CTN-M-1-11 Field Inspection of Reinforcing Bars
CTN-M-1-11 Field Inspection of Reinforcing Bars
CTN-M-1-11 Field Inspection of Reinforcing Bars
Technical Note
CTN–M–1–11
Field Inspection of
Reinforcing Bars
Introduction The improper placement of reinforcing steel
In an ideal world, quality control or inspec- can greatly affect the strength and service life
tion to assure compliance with project drawings*, of a structure. This could lead to reduced struc-
project specifications, material standards, and tural performance, whereby the structure can
building codes would not be necessary because no longer be used in the manner in which it was
the project drawings and project specifications intended. In the transportation field, where the
would be complete without errors or omissions, concrete elements are exposed to the environ-
the materials would be manufactured exactly to ment, costly repairs and early replacement of
the material standards, and the field workman- structures have been too common and are often
ship would be precise. However, in the real world, caused by improper reinforcing steel placement.
quality control programs are recommended, with A better understanding of the reasons for prop-
inspection usually mandated to ensure compli- er reinforcement placement and how to inspect
ance with a regulatory agency’s policies. Why is reinforcement in the field will hopefully reduce
this necessary? the need for costly repairs and possible early re-
placements of structures falling short of their ser-
Project drawings are not always complete due vice life.
to an owner’s desire for a rapid start and com-
pletion of a project. Materials may not meet the Inspector Qualifications
standards due to variations in the raw material or Inspectors are individuals qualified to perform
the manufacturing process. Workmanship is not the inspection tasks. Through education, training,
always accurate due to improper training, inade- and experience, they should have the ability to
quate experience, or careless supervision. Thus, read and understand project specifications, ma-
there is recognition by owners, contractors, ar- terial standards, project drawings, and building
chitects/engineers, and regulating agencies that code requirements. In the event of field problems,
programs for quality control and inspection are they must work with the contractor and make de-
necessary to ensure compliance with the con- cisions on improvised details if the architect/en-
tract documents and the building code applicable gineer is unavailable to provide direction. An in-
to the project under construction. spector must project confidence in his decisions.
He should be meticulous, correct, fair, and firm,
The benefits of a quality control program and along with the ability to compromise when faced
mandated inspection are mainly monetary, but with a dispute regarding a conflict in the contract
they also ensure structural safety and compliance documents or actual field conditions, or both.
with architectural requirements. The owners, pri-
vate and governmental, benefit with lower total Inspection Goals
costs, on-time construction schedules, and quick- The goal of any inspection or quality control
er occupancy. The architect/engineer benefits in program is to ensure that the intent of the contract
the knowledge that the structure will conform to documents is met and the applicable requirements
the design intent. The contractor, his subcontrac- of the building code are followed. Inspection and
tors and suppliers, and all of their employees testing by themselves do not add quality to the
will benefit in a similar manner. The public, as product or the material being inspected, but only
the ultimate consumer and user of the structure, confirm whether or not what is being inspected
benefits in the knowledge that the structure has meets the criteria established by the project draw-
been built according to the project drawings and ings, project specifications, and building code.
specifications.
Quality during the construction process is
* See the Terminology section on Page 7 for definitions of certain achieved almost entirely by the contractor’s
terms used in this report. quality assurance program, which depends on
and involves all workers and field supervisors. The con- d. Approved Placing Drawings: The latest approved
tractor’s inspectors are his employees and are sepa- placing drawings should be available for review and
rate from the inspectors mandated by the owner or lo- study by field placing personnel and the inspector at
cal building department. The quality control inspection least one day prior to the actual placing of the reinforc-
by the contractor helps ensure that the finished con- ing bars.
struction meets the owner’s requirements, while simi-
lar programs by the material producers and suppliers e. Material Shipment: A schedule of anticipated delivery
ensure that the products and materials being supplied dates should be provided and updated as necessary
will meet the specific requirements of the material stan- so the inspector can schedule an in-place inspection
dards. The final in-place acceptance inspection is a and review any reinforcing bar material tags.
formalized procedure providing the owner and regula-
tory agency with an acceptable degree of assurance f. Potential Concerns: A discussion between all parties
that the contractor has satisfied his obligations as de- is desirable to identify difficult-to-place reinforcement
scribed in the contract documents and by the building details, lack of specific details or information on the
code. To accomplish this end, the inspector must be contract documents, possible structural drawing dis-
familiar with the project specifications and project draw- crepancies, detailing or placing errors, and verification
ings, have reasonable knowledge of the building code and acceptability of implemented field changes.
requirements, have access to material standards and
reference codes, and have available industry manuals g. Tolerances: A discussion with all parties is necessary
and reports. See "Applicable References" at the end of regarding which tolerances are critical, the method of
this Technical Note. measurement, and the basis for either rejection or ac-
ceptance.
