Tutorial Final Payment
Tutorial Final Payment
UNIVERSITI TEKNOLOGI
MARA FINAL EXAMINATION
TUTORIAL
QUESTION
Based on the information given in Appendix 1, prepare a draft Final Account Certificate
for the project. All calculation and the draft certificate must be shown and attached. You
may refer to the appendix for your calculation
CONFIDENTIAL APPENDIX 1 (1) AP/JUN 2019/DQS389/QSD389
A - PARTICULARS OF CONTRACT
1. Preliminaries 620,000.00
2. Main Building 15,500,250.00
3. Store 120,450.00
4. Guard House 60,350.00
5. External Works 850,000.00
6. P.C. and Provisional Sums 3,344,200.00
TOTAL 20,495,250.00
b) Provisional Sums
D-SUMMARY OF VARIATIONS
a) Building works
b) External Works
i. Electrical Installation
Accepted tender figure 532,000.00
Variations Omission Addition
V.O. no. 1 21,000.00 28,200.00
V. P.A System
Accepted tender figure 212,000.00
d) Provisional Sums
The final contract figures for provisional sums, undertaken by the main contractor,
have been agreed as follow: