MEP Production Rates
MEP Production Rates
MEP Production Rates
5
Activity Production Rate
Introduction
The production rate should be the planned average daily production rate based on available resource
and the environment within which the work will be performed. The production rate include not only the
productive time associated with a particular activity but also idle and non-productive time associated with
the movement and setup of equipment, break times, expected equipment downtime for maintenance and
repair, and other expected downtime. When estimating a production rate, resource availability and other
factors affecting productive need to be considered.
Resource planning and scheduling are critical to the successful completion of any project. Labor, material
and equipment must be considered when establishing planned activity durations and developing network
logic. Project work cannot be accomplished on schedule without the following three resources being
available in sufficient quantities at the time they are needed:
• Manpower (Labor)
• Equipment
• Materials
Work Quantity
Activity Duration = —––––––––––––––—————————
Production Rate x Resource Usage
This section covers the manpower requirement to complete each activity and the time required to complete.
The production rate given in this section, on the other hand, is not a constant and can be affected by a
number of factors both within and beyond the contractor’s control.
PL = Plumber, PF = Pipe Fitter, PW = Pipe Welder, IN = Insulatar, DM = Ductman, EL = Electrician, HL = Helper Contd...
67
Building Services Planning Manual 2007
PL = Plumber, PF = Pipe Fitter, PW = Pipe Welder, IN = Insulatar, DM = Ductman, EL = Electrician, HL = Helper Contd...
69
Building Services Planning Manual 2007
PLUMBING EQUIPMENT
Water distribution pumps installation (one set) nos 1 0.125 2 2 4
Booster pumps installation nos 1 0.125 2 2 4
Sewage lift pumps installation nos 1 0.125 2 2 4
Electric water heater installation nos 2 0.25 1 2 3
Bath tub installation nos 1 0.125 1 2 3
Shower tray installation nos 1 0.125 1 2 3
Water closet installation nos 1 0.125 1 1 2
Bidet installation nos 1 0.13 1 1 2
Wash basin installation nos 1 0.13 1 1 2
Kitchen sink installation nos 1 0.125 1 1 2
FIRE FIGHTING EQUIPMENT
Fire water pumps installation nos 1 0.13 2 2 4
Fire hose cabinet installation nos 1 0.13 2 2 4
Sprinkler fixing nos 30 3.75 1 1 2
HVAC EQUIPMENT
Fan coil unit (FCU) installation nos 4 0.50 2 2 4
Air handling unit (AHU) installation nos 1 0.13 4 4 8
Fresh air handling unit (FAHU) installation nos 1 0.13 4 4 8
Chilled water pump installation nos 1 0.13 2 2 4
DUCTING
Duct installation sq.ft 60 7.50 1 1 2
Duct insulation sq.ft 60 7.50 1 1 2
Duct connection to FCU nos 4 0.50 1 1 2
Duct connection to AHU nos 1 0.13 4 4 8
Duct connection to FAHU nos 1 0.13 4 4 8
Chilled water pipe connection to
nos 1 0.13 4 4 8
FCU / AHU / FAHU
PL = Plumber, PF = Pipe Fitter, PW = Pipe Welder, IN = Insulatar, DM = Ductman, EL = Electrician, HL = Helper