Appendix O Contents of The Health and Safety File
Appendix O Contents of The Health and Safety File
Appendix O Contents of The Health and Safety File
The Guidance to CDM 2015 L153 outlines at Appendix 4 the information that is likely to be
included within a health and safety file.
While the format of the file will vary greatly between different types of project (eg the file for a
processing plant is likely to be far more extensive than that for an office building), the
sections set out below indicate the basic elements that need to be included in any file.
Section 1 — Drawings
A brief description of the work carried out.
Detailing the sequence in which external cladding panels were assembled could also be
included in the file, which would indicate how they might be safely disassembled.
_________________________________________________________________________________
Page 1
flammable finishes
various types of insulating materials
lead paint
pesticides
special coatings which should not be burnt off.
Section 6 — Health and Safety Information Required for Cleaning and Maintaining the
Structure
The file must set out the various elements within the building that are provided for
maintenance and cleaning purposes and which have health and safety implications for those
using them, including:
mains distribution, eg the location, size and termination of the gas main, water main
and telecommunications
emergency backup facilities, eg standby generators
security alarms
fire-fighting systems, eg sprinkler systems, drencher systems and fire shutters.
_________________________________________________________________________________
Page 2
Section 8 — Information and As-built Drawings
Information and as-built drawings should be included of the structure, its plant and
equipment (for example, the means of safe access to and from service voids, fire doors and
compartmentalisation, etc).
The drawings should be the final, “as-built” version (ie as amended from the originals
through the construction process). These will represent the final structure as it actually exists
and not just as it was conceived. The drawings should:
indicate the position of incoming services and distribution (any or all of which may be
concealed)
indicate the location and details of various building materials used
identify the various types of insulation material, flammable finishes, etc that may
represent hazards if they are disturbed
make cross references to the information on hazards where appropriate.
The Health and Safety File should NOT contain information which will not be of help when
planning construction work in the future such as the following:
the client, who can provide existing information, eg drawings and location of
services, as well as information on how he/she would like the final maintenance
procedures to be arranged
the designers, eg architects, structural engineers and quantity surveyors
the principal contractor and subcontractors
statutory/private undertakers for utilities, eg gas, electricity, water and
telecommunications.
_________________________________________________________________________________
Page 3
Certain information may be readily available, including:
designers' drawings
operation and maintenance manuals from specialist equipment suppliers.
The principal designer may need to be proactive in order to obtain relevant information by
petitioning the various parties to supply the necessary details to complete the contents
outlined above.
Compilation information for the health and safety file and health and safety plan should occur
simultaneously. As with the health and safety plan, the two stages in the development of the
file are the:
Designers are obliged under CDM 2015 to undertake risk evaluations for the health and
safety implications of their designs in order to design out risks or identify any residual risks
that could not be eliminated at design stage. These will highlight any remaining hazards for
inclusion within the pre-construction information.
It would be helpful for designers to distinguish the risk evaluations that have implications for
future maintenance and demolition so that they may be readily accessed by the principal
designer for the purposes of compiling the health and safety file. This may even be
conducted as a separate exercise by designers.
With regard to designers, the management responsibilities of the principal designer may vary
greatly between projects, as follows.
If the design is being carried out by a team within a particular organisation, designers
may liaise directly with one another.
The work of the principal designer in compiling the health and safety file may be
more onerous on projects where the work of several individual designers not directly
in contact with each other needs to be co-ordinated.
In either case, the principal designer will need to:
review the interaction of various elements of the design for their health and safety
implications
extract those elements which will affect future construction work for inclusion in the
health and safety file.
_________________________________________________________________________________
Page 4
The compilation of the health and safety file should be properly managed in order to prevent
it from containing information which is not relevant or helpful. Such management requires:
organising regular meetings between the principal designer and the principal
contractor and designers to review design variations
checking that all variations to the work content are recorded, even when there is no
financial effect
verifying that all variations are assessed in health and safety terms, risk
assessments are carried out and that risks to health and safety for future
construction work are recorded in the file.
When any work has been completed, the file should record any new circumstances that
arise. The file will essentially remain unchanged provided the same methods and materials
as adopted previously are used again. However, changes that affect the ways in which safe
systems of work are set up must be recorded.
in paper format, with all of the necessary information bound into a single or series of
folders, properly cross-indexed
electronically, ensuring that all information will be retrievable in future.
The safe keeping of the file should be treated with as much care as other important legal
documents. In multi-occupancy situations, eg where a housing association owns a block of
flats, the owner should keep and maintain the file but ensure that individual flat occupiers are
supplied with health and safety information concerning their home.
_________________________________________________________________________________
Page 5