WWW Scribd Com Document 387028131 Precast and Modular Construction Practices
WWW Scribd Com Document 387028131 Precast and Modular Construction Practices
What is Scribd? Ebooks Audiobooks Magazines Podcasts Sheet music Documents Snapshots
Document 21 pages
Download now 1 of 50 Search document m1 (2)
Lucky Ck
No ratings yet
Document 2 pages
2012 Concrete
atharvasaxena93
No ratings yet
Prestressed Concrete
CONSTRUCTION PRACTICES Larete Paolo
No ratings yet
Document 4 pages
rcc chap-1
aamaniammu
No ratings yet
Document 6 pages
IJEIT1412201406_16.pdf
Akshay Doble
No ratings yet
Mohd. Asjad
Civil Engineering (B. Tech.) Document 4 pages
ASG1.2
Jomar Lampitok
No ratings yet
Document 73 pages
Unit-3: Use of equipments in precast prefabricated structure, Productivity analysis, Economics of form Document 7 pages
work, Design of Formwork and their reusability,
CE-327-RConcrete-Module-1
Unit-4: Modular construction Practices, Fibonacci series, its handling and other reliable proportioning Niel John Baquilar
concepts.
No ratings yet
Unit-5: Modular coordination, Standardization, system building, Lamination and Advantages of
modular construction.
Document 21 pages
Theory of Structures
Assignment Final
ManasArora
No ratings yet
Document 40 pages
RCC UNIT-1.pdf
Sandeep Gowda
No ratings yet
Document 5 pages
eq
kartik.123
No ratings yet
1
Document 66 pages
FINALL STRUCTURALL
REPORT FOR PRINT
This website stores data such as cookies to enable essential site functionality, as well as marketing, personalization, and analytics. By remaining on this website you indicate your consent. Privacy Policy
poojitha
100% (1)
EN Upload
Document 12 pages
1. INTRODUCTION: Concrete is good in resisting compression but is very weak in resisting tension.
RC skeleton in residential
Hence reinforcement is provided in the concrete wherever tensile stress is expected. The best
reinforcement is steel, since tensile strength of steel is quite high and the bond between steel and buildings.docx
concrete is good. As the elastic modulus of steel is high, for the same extension the force resisted by MoHamed M. Scorpi
steel is high compared to concrete.
No ratings yet
Since concrete is a brittle material and it is weak in tension but strong in compression, so steel is used
inside concrete for strengthening and reinforcing the tensile strength of concrete. The steel must have
suitable deformations to provide strong bonds and interlocking of both materials and be surrounded by
the hardened concrete mass it forms an integral part of the two materials, known as " Reinforced
cement Concrete". Document 6 pages
Reinforced concrete, as a structural material, is widely used in many types of structures. It is HW#1 RCD
competitive with steel if economically designed and executed.
Properties of R.C.C./Requirement of Good R.C.C. Kevin Coloso
1. It should be capable of resisting expected tensile, compressive, bending and shear forces. No ratings yet
2. It should not show excessive deflection and spoil serviceability requirement.
3. There should be proper cover to the reinforcement, so that the corrosion is prevented.
4. The hair cracks developed should be within the permissible limit.
5. It is a good fire resistant material.
6. When it is fresh, it can be moulded to any desired shape and size.
7. Durability is very good. Document 3 pages
Document 12 pages
2
Civil Concrete Technology
Lectures Notes Download
Mildred Ivy Bangoy Pangilinan
0% (1)
Advantages of reinforced concrete
Relatively high compressive strength
Better resistance to fire than steel
Long service life with low maintenance cost Document 8 pages
In some types of structures, such as dams, piers and footings, it is most economical f 201508281440732314
It can be casted in any required Rajalakshmi Jothivel
It yields rigid members with minimum apparent deflection
Yield strength of reinforcement is about 15 times the compressive strength of structural concrete No ratings yet
and well over 100 times its tensile strength
Disadvantages of reinforced concrete
It has a low tensile strength of about one-tenth of its compressive strength.
It needs mixing, casting and curing to affect the final strength of concrete
The cost of the forms used for casting concrete is relatively high than other materials. Document 5 pages
It has low compressive strength as compared to steel (the ratio 1:10 based on material).
QUINDAO LIZA MARIE P
Cracks develop in concrete due to shrinkage and the application of live loads.
Causes of Deterioration of Structures LIZA MARIE QUINDAO
A structure becomes deteriorated for the following reasons: No ratings yet
Defective Construction: If proper supervision and inspection are not carried out during the
construction, the work will be defective. Such structures may show signs of deterioration in due course
of time. The ageing and atmospheric effects will increase the degree of deterioration.
Defective materials: If poor quality materials are used in the construction, deterioration can occur at a
fast rate. Proper inspection and quality control of the materials is a must. Where required, materials that
can withstand the effects of fire should be used. Document 29 pages
Environmental factors: The main environmental factors are atmospheric pollution, floods, and Seismicretrofittingtechniqu
earthquakes. Industries in the surrounding areas may inject poisonous gases such as sulphur dioxide into
the atmosphere, which in turn may cause deterioration of the structures. esofrcc 151001030212 Lva…
Design drawbacks: If the design is not per the prescribed norms in tune with the site conditions, it may chbasker
cause defects. For example in seismic zones, the additional force on account of the vibrations has to be No ratings yet
taken into account.
The Repair and Rehabilitation of structures include the following
Inspection methods, assessment, monitoring, maintenance of structures.
Concrete durability, fatigue issues in bridges, laboratory studies, dynamic testing & analysis
Document 12 pages
Seismic strengthening
General repairs unit 1
The repair and rehabilitation methods involve the attachment of new materials to existing structures or poosa annupriya
applying protective coatings to the structures. Research in rehabilitation includes the prevention of
No ratings yet
corrosion of steel which is the most important structural member used in the construction. Research in
design, behavior, and analysis of reinforced building and bridge construction includes studies in
materials, components, and complete structural systems. Materials studies have included normal- and
high-strength concretes; effects of material sagging and materials deterioration on component
properties; bond between concrete and steel reinforcement, and use of headed reinforcement.
Methods of Design of R.C.C. Members Document 5 pages
Working Stress or Elastic Theory Method,
108
Ultimate Load Method,
Adnan Buljubasic
3 No ratings yet
Document 5 pages
Reinforced Cement
Concrete Design
Kimo Keno
No ratings yet
Document 5 pages
86363-158218-1-PB
BasavarajBachihal
No ratings yet
This website stores data such as cookies to enable essential site functionality, as well as marketing, personalization, and analytics. By remaining on this website you indicate your consent. Privacy Policy
EN Upload
Document 5 pages
4
Document 6 pages
Reinforced Concrete Design
Johndee Isip
No ratings yet
vertical and horizontal directions so that the wall panels enclose appropriate spaces for the rooms within
a building. These panels form a box-like structure. Both vertical and horizontal panels resist gravity
load. Wall panels are usually one story high. Horizontal floor and roof panels span either as one-way or
two-way slabs. When properly joined together, these horizontal elements act as diaphragms that transfer
the lateral loads to the walls.