At the start of a construction project, whether small,
medium or large, it is recommended that the inspector h. Periodic Meetings: It is recommended that regularly
establish an inspection program for the reinforcing bars. scheduled meetings be held in order to discuss the
The program can be established at a pre-construction previous inspection reports, any problems that were
conference with the general contractor’s superintendent, encountered, solutions to the problems, and the
the supplier’s representative, the ironworker foreman, schedule of work for the next period.
and other interested parties, such as the architect/engi-
neer or the architect/engineer’s inspector. This meeting Material Verification
should establish a checklist procedure and minimum re- In-place inspection of reinforcing bars starts with the
quirements for inspection acceptance. mill test report, which in some cases is supplemented
by a report from an independent testing laboratory. Both
Checklist reports should provide data as to grade of steel, tensile
The checklist for the inspection of reinforcing bars properties (yield strength, ultimate tensile strength, and
should include, but not be limited to, the following: percentage of elongation), bend tests, chemical com-
position and carbon equivalent (C.E.) in the event the
a. Construction Schedule: A construction schedule reinforcing bars are to be welded, and the spacing and
from the general contractor is important and neces- height of deformations. The reported data should meet
sary so the inspector can follow the reinforcing bar the requirements of the applicable ASTM standard. A vi-
placing crew and carry out an inspection of the in- sual examination of the mill markings on a bar will iden-
place reinforcing bars prior to the scheduled placing tify the producing mill, the bar size, the type of steel, and
and finishing of the concrete. the grade of steel.
b. Certified Mill Test and/or Bar Coating (Certifica- Inspection of In-Place Reinforcing Bars
tion) Reports: These reports may accompany the Inspection of the reinforcing bars installed in the forms
shipments of material to the job-site, and thus should is done by visually examining the layout pattern, measur-
be available to the inspector. In the event the reports ing the spacing, and counting of bars. The bar diameter
are sent to the contractor’s office rather than to the and the bar shape, if bent, can be visually checked. Bar
job-site, arrangements should be made to make them lengths, bar spacings, embedments, and bearings on
available to the inspector. walls or beams are normally checked by measurement.
In a slab, the total number of pieces can be counted with
c. Independent Testing Laboratory Reports: The re- the spacing of the slab bars verified by measurement,
ports on samples taken either at the reinforcing bar all checked against the approved placing drawings in
fabricator’s shop or from material shipped to the job- conjunction with the structural drawings. Similarly, beam
site, offer supplemental verification of the producer’s longitudinal bars, column vertical bars, and stirrup and
mill test report. tie spacings are checked visually and by measurement,
as required.
The tolerance for deviations from cross-sectional di- The ACI 117 spacing tolerance for stirrups measured
mensions, except slabs, are: along a line parallel to the stirrup spacing is the lesser
of plus or minus 3 in., or plus or minus 1 in. per ft. of
Specified Dimension Tolerance beam depth. For column ties, the requirements are the
≤ 12 in. + ⅜ in., – ¼ in. same except the least column width is the key dimension
> 12 in. and ≤ 36 in. + ½ in., – ⅜ in. instead of beam depth. Thus, stirrup or tie placement in
> 36 in., + 1 in., – ¾ in. an 18-inch square beam or column could vary from the
specified location by 1½ inches.
The tolerance for the thickness of suspended slab is
– ¼ in.
In-Situ Bending and Rebending*
A potential problem occurs if the stirrups or ties are The practice of bending and rebending installed re-
fabricated to the plus tolerance of ½ inch when the forms inforcing bars is often questioned. Many conditions and
are made to the minus tolerance of ⅜ inch. This condi- situations at the job-site require such bending and re-
tion has the effect of reducing the clearance to 7/16 inch bending. As an example, the horizontal leg of bent rein-
on each side of the stirrup or tie. The inspector must de- forcing bars (fabricated) projecting from a wall to become
termine whether or not this encroachment on concrete the top bars of a beam may have been improperly placed
cover is critical. As previously stated, the ACI 117 Speci- too low or too high, well in excess of concrete cover and
fication permits a reduction in concrete cover of ⅜ inch placing tolerances. These bars will require ‘straightening’
when the member size is 12 inches or less, and ½ inch and then ‘rebending’ to the proper position. The inspector,
if the member is over 12 inches in the direction of toler- after consultation with the architect/engineer, should ap-
ance. This type of problem should be resolved with the prove the procedure used to accomplish the task. Section
assistance of the architect/engineer. R7.3.2 in the Commentary of the ACI 318 Building Code
presents guidelines for straightening and rebending em-
Another example of encroachment on concrete cover is bedded reinforcing bars. Section 3 in the ACI 301 Specifi-
a formed footing; the horizontal form tolerance is plus 2 inch- cation includes provisions for field bending or straighten-
es and minus ½ inch, while the tolerance on the reinforcing ing of reinforcing bars.
bars, either straight or bent, is plus or minus 1 inch. Again, if
the forms are ‘minus’ and the reinforcing bars are ‘plus’, the In some instances, the use of planned pre-bent dow-
concrete cover at each end of the bars is reduced from 3 els is requested by the contractor. The architect/engi-
inches to 2 ¼ inches. However, this condition would be ac- neer should review the request and notify the inspector.
