“Construction of H.L. Bridge over river Salandi at 9th Km on Chandbali Aradi road in the district of Bhadrak under State plan in EPC mode of contract.
Payment as
Payment %of Amount of Proposed
Payment as
Project Activity / Description of Item as % of Contract Payment as % of Proposed Activity / Description of Item Unit Quantity % of Amount Unit rate Remarks
Phases Agreemen Agreement Agreement Cost
t Cost Cost per Stage Contract
Value
Stagewise
Completion of 60% of total no's of superstructure including casting Casting Of Deck slab and Cross Girder Spans 8 3.30% ₹ 15,060,540.00 ₹ 1,882,567.50 To be paid on Prorata basis
Phase-X 12.00%
of deck slab.
Crash barrier cum hand rail Spans 8 0.59% ₹ 2,692,642.00 ₹ 336,580.25 To be paid on Prorata basis
Completion of 100% of wearing coat, hand rails, Drainage spouts, Drainage Spouts and Other miscellaneous Spans 8 0.01% ₹ 45,638.00 ₹ 5,704.75 To be paid on Prorata basis
Phase-XII Expansion joints and other miscellaneous items. 4.00%
Payment as Percentage for STAGE - 4 - APPROACH ROAD AND OTHER MISCLANEOUS : Including Survey, Investigation, Design ,and execution till completion. 10.00% ₹ 45,638,000.00
30% of approach roads with CD works,river training , erosion
control and protection works , road side drains, road furniture, Approach Embankment up to top of Sub grade Lm
safety devices, road marking, signage, crash barriers and other
miscellaneous items etc., as per the design requirement.
i) 0 to 2m Height Lm 500 1.00% ₹ 4,563,800.00 ₹ 9,127.60 To be paid on Prorata basis
Phase -XIV 3.00% ii ) From 2.0 m to 4.0 m height Lm 500 1.00% ₹ 4,563,800.00 ₹ 9,127.60 To be paid on Prorata basis
iii ) from 4.0 m to Top of Sub grade Lm 500 1.00% ₹ 4,563,800.00 ₹ 9,127.60 To be paid on Prorata basis