Document 10 pages
Depending on wall layout, there are three basic configurations of large-panel buildings:
Cross-wall systems ductility.pdf
Longitudinal wall systems hfgfg
Two-way system
No ratings yet
FRAME SYSTEMS
Precast frames can be constructed using either linear
elements or spatial beam column sub-assemblages. Precast
beam-column sub-assemblages have the advantage that the
connecting faces between the sub-assemblages can be placed
away from the critical frame regions; however, linear Document 10 pages
elements are generally preferred because of the difficulties DUCTILITY REQUIREMENTS
associated with forming, handling, and erecting spatial
FOR BUILDINGS
You're Reading a Preview
elements. The use of linear elements generally means
placing the connecting faces at the beam-column junctions. Subin Babu George
The beams can be seated on corbels
Uploadat the columns,
your for ease
documents to download. No ratings yet
of construction and to aid the shear transfer from the beam to
the column. The beam-column joints accomplished in this
way are hinged. However, rigid beam-column connections
OR
are used in some cases, when the continuity of longitudinal reinforcement through the beam-column
Document 303 pages
joint needs to be ensured. The components of a precast reinforced concrete frame are shown in Figure
Become
SLAB-COLUMN SYSTEMS WITHa Scribd
SHEAR member
WALLS for full access. Your rc-ductility due to EQ
first 30lateral
These systems rely on shear walls to sustain days are
loadfree.
effects, whereas the slab-column structure nfaayed
resists mainly gravity loads. There are two main systems in this category: 100% (1)
Lift-slab system with walls
Document 19 pages
CE2306-NOL
H S Vishwanath Shastry
No ratings yet
Document 3 pages
Activity 1 in Pre-stressed
Francis Prince Artiaga
This website stores data such as cookies to enable essential site functionality, as well as marketing, personalization, and analytics. By remaining on this website you indicate your consent. Privacy Policy
No ratings yet
EN Upload
tendons that pass through ducts in the columns at the floor level and along the gaps left between
adjacent slabs. AfterWhat is Scribd? the gaps
pre-stressing, Ebooks Audiobooks
between the Magazines
slabs are filled Podcastsand theSheet music
with in situ concrete Documents Snapshots
tendons then become bonded with the spans. Seismic loads are resisted mainly by the shear walls
(precast or cast-in-place) positioned between the columns at appropriate locations.
Document 89 pages
Document 12 pages
Document 12 pages
Document 13 pages
6
precast systems
paramarthasom1974
No ratings yet
Precast Walls
Document 29 pages
1 Introduction c
thuaiyaalhinai
No ratings yet
Document 15 pages
BUILDING CONSTRUCTION
PRESENTATION 1
Nidhi Mehta
You're Reading a Preview No ratings yet
OR Document 23 pages
Elementary Design of
Become a Scribd member for full access. Your Structures 2015
first 30 days are free. Brian Masogoyi N
No ratings yet
Elementary Design of
Structures
7 NADS UG
100% (1)
Document 7 pages
1-s2.0-S1877705817305878-
main
Ema Emilia
No ratings yet
Document 19 pages
This website stores data such as cookies to enable essential site functionality, as well as marketing, personalization, and analytics. By remaining on this website you indicate your consent. Privacy Policy
EN Upload
Document 3 pages
8
Ebook 294 pages
Reinforced Concrete
Buildings: Behavior and…
Ahmad A. Hamid
2
of joints in prefabricated structures
Ebook 506 pages
Document 16 pages
Lecture 01
Fritzie Vega
No ratings yet
Document 19 pages
Document 50 pages
icpi
anmol
This website stores data such as cookies to enable essential site functionality, as well as marketing, personalization, and analytics. By remaining on this website you indicate your consent. Privacy Policy
No ratings yet
EN Upload
If architectural requirements dictate more-closely spaced joints, false joints can be used to achieve
a similar visual What
effect.is Scribd? Ebooks Audiobooks Magazines Podcasts Sheet music Documents Snapshots
Weathering of the building facade can be controlled to a large extent by careful joint location.
Recessing the sealant in the joint, or use of an open-drained system, will minimize concentrated
rainwater runoff and water-stain patterns.
A nominal joint width of 20 mm will usually be satisfactory for most conditions and is the
recommended design starting point. Document 62 pages
Document 41 pages
10
17-10-23 Inhabit -
Presentation Glass…
BINAZIR
No ratings yet
Difficult to maintain and/or
replace.
Time-consuming while erecting.
Document 2 pages
These joints are simple, economical and are most suited to low-rise construction (see Figure 3).They are
Uploadsealant
sealed by a single run of gun-applied your documents
close to thetoexterior
download.
surface of the joint. A backing-rod
forms the rear of the sealant. The external face seal should, where practical, be supplemented by a seal
near the inside face of the panel.
OR Document 14 pages
1502957399lectrure_5_KUE
Become a Scribd member for full access. Your T
first 30 days are free. Yashwant Choudhary
No ratings yet
Document 89 pages
Sample BOQ
kanishka
No ratings yet
Monique Frize-Ethics,
Research Methods and…
11 EliasA.Tiongkiao
No ratings yet
2014-scheme-abd-
syllabus_12-11-2017 (1).pdf
Nikhil Joshi
No ratings yet
Document 6 pages
This website stores data such as cookies to enable essential site functionality, as well as marketing, personalization, and analytics. By remaining on this website you indicate your consent. Privacy Policy
EN Upload
Document 12 pages
19 Stone Columns
What is Scribd? Ebooks Audiobooks Magazines Podcasts Sheet music Documents Snapshots alexjos1
No ratings yet
Document 1 page
12
Document 3 pages
Fire Resistance Assembly
Chart
Asif Rahman
UV light. No ratings yet
For face-sealed joints the sealant should have a stable color, be non-staining and resistant to pickup
of dirt.
4.2 Sealant Types
Field-moulded sealants are available in the following types:
Document 5 pages
Poly-sulphide sealants (two-part)
Note: silicone sealants should be avoided where possible as they stain the concrete surface and cannot No ratings yet
be painted.
