
1. 9440300091, Mathematical Per-Unit Model of the DECS-250 Excitation System, Revision E, October
2021
2. VDE-AR-N-4110, Technical requirements for the connection and operation of customer installations
to the medium voltage network (TCR medium voltage), November 2018