Processing Building Permit

The document outlines the general flow in the building permit process, which includes an applicant securing application forms and requirements, preliminary reviews by processing clerks and other officials, reviews and approvals from engineers and the building official, assessment and payment of fees, verification of payment, approval of the building permit, and release of the permit to the applicant. Key steps involve application submission and review, plan approval by various officials, fee payment, and final permit issuance.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
55 views3 pages

Processing Building Permit

The document outlines the general flow in the building permit process, which includes an applicant securing application forms and requirements, preliminary reviews by processing clerks and other officials, reviews and approvals from engineers and the building official, assessment and payment of fees, verification of payment, approval of the building permit, and release of the permit to the applicant. Key steps involve application submission and review, plan approval by various officials, fee payment, and final permit issuance.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

GENERAL FLOW IN THE PROCESSING BUILDING PERMIT

START

Applicant Shall secure application forms and


requirements.

Secure Note: the Applicant shall secure Location


Application Clearance prior submission of application
to OBO in accordance with the Zoning
Control Procedure of MPDO
Shall jointly review application, auxiliary
Processing and other related permits as to
Preliminary
ation Clerk/ completeness and correctness of related
review Applicant plan/s and supporting documents.
Shall advise applicant for any deficiencies
observed.

Building Shall prepare the endorsement letter


Official (form) for signature of Building Official who
shall cause the endorsement of the whole
Endorse Processing set of application to include all copies of
Clerk document requirements to concerned
offices.
Note:
Applicant shall be responsible in securing
the Fire Safety Evaluation Clearance/other
clearances as necessary.

Receives Processing Receives application from Applicant with


Permit Clerk, the same whole set of plans and
Application (OBO) documents plus clearances as applicable.

Architect/ BO Shall review and approve the architectural


plan if it complies with requirements of the
National Building Code.

Line and Shall review and approve the Line and


Grade Grade aspect of the plan.
Engineer/ BO

Review and Sanitary Shall review and approve the Sanitary


Engineer/ BO aspect of the plan.
approval
Structural Shall review and approve the structural
Engineer/ BO aspect if it complies with the Structural
Code of the Philippines.

Electrical Shall review and approve the electrical


Engineer/ BO aspect if it complies with the Philippine
Electrical Code.

Mechanical Shall review and approve the Mechanical


Engineer/ BO aspect if it complies with the Philippine
Mechanical Code.

Note:
If the plan complies with the specifications
and classification of the building the
concerned signatories shall sign Building,
Electrical, Sanitary, and Mechanical forms
whichever is appropriate.

Processing Shall compute the prescribed fees based


Assessment of Clerk on the National Building code using the
fees Order of Payment form to be signed
“Reviewed and Recommended for
Payment” by the Building Official.

MTO Shall Issue Official receipt to payment


Payment of fees made by the applicant.

Processing Shall make sure that the assessed fees in


Clerk the Order of Payment are reflected in Box
Verification of 4 of the Building Permit Form including O.R.
payment Number and date paid.
Shall approve the Building Permit.
Building
Approval of Official
Building permit

Release of Processing Shall release the Building Permit


Building permit Clerk
(OBO)
Shall require the applicant to receive the
Records and Processing Building Permit and its accompanying
release Building Clerk attachments.
permit (OBO)
application Shall record such proof of receipt in the
releasing logbook.

Shall distribute the copies of the whole set


of approved plans to Fire Department,
MPDO, and Municipal Assessor’s Office.

END