4.3 Joint Design and Sealant Application
To ensure the joint and sealant give satisfactory performance, the following points should be noted (see
also Figure 5): Document 90 pages
1906003-Digital Signal
Processing Lab Manual
You're Reading a Preview
Rajesh
Upload your documents to download. No ratings yet
OR
Figure 5 Document 7 pages
Correct joint preparation
Become a Scribd member for full access. Your Compaction Grouting -
Correct sealant-backing systems
Correct joint geometry first 30 days are free. Karst Guide Specification
Sufficient curing time. yoyo
5 Fires Rating of Joints No ratings yet
Continue for Free
External cladding may be required to have a specified Fire Resistance Level (FRL). Cladding panels
will usually be designed or tested to meet these requirements in accordance with Section 5 of AS 3600.
Most sealant manufacturers produce sealants that are designed to provide resistance to fire. The joint
details and sealants should be designed and applied in accordance with the manufacturer‘s
recommendations to give the required level of fire resistance. Document 6 pages
Document 35 pages
Tonio,Lowie Jay -
13 Assignment No. 1.docx
Lowie Torres Tonio
No ratings yet
Document 15 pages
Document 26 pages
PhD in Data
Communications &…
Ganesh Alessandro Gana
No ratings yet
Document 5 pages
Resume-Rahul Sah2
Rahul Sah
This website stores data such as cookies to enable essential site functionality, as well as marketing, personalization, and analytics. By remaining on this website you indicate your consent. Privacy Policy
No ratings yet
EN Upload
Document 14 pages
BS-00812-114-1989-2011
KEVIN
No ratings yet
Document 1 page
OR
Document 26 pages
Controlling Machinery
Induced Underwater Nois…
pal_malay
No ratings yet
Document 3 pages
14
Fore Poling
mypenta2008
No ratings yet
Document 2 pages
aesthetic considerations in
design
Naresh Kumar
No ratings yet
OR
15
This website stores data such as cookies to enable essential site functionality, as well as marketing, personalization, and analytics. By remaining on this website you indicate your consent. Privacy Policy
EN Upload
What is Scribd? Ebooks Audiobooks Magazines Podcasts Sheet music Documents Snapshots
OR
16
17
This website stores data such as cookies to enable essential site functionality, as well as marketing, personalization, and analytics. By remaining on this website you indicate your consent. Privacy Policy
EN Upload
Fluid-fill Concrete
Whatsimplifies
Fluid mortar or concrete is Scribd? the process
Ebooksof layingAudiobooks Magazines
pipe and cable by Podcasts
surrounding the Sheet music
pipe or cable Documents Snapshots
with a tightly packed shell that provides protection from the elements, prevents settling, and enables
crews to work quickly.
Roller-compacted Concrete
Compacted in place and cured, roller-compacted concrete is a zero slump concrete with the abrasion
resistance to withstand high velocity water — making it the material of choice for spillways and other
infrastructure subject to high flow conditions. It represents a competitive solution in terms of cost and
durability when compared to asphalt.
Self-consolidating Concrete (SCC)
SCC has very high flow; therefore, it is self-leveling, eliminating the need for vibration. Due to the
super plasticizers used — chemical admixtures that impart very high flow — SCC exhibits very high
compaction as a result of its low air content. Consequently, SCC can have very high strengths,
exceeding 50MPa.
Pervious Concrete
Because of its unique design mix, pervious concrete is a highly porous material that allows water,
particularly rainwater, to filter through, reduces flooding and heat concentration by up to 4°C, and helps
18
19
This website stores data such as cookies to enable essential site functionality, as well as marketing, personalization, and analytics. By remaining on this website you indicate your consent. Privacy Policy
EN Upload
the bin. The speed of the belts is connected to a feeder in a cement bin, and all three materials drop
down into a mixer. FlowWhatmeters
is Scribd? Ebooks
control the introductionAudiobooks Magazines
of water and admixtures. Podcasts Sheet music Documents Snapshots
Plant Styles, etc.
Concrete batch plants come in a variety of styles and configurations designed to accommodate a variety
of markets, technical and environmental considerations.
Portable Plants In general, they have a cement silo and an overhead bin for sand or one or two
coarse aggregates.
Permanent Plants The plant operates from same location for a relatively long period of time.
Large quantities of materials of greater variety are stored at the plant. The plant will tend to have
larger overhead storage and may have two lanes to permit batching two trucks at the same time.
Plants may be also classified as
High profile - The traditional stack up plant is a tall plant that has aggregate and cement storage
bins that feed into batchers or weigh hoppers by gravity.
Low profile - The aggregate weigh hoppers are near the ground with belts to elevate the aggregate
to load the mixer.
Quality
You're Reading a Preview
What does ‗quality‘ mean when applied to concrete?
It is very easy to say that a product is ‗top quality‘ but what does this really mean?
Upload
For concrete, ‗quality‘ has a specific your documents
meaning. It must meettothe
download.
relevant British Standards (eg BS 8500)
and its quality is independently verified. All CEMEX concrete is certified by QSRMC, the quality
scheme for ready mixed concrete. QSRMC provided ISO 9001 and product conformity certification for
OR
the design, production and supply of ready mixed concrete.
To ensure that concrete meets the high demands imposed in constructing bridges, concrete-framed
buildings and other complex structures,
Become CEMEX‘s
a Scribd member in-house
for fulltechnical
access. department
Your provides advice and
carries out standard tests. The most common of these is the cube test. A small concrete cube is formed
using a sample of concrete at the constructionfirst 30site
days
andare free.
when set it is crushed in a laboratory. The force
needed to crush the concrete determines its strength. This force is commonly described in Newton‘s and
so the strength of different concrete mixes can also be expressed in Newton.
Continue for Free
Concrete for a path or simple footings need not be as strong as that used in a bridge but it must still be
‗fit for purpose‘. In other words it must still be of an equally high ‗quality‘. So having hi gh quality
concrete is just as important for a small project as for a massive civil engineering site.
All CEMEX concrete is produced to the same high quality, irrespective of the end use. As one of the
World‘s leading suppliers of building materials CEMEX concrete plants benefit from the very best
computerized systems, ensuring consistent accuracy in measuring the proportions of cement, aggregate
and special additives required for each mix. CEMEX is also a major manufacturer of cement and
produces a range of products which can be blended to give the best handling and setting characteristics
under all conditions.
Such refinements cannot be achieved with any degree of consistency using a small site mixer and other
forms of site mixing may not be QSRMC certified.
Quality Assurance
PCI has three different certification programs:
Plant Certification – First introduced in 1967, covers the overall management of the quality system
within precast/prestressed plants.
20
Personnel Training and Certification – First introduced in 1985, covers the qualification and
certifications of the people doing the product inspections and managing the Quality Assurance
departments within precast/prestressed plants.
Erectors Qualification/Certification – First introduced in 1999, covers the training and qualification of
field services personnel.
PRECAST CONCRETE CONSTRUCTION AND SEISMIC DESIGN
There is a general concern regarding the seismic performance of precast construction. It is noticed that
large panel construction performs better than frame system. However, in areas of high seismic risk,
structures must be designed to respond safely to the dynamic forces imparted into the structure.
