PROJEK PEMBINAAN LALUAN TAXIWAY TAMBAHAN, APRON DAN PAGAR KESELAMATAN DI UNIVERSITY KUALA LUMPUR MALAYSIAN INSTITUTE OF AVIATION

TECHNOLOGY (UniKL MIAT) SUBANG, SELANGOR


ID Task Name Duration Start Finish Target % Complete
2023 2024
Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024
A M J J A S O N D J F M A M J J A S O
1 OVERALL WORK PROGRAMME 546 days Wed 12 Apr '23 Tue 8 Oct '24 9% 8%
2 PRELIMINARIES AND GENERAL CONDITIONS 546 days Wed 12 Apr '23 Tue 8 Oct '24 16% 14%
3 Contractual Requirements 35 days Wed 12 Apr '23 Tue 16 May '23 100% 100%
4 Insurance of Works 28 days Wed 12 Apr '23 Tue 9 May '23 100% 100%
5 Performance Bond 35 days Wed 12 Apr '23 Tue 16 May '23 100% 100%
6 Site Facilities 532 days Wed 26 Apr '23 Tue 8 Oct '24 20% 16%
7 Site Office 42 days Wed 26 Apr '23 Tue 6 Jun '23 100% 100%
8 Site Office 21 days Wed 26 Apr '23 Tue 16 May '23 100% 100%
9 Furniture 21 days Wed 17 May '23 Tue 6 Jun '23 100% 100%
10 Office Equipment 28 days Wed 10 May '23 Tue 6 Jun '23 100% 13%
11 Confirmation 7 days Wed 10 May '23 Tue 16 May '23 100% 50%
12 Delivery Lead Time 21 days Wed 17 May '23 Tue 6 Jun '23 100% 0%
13 Transport Services 518 days Wed 10 May '23 Tue 8 Oct '24 9% 9%
14 Confirmation 14 days Wed 10 May '23 Tue 23 May '23 100% 100%
15 Delivery Lead Time 28 days Wed 24 May '23 Tue 20 Jun '23 100% 100%
16 Upkeep and Maintenance 476 days Wed 21 Jun '23 Tue 8 Oct '24 1% 1%
17 Construction Plans 49 days Wed 12 Apr '23 Tue 30 May '23 100% 100%
18 Programme of Work 28 days Wed 12 Apr '23 Tue 9 May '23 100% 100%
19 PQP 21 days Wed 10 May '23 Tue 30 May '23 100% 100%
20 Site Management 532 days Wed 26 Apr '23 Tue 8 Oct '24 11% 11%
21 Site Agent 532 days Wed 26 Apr '23 Tue 8 Oct '24 11% 11%
22 Security Clearance 532 days Wed 26 Apr '23 Tue 8 Oct '24 11% 11%
23 Temporary Facilities 475 days Wed 7 Jun '23 Mon 23 Sep '24 4% 0%
24 Hoarding 14 days Wed 7 Jun '23 Tue 20 Jun '23 100% 0%
25 Access 21 days Wed 21 Jun '23 Tue 11 Jul '23 19% 0%
26 Upkeep and Maintenance 440 days Wed 12 Jul '23 Mon 23 Sep '24 0% 0%
27 MAIN WORKS 481 days Wed 7 Jun '23 Sun 29 Sep '24 1% 1%
28 Site Survey & Setting Out 14 days Wed 7 Jun '23 Tue 20 Jun '23 100% 100%
29 Detection of Existing Services 14 days Wed 12 Jul '23 Tue 25 Jul '23 0% 0%
30 General Clerance (12000m2) 21 days Wed 21 Jun '23 Tue 11 Jul '23 19% 0%
31 Enviromental And Sedimentation Control Plan 49 days Wed 12 Jul '23 Tue 29 Aug '23 0% 0%
32 Earth Drain 14 days Wed 12 Jul '23 Tue 25 Jul '23 0% 0%
33 Silt Trap 35 days Wed 26 Jul '23 Tue 29 Aug '23 0% 0%
36 Wash Trough 35 days Wed 12 Jul '23 Tue 15 Aug '23 0% 0%
39 Earthworks (11320m3) 91 days Wed 16 Aug '23 Tue 14 Nov '23 0% 0%