ceptable, because the allowed reduction in concrete cover Similarly, straight dowels may be planned to be field bent
is 1 inch for sizes of structural members in excess of 2 feet. into place, such as an outside face wall where vertical
bars will be bent horizontally to become the slab end
In another example, the length of a beam which is top bars. This procedure is intended to facilitate slab
discontinuous at each end may create a problem if the formwork erection. Again, the architect/engineer should
formwork is ‘minus’ when at the same time the reinforc- review the procedure and notify the inspector. The in-
ing bars are ‘plus’. Each trade, carpenter and ironworker, spector should discuss the bending procedure with the
can claim that their work is within tolerance, thus giving placing foreman to ensure that the bends conform to the
the responsibility to the inspector to make a decision. ACI 315 Standard. Where large diameter bars are in-
The inspector must determine whether the encroach- volved, some amount of heating may be recommended
ment on concrete cover is detrimental to the safety and
service life of the structure, or is within the allowable lim-
its of reduction in concrete cover. * This subject is not related to the fabrication of reinforcing bars. Fabrication
of reinforcing bars is the cutting-to-length of straight bars, and cutting-to-
length and bending-to-shape of bent bars. The issue here is concerned
Inspection of reinforcing bar placement in walls and with bending and straightening or rebending of reinforcing bars that are
slabs is usually straight forward and normally no mis- partially embedded in hardened concrete.
Welding of Crossing Bars – The inspector should not “Standard Specification for Low-Alloy Steel Deformed
allow field tack welding of reinforcing bars, i.e., welding and Plain Bars for Concrete Reinforcement (A706/
of crossing bars, as a means for assembly of reinforce- A706M-09b)”, ASTM International.
ment. Tack welding can embrittle the steel, which reduces
strength and can also have a detrimental effect on ductility “Standard Specification for Epoxy-Coated Steel Rein-
and fatigue resistance. Field tack welding is not a substi- forcing Bars (A775/A775M-07b)”, ASTM International.
tute for wire tying the assembly of reinforcing bars.
“Standard Specification for Epoxy-Coated Prefabricated
For information on shop-welded assemblies of rein- Steel Reinforcing Bars (A934/A934M-07)”, ASTM Inter-
forcing bars, see EDR No. 53 “Assembling Reinforcing national.
Bars by Fusion Welding in the Fabricating Shop.”
“Standard Specification for Zinc-Coated (Galva-
nized) Steel Bars for Concrete Reinforcement (A767/
Conclusions A767M-09)”, ASTM International.
All the foregoing discussion indicates that the in-
spector has a formidable assignment when inspecting “Standard Specification for Deformed and Plain Stain-
in-place reinforcing bars. This impression is not neces- less-Steel Bars for Concrete Reinforcement (A955/
sarily true, but it is an exacting task, one that assures A955M-10a)”, ASTM International.
the workers perform their job to the best of their ability.
However, mistakes can and will happen, but an inspec- “Standard Specification for Headed Steel Bars for Con-
tor is expected to find them and have them corrected. All crete Reinforcement (A970/A970M-09)”, ASTM Interna-
parties involved in a construction project, from the archi- tional.
tect/engineer to the contractor, attempt to do error-free
work. A quality control program by the contractor helps in “Standard Specification for Rail-Steel and Axle-Steel De-
achieving this goal, which makes final inspection easier. formed Bars for Concrete Reinforcement (A996/A996M-
The inspector should not perceive his role as adversarial, 09b)”, ASTM International.
but as complementary to the workers in support of good
construction techniques and practice. Good inspection Manual of Standard Practice, 28th Edition, 2009, CRSI.
is assurance of a properly built structure, one which all
parties involved in the process can take pride. Placing Reinforcing Bars, 8th Edition, 2005, CRSI.
• Certified mill test reports on reinforcing materials. • When Contractor finds it necessary to move reinforcement
beyond the specified placing tolerances to avoid interfer-
• Placing drawings showing fabrication dimensions and lo-
ence with other reinforcement, conduits, or embedded
cations for placement of reinforcement and supports.
items, review a submittal showing the resulting reinforce-
• List of splices and request to use splices not indicated on ment arrangement.
the Contract Documents.
• Inspection and quality-control program of plant that is not
• Request to use mechanical splices not shown in the Con- certified by Concrete Reinforcing Steel Institute.
tract Documents.
• Provide equivalent certification program for evaluation by
• Request for placement of column dowels without using Architect/Engineer.
templates.
• Precast concrete support materials.
• Request a procedure to field bend or straighten partially
• Request to heat reinforcement before bending.
embedded reinforcing bars.
• Request to extend reinforcement through control joints,
• Copy of CRSI Plant Certification and/or NTPEP Mill Certi-
including saw-cut joints.
fication, if applicable.
• Request to use an alternative method or setting column
• Description of reinforcing bar weld locations, welding pro-
dowels.
cedure specifications, and welder qualifications.
• Request to use other method to measure preheat tem-
• Proposed supports for coated reinforcement and materi-
perature.
als for fastening coated reinforcement.
• Request to field cut reinforcement.
• Request use of alternative reinforcement support type.
Contributors: Dr. David P. Gustafson, P.E., S.E. and Anthony L. Felder, P.E., with subsequent
contributions from Neal S. Anderson, P.E., S.E..