Innovations in joint design are improving the connection systems in precast concrete structures and
making them increasingly suitable for use in such areas.
OR
21
This website stores data such as cookies to enable essential site functionality, as well as marketing, personalization, and analytics. By remaining on this website you indicate your consent. Privacy Policy
EN Upload
What is Scribd?
Use of equipments
Ebooks
in precast
Audiobooks Magazines
prefabricated
Podcasts Sheet music Documents Snapshots
3
structure, Productivity analysis
Formwork
Formwork is the term given to either temporary or permanent molds into which concrete or similar
materials are poured. In the context of concrete construction, the false work supports the shuttering
moulds.
Formwork and concrete form types
Formwork comes in several types:
1. Traditional timber formwork. The formwork is built on site out of timber and plywood or moisture-
resistant particleboard. It is easy to produce but time-consuming for larger structures, and the
You're Reading a Preview
plywood facing has a relatively short lifespan. It is still used extensively where the labour costs are
lower than the costs for procuring re-usable formwork. It is also the most flexible type of
Upload
formwork, so even where other yourare
systems documents to download.
in use, complicated sections may use it.
2. Engineered Formwork System. This formwork is built out of prefabricated modules with a metal
frame (usually steel or aluminium) and covered OR on the application (concrete) side with material
having the wanted surface structure (steel, aluminum, timber, etc.). The two major advantages of
formwork systems, compared to traditional timber formwork, are speed of construction (modular
Become a Scribd member for full access. Your
systems pin, clip, or screw together quickly) and lower life-cycle costs (barring major force, the
frame is almost indestructible, whilefirst 30 days are
the covering free.of wood; may have to be replaced after a
if made
few - or a few dozen - uses, but if the covering is made with steel or aluminium the form can
achieve up to two thousand uses dependingContinue for Freethe applications).
on care and
3. Re-usable plastic formwork. These interlocking and modular systems are used to build widely
variable, but relatively simple, concrete structures. The panels are lightweight and very robust.
They are especially suited for low-cost, mass housing schemes.
4. Permanent Insulated Formwork. This formwork is assembled on site, usually out of insulating
concrete forms (ICF). The formwork stays in place after the concrete has cured, and may provide
advantages in terms of speed, strength, superior thermal and acoustic insulation, space to run
utilities within the EPS layer, and integrated furring strip for cladding finishes.
Stay-In-Place structural formwork systems. This formwork is assembled on site, usually out of
prefabricated fiber-reinforced plastic forms. These are in the shape of hollow tubes, and are usually
used for columns and piers. The formwork stays in place after the concrete has cured and acts as axial
and shear reinforcement, as well as serving to confine the concrete and prevent against environmental
effects, such as corrosion and freeze-thaw cycles.
22
A B C D
Construction speed 3 flats/day 4 flats/day 5 flats/day 6 flats/day
Period of const. 23 months 18.7 months 16.2 months 14.2 months
Forming area 741.9 989.2 1236.5 1483.8
Misc formwork 55.5 55.5 55.5 55.5
Total formwork to be 797.4 1044.7 1292 1539
ordered
Cost of formwork 14353200 18804600 23256000 27707400
Two third of the 9568800 12536400 1550400 18471600
loaded cost
Profit & Overhead 1435320 1880460 2325600 2770740
15%
Total Rs. You're Reading
11004120 14416860 a Preview
17829600 21242340
Cost per flat, Rs 9825 12872 15919 18966
Upload your documents to download.
Note:
Construction period is calculated as follows:
Average 22 pouring of concrete are considered perOR month.
About 3 months are required for mobilization and getting plinths ready.
About 3 months are required for finishing.
Become a Scribd member for full access. Your
Cost of formwork = $ 360; dollar Exchange Rate = Rs50; No of flats = 1120
first 30 days are free.
(Weight of aluminium formwork = 24 kg/m²).
Formwork Design Criteria
Formwork components can be designed and Continue for Free
constructed in many materials, such as plywood, wood,
steel, aluminum, and fiber composites. Frequently, a mixture of materials is used (Figure 7.31). Steel,
aluminum, and fiber composites are more likely to be parts of manufactured components or systems
that are rated or designed by the producer and may be supplied predesigned on a rental basis for the
project needs. Forms intended to be job built are often made of wood and require design by the
construction engineer associated with the project or by a consultant to the contractor. The examples in
this chapter illustrate the latter case for wood components designed by allowable stress methods. To
understand the examples, it is necessary to provide some of the essentials of wood design. Readers
undertaking the design of formwork in wood are advised to obtain and follow the more comprehensive
specifications in the National Design Specification for Wood Construction (AFPA, 2005) and the
Plywood Design Specification (APA, 1997).
Most of the lumber used in formwork is surfaced on four sides (S4S) to achieve its final dimensions as
shown in Table 7.3. The S4S dimensions are smaller than the nominal sizes referred to in the table.
23
This website stores data such as cookies to enable essential site functionality, as well as marketing, personalization, and analytics. By remaining on this website you indicate your consent. Privacy Policy
EN Upload
Except for classification purposes, it is the actual dimensions and actual section properties that are used
in design. A secondWhat is Scribd?
set of sizes known as Ebooks
rough lumberAudiobooks
(not shown inMagazines
Table 7.3) hasPodcasts Sheet music
slightly larger Documents Snapshots
dimensions but is still not the full nominal size. Rough lumber sizes are sometimes used in heavy false
work-supporting forms.
Plywood is frequently used as the surface layer of the formwork in contact with the fresh concrete.
Plywood has different strengths and stiffness depending on the direction of its span relative to the
direction of the grain in the outer layers. The equivalent section, considering the varying elastic
modulus and strength between parallel-to-grain loading and side-grain loading, is illustrated by
equivalent sections in Figure 7.32. When the grain of the outer layers is parallel to the span direction,
the strength and stiffness are greatest (Figure 7.33). Many types of plywood are available. Section
properties for B-B Ply form, Class I, plywood, one of the most frequently selected types for moderate
reuse in formwork, are given in Table 7.4. Note that, due to the alternating grain directions in the
plywood veneer layers, conventional methods for calculating section properties of homogeneous,
isotropic sections do not apply.
The section properties given in Table 7.4 have been determined by considering the varying properties in
You're Reading a Preview
the different layers as well as the complications of weakness induced by the tendency of fibers to roll
over each other in shear lateral to the grain, or rolling shear (Figure 7.34). For these reasons, use the
listed value of S only in bending calculations,
Upload use I only to
your documents deflection calculations, and use Ib/Q, the
fordownload.
rolling shear constant, for shear calculations.