40 Zone 1 28 days Wed 16 Aug '23 Tue 12 Sep '23 0% 0%
44 Zone 2 28 days Wed 13 Sep '23 Tue 10 Oct '23 0% 0%
48 Zone 3 21 days Wed 11 Oct '23 Tue 31 Oct '23 0% 0%
52 Zone 4 14 days Wed 1 Nov '23 Tue 14 Nov '23 0% 0%
55 PQC Works 320 days Wed 15 Nov '23 Sun 29 Sep '24 0% 0%
56 Confirmatory Probe Test (50nos) 28 days Wed 15 Nov '23 Tue 12 Dec '23 0% 0%
59 Remove Existing Fence & PQC (460m2) 63 days Wed 15 May '24 Tue 16 Jul '24 0% 0%
65 Excavation (27750m3) 189 days Wed 13 Dec '23 Tue 18 Jun '24 0% 0%
81 Temporary Cable Protection Works 189 days Wed 13 Dec '23 Tue 18 Jun '24 0% 0%
97 Sand Fill with Geotextile (18800m3) 189 days Wed 20 Dec '23 Tue 25 Jun '24 0% 0%
113 Crushed Aggregate Fill with Geogrid (3800m3) 133 days Wed 21 Feb '24 Tue 2 Jul '24 0% 0%
151 Proof Rolling Test 84 days Wed 17 Apr '24 Tue 9 Jul '24 0% 0%
156 Cement Treated Base (2250m3) 77 days Wed 1 May '24 Tue 16 Jul '24 0% 0%
161 PQC with BRC & Dowel Bar (7500m2) 128 days Wed 22 May '24 Thu 26 Sep '24 0% 0%
235 PU Sealant (3300m) 124 days Wed 29 May '24 Sun 29 Sep '24 0% 0%
251 Turfing (800m2) 28 days Wed 29 May '24 Tue 25 Jun '24 0% 0%
254 Drainage Works 175 days Wed 21 Feb '24 Tue 13 Aug '24 0% 0%
255 Slotted Drain (293m) 119 days Wed 21 Feb '24 Tue 18 Jun '24 0% 0%
272 U-Drain (90m) 21 days Wed 26 Jun '24 Tue 16 Jul '24 0% 0%
274 Sump (8nos) 28 days Wed 17 Jul '24 Tue 13 Aug '24 0% 0%
277 Gate Storage 35 days Mon 19 Aug '24 Sun 22 Sep '24 0% 0%
278 Structural Works (2 no) 35 days Mon 19 Aug '24 Sun 22 Sep '24 0% 0%
281 MECHANICAL WORKS 35 days Mon 19 Aug '24 Sun 22 Sep '24 0% 0%
282 Gate 35 days Mon 19 Aug '24 Sun 22 Sep '24 0% 0%
283 Gate Rail Track 28 days Mon 19 Aug '24 Sun 15 Sep '24 0% 0%
284 Retractable Gate 7 days Mon 16 Sep '24 Sun 22 Sep '24 0% 0%
285 PROVISIONAL SUMS 21 days Wed 19 Jun '24 Tue 9 Jul '24 0% 0%
286 Fencing Works 21 days Wed 19 Jun '24 Tue 9 Jul '24 0% 0%
287 G1 Contractor 21 days Wed 19 Jun '24 Tue 9 Jul '24 0% 0%
288 PRIME COST SUMS 90 days Wed 26 Jun '24 Mon 23 Sep '24 0% 0%
289 Electrical Works 90 days Wed 26 Jun '24 Mon 23 Sep '24 0% 0%
290 NSC 90 days Wed 26 Jun '24 Mon 23 Sep '24 0% 0%
291 HANDING OVER 28 days Wed 11 Sep '24 Tue 8 Oct '24 0% 0%
292 Cleaning Upon Completion 28 days Wed 11 Sep '24 Tue 8 Oct '24 0% 0%

Task Manual Task Deadline


Split Duration-only Critical
Milestone Manual Summary Rollup Critical Split
PREPARED BY: YAKIN SERBA SDN BHD
Summary Manual Summary Baseline
DATE: 23-5-2023
REVISION : 5 Project Summary Start-only Baseline Milestone
Inactive Task Finish-only Baseline Summary
Inactive Milestone External Tasks Progress
Inactive Summary External Milestone Manual Progress