The basic design values for wood and for plywood of the species, grades, sizes, and types frequently
used in formwork are listed in Table 7.5. The species OR and grades readily available in the area of the
project should always be verified. Contractors also often have stocks of form lumber for reuse from
previous projects. Such lumber should always be inspected
Become a Scribd member for full for defects
access.as the material is assembled, and
Your
unsuitable pieces must be rejected.
first 30 days are free.
1 ASD Adjustment Factors for Lumber Stresses
The AFPA-NDS (AFPA, 2005) provides for adjustment of the lumber reference design values ( F ),
such as those given in Table 7.5, by a seriesContinue for Free
of multipliers yielding the allowable design values ( F ′) for
stress as follows:
Bending:
24
Some of the adjustment factors (in brackets) only apply to truss members (buckling stiffness factor,
CT ), when the member is incised (incising factor, Ci) or when the temperature is >100 °F (temperature
factor,
Ct ), and thus have only rare uses in formwork. The remaining factors are discussed below.
2 Load Duration Factor ( CD )
The adjustment for load duration ( CD) reflects the ability of wood to exhibit increased strength under
shorter periods of loading. The following values may be applied for the indicated cumulative maximum
load durations:
CD = 0.9 Load duration > 10 year
CD = 1.0 2 months < load duration ≤ 10 year
CD = 1.15 7 days < load duration ≤ 2 months
CD = 1.25 Load duration ≤ 7 days
CD = 1.6 Wind/earthquake
CD = 2.0 Impact
For most formwork, an adjustment of CD = 1.25 is applied; however, when the components are reused
You're Reading a Preview
for longer cumulative durations at maximum level, CD should be appropriately reduced.
3 Moisture Factor (CM )
Upload
Wood gains in strength as it loses your documents
moisture to download.
in a range below the fiber saturation point (about 30%
moisture content). The basic design values are established for lumber that has moisture content of 19%
or less, typical of air-dried lumber. When the exposure is such that the wood moisture content will
OR
exceed 19% for an extended period of time, the design values should be multiplied by the CM values
indicated in Table 7.5.
4 Size Factor (CF ) Become a Scribd member for full access. Your
Tests indicate that member overall size first
affects
30 the
daysfailure stress. To account for these variations, the
are free.
size factor (CF ) as shown in Table 7.6 is applied to the bending and compression basic design values.
Note that the size factor does not apply to the basic design values of Southern Pine, whose basic design
Continue
values in Table 7.5 are pre adjusted to reflect most offor
theFree
size effect.
5 Flat-Use Factor ( Cf u)
Lumber loaded on its wide face and bending about its weak axis ( y– y) exhibits a slightly higher failure
stress. To reflect these variations, the flat-use factor (Cfu) adjustments in Table 7.6 may be applied to
the basic design values for bending stress.
6 Beam-Stability Factor ( CL )
The AFPA-NDS (AFPA, 2005) provides equations for determining the beam-stability factor ( CL), an
adjustment less than 1.0, when the compression edge of a beam may become unstable. For sawn
lumber, however, the AFPA-NDS also provides prescriptive d /b ratios, based on nominal dimensions
and lateral support conditions where the member may be assumed to be stable and no reduction for CL
is needed, as follows:
• d /b = 2 to 1 or less, no lateral support is necessary.
• d /b = 3 to 1 or 4 to 1, ends shall be held in position against lateral rotation or displacement by
25
This website stores data such as cookies to enable essential site functionality, as well as marketing, personalization, and analytics. By remaining on this website you indicate your consent. Privacy Policy
EN Upload
where:
Fc* = tabulated compression design value multiplied by all applicable adjustment factor except CP .
c = 0.8 (for sawn lumber).
You're Reading a Preview
FcE = 0.822 E ′min/(le/d )2, where le is the effective length, and le/d is the larger of the slenderness
ratios about the possible buckling axes; the value of le/d shall not normally exceed 50, except for short
Upload your documents to download.
duration loadings during construction when it shall not exceed 75.
8 Bearing-Area Factor ( Cb)
OR perpendicular to the grain of the wood —that is,
The bearing-area factor ( Cb) is for the case of bearing
bearing on the side grain. The bearing factor is normally taken as 1.0; however, if the bearing area is
more than 3 in. from the endBecome a Scribd and
of the member member for full
less than 6 in.access. Your
in length as measured along the grain,
then the following increase factor may be applied:
first 30 days are free.
26
allowable stresses listed for B-B Ply form, Class I, plywood in Table 7.3. The calculation of plywood
deflection can be refined to include both the bending deflection and the shear deflection. In this
presentation, for simplicity, only the bending deflection is considered, but the lower value of the
plywood elastic modulus will be used to partially compensate for this. Consult APA (2004) for
procedures for calculating the shear deflection component.
Formwork Design
Most components of a form system can be subdivided into members that are primarily bending
elements (sheathing, joists, studs, stringers, and Wales) and members that are primarily tension or
compression elements (shores, braces, etc.). In addition, there are numerous details to design, such as
connections (Figure 7.35), hangers, and footings or mudsills (Figure 7.36). The following sections
provide example designs, in wood, of the main members of an elevated floor slab form and a vertical
wall form to convey a sense of the procedures involved. After the design is complete, the formwork
material specifications, member layout, member sizes, connection details, erection procedures, and use
limitations should be conveyed by means of drawings with appropriate notes to the field workers who
will fabricate and erect the form.
You're Reading a Preview
7.6.1 Determination of Resultants from Loads
The bending members of a wood form system are either single-span or continuous multiple-span
elements, usually with bearingUpload
supports
youras documents
illustrated into Figure 7.37. Although the members may
download.
sometimes have more than three spans, the benefits from considering more than three span conditions
are very limited. Many of the member loads are uniform. In other cases, the loadings may be a series of
closely spaced concentrated loads that can oftenORbe approximated as a uniform load if there is a
sufficient number in a span. Figure 7.37 also provides the formulas for the maximum moments, shears,
and deflections for the uniformly
Become loaded one-,
a Scribd two-, and
member forthree-span
full access.cases.
Your It should be noted that the
formulas for calculating the maximum shear force are modified to calculate the shear at a distance d
first 30 days are free.
from the face of the supporting member, where d is the depth of the member being designed and lb is
the length of bearing at the supporting member. In wood design, the AFPA-NDS provides that loads
Continue
within a distance d of the face of the support can be for Free when designing for shear if the member
neglected
is loaded on one face and supported on the opposite face or edge. However, in cases where the member
is notched or connection is made in the web, as by bolting, other AFPA-NDS special provisions should
be consulted which, in effect, magnify the shear force used for design.
7.6.2 Fundamental Relations between Resultants and Stresses
From mechanics of solids, the following relationships apply to the elastic design of wood elements:
Bending of beams or plywood:
=
Shear of solid rectangular beams:
3
=
2
27
This website stores data such as cookies to enable essential site functionality, as well as marketing, personalization, and analytics. By remaining on this website you indicate your consent. Privacy Policy
EN Upload
What is Scribd? Ebooks Audiobooks Magazines Podcasts Sheet music Documents Snapshots
OR
Shear of plywood:
= =
28
29
This website stores data such as cookies to enable essential site functionality, as well as marketing, personalization, and analytics. By remaining on this website you indicate your consent. Privacy Policy
EN Upload
for on rail travel, transverse carriage, drives over the tilting tables
What
• production line: fab. is Scribd?
TECHNOPLAN, Ebooks
steel surface inAudiobooks Magazines
very good condition, Podcasts
incl. shuttering Sheet music Documents Snapshots
dim.: 52,50 x 4,20 m
• stair moulds: fab. GÄRTNER, for straight and spiral stairs
incl. mould for front door stair
Fully Automatic Pallets Circulating Plant
Sandwich-, lightweight concrete-, solid walls, solid floors
• Manufacturer: VOLLERT – WECKENMANN – UNITECHNIK
• Year of construction: approx. 1998 (as good as new)
• Performance: sandwich -, lightweight concrete-, solid walls, solid floors
• 49 pallets, dim. 12,50 x 3,50 (effec. dim.), excellent steel surface
• Perfectly flat
• Fully automatic shelf operating device
• Complete drying chamber; 45 storing positions; incl. housing in steel construction
• Fully automatic shuttering robot
You're Reading a Preview
• Automatic cleaning and oiling device for pallets
• 2-chamber concrete distributor for lightweight concrete and standard concrete
• Frequency adjustable shaking-Upload
station your
for concrete compacting;
documents man. NETTER
to download.
• Vibration- and smoothing facility
• Automatic power trowel, gantry construction
• Hydraulic tilting station for pallets OR
• 6 heavy load trailers for rail travel; cable control; man. NUSPL
• handling crane for shuttering; man. ABUS
Become a Scribd member for full access. Your
• working station for manual shuttering integration
first 30 days are free.
• Cleaning and transportation device for magnets and shuttering
• Extensive magnets and shuttering system for walls and floors
Continue
• Extensive circulation equipment; f riction wheels, for Free traveler, rolls
transverse
• Fully automatic main computer control system; man. UNITECHNIK/SIEMENS
Fully Automatic Concrete Mixing Plant
• Manufacturer: EIRICH - SIEMENS
• Year of construction: approx. 1996
• Performance: 2,0 m³ concrete e ffec. Output per charge
->approx. 120 m³/ h
Consisting of the following main components:
• Compulsory mixer with swirl; type: DZV29
• Automatic hygrometer
• 8 chamber steel silo for aggregates storage
• 3 cement silos incl. screw conveyor
• feed hopper
30
31
This website stores data such as cookies to enable essential site functionality, as well as marketing, personalization, and analytics. By remaining on this website you indicate your consent. Privacy Policy
EN Upload
Gantry Crane
• Manufacturer: DEMAGWhat –
is Scribd?
LIEBHERR Ebooks Audiobooks Magazines Podcasts Sheet music Documents Snapshots
• Year of construction: approx. 1994
• Lifting capacity: 10 to
• Span: 25.000 mm
• Cantilever: 8.000 mm, each side
• Performance: crane: 5,0 / 40 m/min
Trolley: 8,0 / 30 m/min
Lifting unit: 0,5 / 5,0 m/min
• Incl. radio control and track system, approx. 120 m track system
FILIGREE - floor production
• Manufacturer: AVERMANN
• Length: approx. 125 m
• Operation width: approx. 2,49 m
• Lateral shuttering: approx. 7 cm
• Steel cover: good condition
You're Reading a Preview
• Incl. concrete distributor
• Incl. plotter Upload your documents to download.
• Incl. cleaning and oiling device
• incl. 2 transversal transporter
Transportation Racks OR
• Manufacturer: NUSPL
• Year of construction: approx. 1998
Become
• Lifting capacity: approx. 25 to a Scribd member for full access. Your
first
• Dimensions: 2,50 x 7,50 m / 9,0 m x 2,20 m 30 days are free.
• Pieces: approx. 30 pieces
• Incl. fixation anchor
Continue for Free
Heavy Load Trailer
• Manufacturer: NUSPL
• Year of construction: approx. 1998
• Load capacity: approx. 25 to
• dim.: 6,0 m x 2,5 m
• Incl. transportation rack for wall panels
Cutting Machine for FILIGREE- Lattice Girder
• Manufacturer: FILZMOSER
• Type: Gitterträgerschere TA
• Year of construction: approx. 1995
• cutting performance: - up to Ø 16 mm -> 1 piece
- up to Ø 10 mm -> 4 pieces
32
Cement silo
• Manufacturer: STANELLE
• Year of construction: approx. 2005
• Volume: approx. 40 m3
• Incl. complete silo equipment
• Ladder and safety cage
Hydraulic Ring- And Cone Clamp
• Manufacturer: PROBST / RKZ - H
• Year of construction: approx. 1995
• Opening range: 600 - 1.500 mm
Hydraulic Turning Device for Concrete Elements
• Manufacturer: PROBST
• Year of construction: approx. 1995
• Opening range: 500 - 1.800 mm
• rotating range: 360° endless
Fork Lifter
You're Reading a Preview
• Manufacturer: LINDE / CLARK
• Load capacity: 3,0 to; 4,0 to; 4,5 to your documents to download.
Upload
OR
33
This website stores data such as cookies to enable essential site functionality, as well as marketing, personalization, and analytics. By remaining on this website you indicate your consent. Privacy Policy
EN Upload
In the market for a new facility or addition but concerned about construction costs? Look to permanent
modular construction (PMC) as a way to acquire a new building in a tough economy. This alternative
construction technique yields faster completion times, improved efficiency, cleaner materials, and better
quality control.
Overview of Modular Construction
The speed with which a building is completed is the key advantage of modular construction. Because
site preparation and module fabrication processes occur simultaneously, the overall project construction
timeline is decreased by 30 to 50 percent. Modular construction has to adhere to the same building code
requirements as traditional construction methods, and the same building materials and standards are
You're Reading a Preview
utilized to fabricate each module. All modules meet the building, safety and occupancy code
requirements (typically International Building Code) and in many instances, modular buildings exceed
Uploadare
local building specifications. Designs your documents
flexible, to download.
expandable and easily reconfigured, so they may be
adapted to meet the changing needs of the healthcare facility over time. Their durable, secure and
relocatable characteristics make them ideal for both OR temporary and permanent applications that will
meet the requirements of healthcare organizations over a longer time horizon.
The old ―square box‖ or ―cookiecutter‖ building analogy no longer applies to today‘s modular
buildings. Today, designersBecome a Scribd
and builders havemember
much morefor flexibility
full access.
to Your
design using the highest quality
firstor30
materials and finishes. They are not limited daysto
forced are free.
compromise aesthetics for overall space or time
efficiencies.
Modules and building components are built in a controlled environment, therefore mitigating risks to
Continue for Free
the project due to volatile weather, material shortages, theft and vandalism. Prefabricated components
and modules are built in a factory and installed on-site to expedite assembly time and create less
disruption to the site environment during the installation phase. This differs from conventional
construction by minimizing noise and debris from the existing patient services and creating a safer work
and patient environment during construction. The interior finishes can be selected from a variety of
options and are consistent with those of conventional construction methods. Facility planners can easily
choose from existing blueprints for examination rooms, patient treatment areas, nurses‘ stations and
waiting rooms; or the building modules can be constructed in accordance with their already established
design criteria.
Modular construction enhances quality assurance because QA is built into every step of the process.
Quality control is assured with multiple inspections performed at each phase. The building components
are inspected and approved by third-party inspectors who are usually agents of the state, not the
locality.
34
This unique building technique enhances quality and simplifies logistics on the job site. Scheduling,
trade coordination and construction sequences are all streamlined. Modular methodologies build
technical innovation into a repeatable construction process that utilizes proven, standardized practices
and process efficiencies. The result is greater reliability and higher quality than conventional site-built
construction projects, particularly in areas where a skilled labor force is unavailable. This process truly
exemplifies the philosophies of ―best practices.‖
Many modular healthcare structures have been recognized for their design excellence, as architects and
interior designers often work closely with modular consultants and manufacturers to ensure optimum
design outcomes for the client. Again, the days of the boring boxy structure are long gone. Permanent
modular buildings can be built as single one-story structures or intricate multiple-story buildings.
When it comes to the internal space, interior designers and architects collaborate with the client to
develop the architectural interior finishes and patient and workflow environments that are consistent for
each medical application. Designs can be altered for specific services. For example, considerations are
made for additional floor loading, and provisions are incorporated into building design to accommodate
the weight of heavy dialysis water treatment equipment in dialysis treatment centers. Depending on the
You're Reading a Preview
client‘s needs, the modular builder can be responsible for just a few or all of the prefabricated interiors
of the modules.
Lastly, the new or renovated structure
Uploadcan be documents
your designed to correspond with the surrounding environment
to download.
and existing buildings and hospitals. Exterior architectural finishes, such as brick, stucco and exposed
aggregate architectural panels, can complement those of neighboring buildings on the healthcare
campus. OR
A DIFFERENT CONSTRUCTION PROCESS
PMC is a method of construction,
Become notaaScribd
building type. Itfor
member greatly differs from
full access. Yourtemporary buildings, such
as construction trailers or mobile homes.
first 30 days are free.
―These are custom-designed commercial buildings just like their site- built counterparts,‖ explains Phil
Slingerlands, COO of Warrior Group, a firm specializing in modular construction. ―Using PMC does
not change the design, structural system, or Continue for Freeoptions available to the owner and architect.
finish materials
The only difference is in the method of construction.‖
After the design is finalized with an architect, construction plans are sent to a factory where the
majority of the building is erected. PMC uses prefabricated elements for as many building components
as possible. Everything from walls and mechanical systems to painting and carpet can be completed on
the assembly line.
―The difference is that 60% to 90% of modular buildings are completed offsite in a controlled
production environment, including all MEP, fixtures, and interior finishes,‖ says Tom Hardiman,
executive director of the Modular Building Institute (MBI).
While modules are assembled at the factory, site work can begin at the same time, such as laying the
foundation or prepping utility connections. This greatly decreases the time needed for total construction.
Modular buildings are often completed 30-50% faster than conventional structures.
35
This website stores data such as cookies to enable essential site functionality, as well as marketing, personalization, and analytics. By remaining on this website you indicate your consent. Privacy Policy
EN Upload
Once the modules are ready, they are shipped to the site and fastened together. The final construction
What is Scribd?
stage includes completing Ebooks
exterior systems such as Audiobooks Magazines
cladding and roofing Podcasts
components Sheet music
and internal Documents Snapshots
spaces like lobbies, stairwells, and elevator shafts.
The beauty of the finished building is that occupants will not be able to tell how the structure was built.
―The art of PMC is to make the modularity disappear once you complete the building,‖ says Sue
Johnson, chief development officer for Warrior Group.
SERVING MULTIPLE MARKETS
This technique can produce a single building, an addition, or a campus setting, but it is most beneficial
for projects with highly repetitive spaces. Think of duplicate rooms common to schools, dorms, offices,
military housing, senior living, and hotels.
Modular construction has also been used for standalone buildings, such as banks, chain restaurants,
satellite bureaus, and retail. Any building without irregular layouts or large expanses will benefit.
The only limitations to size are those dictated by material use and code. For example, the world‘s tallest
modular building in the U.K. is over 25 stories. Buildings can occupy any square footage specified and
are easy to expand. Modular construction is also a great way to add an addition onto a traditional
building.
You're Reading a Preview
THE CORE BENEFITS
From factory precision to faster installation,
Upload modular to
your documents construction
download. offers an attractive range of
advantages:
1) Scheduling: One of the greatest benefits is the ability to dramatically reduce the time needed for
construction. Factory efficiencies allow buildingOR components to be completed quickly and without
weather delays. No more contracting with multiple crews – the factory has all of the key player‘s onsite
to handle multiple building Become
requirements.
a Scribd member for full access. Your
This makes modular construction suitable for owners who need buildings quickly, properties with hard
first 30 days are free.
dates for occupancy, and areas where seasonal weather restricts or even halts construction.
2) Jobsite Improvement: Nearly completed modules ease the need for site equipment and staging
areas, making them ideal for complicated Continue for Free
sites. Perhaps your property is in a remote location or has
accessibility difficulties. You may be in an urban or campus setting and have a narrow building site.
Modular construction is likewise a great alternative for areas where an experienced or affordable labor
force is difficult to come by.
PMC affords a cleaner worksite with fewer disruptions. With the majority of work completed offsite,
issues such as noise, dust, debris, and weather complications are greatly reduced.
The lower numbers of people, equipment, and traffic at the worksite also decreases the number of
construction hazards. ―The chance for accidents and related liabilities caused by such a volume of
people and materials moving on, around, and of fsite every day is significantly reduced,‖ says Slinger
land.
3) Waste Reduction: Because the factory process decreases the potential for errors, material use is
more carefully monitored, Hardiman explains. By controlling inventory, resources and building
36
materials are better protected. An assembly line also offers more opportunities for recycling throughout
the process.
―PMC really works well with lean construction – it‘s engineered to cut out any construction waste,‖
says Johnson. ―For example, steel stud s are usually cut to a standard length and shipped to a jobsite
where they‘re cut to the needed size. Instead of wasting 2 feet of metal, the studs are created on the
factory line to the exact length required.‖
4) Quality Control : Just like a car assembly line, a prefabricated building module has built-in quality
checks. Modular building factories are dedicated to crafting highly effective buildings with inspections
at each station, eliminating on-the-fly decisions or unexpected complications that can occur in the field.
―The construction process is carefully engineered to create a sequence of steps that is repeated precisely
on every module,‖ Slingerland explains. ―This decreases the variability that can occur on a site -build
project.‖
After installation, capital improvements to extend the building‘s life, such as HVAC or
roofreplacements, can be made on the same schedule as a conventional building. The same maintenance
and inspection requirements common to traditional facilities will also apply to modular buildings.
You're Reading a Preview
5) Sustainability: As with traditional buildings, modular construction easily incorporates sustainability.
Specify the use of recycled materials, LED lighting, high-efficiency mechanical systems, and
sustainably harvested wood andUpload
low-flow fixtures
your just as you
documents normally would.
to download.
―We‘re seeing a shift toward high - performance, sustainable design,‖ says Maggie Hartley, director of
marketing for American Modular Systems. ―Energy efficiency over the lifespan of the building is a
definite priority. There‘s a reliance on mechanical OR systems, tight envelopes, ventilation, and smart
lighting to achieve energy savings.‖
While the process itself affords more aopportunities
Become Scribd member for sustainability, other
for full access. Yourgreen benefits include:
Improved IAQ – Moisture reduction, use of dry materials, and time for off-gassing result in fewer
first 30 days are free.
VOCs.
Compatible with LEED – Modular buildings can compete in the same categories as traditionally
built ones. They can even yield an Continue
advantageforinFree
credits for Sustainable Sites, Materials and
Resources, and Energy and Atmosphere.
Reusable – Whether you need a new layout or your building has been damaged, modular buildings
can be disassembled so individual modules can be replaced or refurbished.
Tighter Envelope – PMC typically results in a tighter envelope, which improves
energy efficiency. This is due to the durability required for transportation and the lack of weather
complications such as moisture and water intrusion.
Renewable Energy – Modular construction can accommodate alternative energy sources, from
solar panels to a geo exchange system. Buildings can also be designed so renewable energy can be
added down the road.
LIMITATIONS OF PMC
Modular construction isn‘t without its drawbacks. Much like choosing a sustainable building, the
decision to use modular construction must be made from the onset of design.
37
This website stores data such as cookies to enable essential site functionality, as well as marketing, personalization, and analytics. By remaining on this website you indicate your consent. Privacy Policy
EN Upload
―Using PMC changes the critical path for construction and, if not scheduled properly, you can easily
What is
lose the schedule benefits ofScribd?
PMC,‖ warnsEbooks
Slingerland.Audiobooks
Magazines Podcasts Sheet music Documents Snapshots
The advantages of PMC also wane conside rably if your intended building doesn‘t have repeating
spaces. The prefabrication of entire rooms lies at the heart of modular construction, so a building with
open expanses is not the best candidate.
―For example, an office building shell designed with un finished interiors and intended for multiple
tenants who would finish out their own individual space would not be a good option for PMC,‖
Slingerland adds.
Permanent vs. Temporary
Modular construction is an alternative to traditional construction only. It is not an extension of
temporary modular buildings, which meet a different purpose and offer separate benefits.
Permanent modular buildings are comparable to buildings strictly built onsite in terms of quality,
life span, and materials used for construction. They are not intended to be relocated, though
individual modules can be replaced.
Temporary buildings provide an affordable space that is mobile or relocatable. Clients are
38
additional options include lease purchase programs, conventional lease and other creative financing
options. Consulting with accounting and tax professionals regarding the potential accelerated
depreciation characteristics of modular structures is recommended.
Step Two: Design. Analyze all requirements specific to dialysis treatment centers and devise a clear
strategy and recommendations based on the design and budget. Develop a componentized approach that
incorporates value engineering, project efficiencies and alternative module configurations.
Step Three: Apply the concurrent construction process. Conventional construction is a linear process.
One step cannot begin until other steps have been completed. With concurrent construction, critical
steps in the construction process occur simultaneously. More than 50 percent of the construction occurs
off-site, in a factory-controlled environment. Site work and building preparations including grading,
foundations, utilities, paving and some landscaping happen while the building‘s modules are fabricated
in the factory.
Step Four: Deliver and install. Shipment of all modular components is coordinated and completed.
Additionally, the majority of the site work, including final grading, utility connections, sidewalks,
ramps, stairs and final landscaping is finished. The goal is to create pleasing aesthetics and coordinating
You're Reading a Preview
exterior elements that establish the facility harmoniously within its setting.
Step Five: Complete the interior finishes and finalize for occupancy. Interior finishes, such as
furnishings are completed on-site.
UploadFinally, the modulartobuilding
your documents consultant instructs the client on
download.
modular-specific maintenance, planning for future expansion and other specifics while a building
inspector conducts final code inspections and approvals.
Considering Modular Construction OR
Modular building is proving to be an outstanding choice for quality healthcare environments. According
to Architectural Record , accelerated
Become a construction
Scribd member methods have
for full been Your
access. employed since the 1960s and
now account for an estimated 40 percent of all building projects. The range of modular healthcare
first 30 days are free.
buildings existing today attests to the diversity and creativity that modular processes afford. Modular
construction is an attractive option to get dialysis treatment centers up and running quickly and
efficiently. Continue for Free
Fibonacci Series
The Fibonacci Series is a sequence of numbers first created by Leonardo Fibonacci (fi-bo-na-chee) in
1202. It is a deceptively simple series, but its ramifications and applications are nearly limitless. It has
fascinated and perplexed mathematicians for over 700 years, and nearly everyone who has worked with
it has added a new piece to the Fibonacci puzzle, a new tidbit of information about the series and how it
works. Fibonacci mathematics is a constantly expanding branch of number theory, with more and more
people being drawn into the complex subtleties of Fibonacci legacy.
The Fibonacci sequence is the series of numbers:
0, 1, 1, 2, 3, 5, 8, 13, 21, 34...
The next number is found by adding up the two numbers before it.
The 2 is found by adding the two numbers before it (1+1)
Similarly, the 3 is found by adding the two numbers before it (1+2),
39
This website stores data such as cookies to enable essential site functionality, as well as marketing, personalization, and analytics. By remaining on this website you indicate your consent. Privacy Policy