L3 May 2023 Time, WBS
L3 May 2023 Time, WBS
Economics
Dr Wesam Salah Alaloul
Civil & Environmental Engineering Department
Time management
▪ Activity scheduling
Many software tools (MS Project) do the job quite well (in a
deterministic manner)
They offer many outputs (GANTT Chart, PERT … etc)
Time management
A 2 4 8 4.3 1 1
days days days days day day
Time management
Network Logic Diagram
A B E
Start
Finish
D F
C
B
A E
Start Finish
C F
D
• Scheduling forces:
– Quantification of discrete effort
– Placement of tasks in proper relationship
25 01 08 15 22 29 05 12 19 26 05 12 19 26 02 09 16 23 30 07 14 21 28 04
WBS Description
5 Prototype
Behind
Schedule Time Now
Time Management
Critical Path Method Advantages
▪ Identifies activities that control the project length.
▪ Determines shortest time for completion.
▪ Identifies activities that are critical (i.e. cannot be delayed)
▪ Shows available float for non-critical activities.
▪ Allows evaluation of “what-if” scenarios.
▪ Allows monitoring & control of fast-track projects.
▪ With software can be resource loaded and leveled.
Time Management
Bar/Gantt Charts Defined:
Finish to Start (FS) – Activity A must Finish before Activity B may Start.
The lag is usually zero. FS is the most common type.
Activity A Activity B
Start to Finish (SF) – Activity A must start before Activity B may Finish. The
lag is usually greater than either activity duration. SF is the least common type.
Activity A Activity B
Time Management
PDM Logic Relationships
Finish to Finish (FF) – Activity A must Finish before Activity B may Finish or finish together.
The lag value is usually greater than zero. FF is a less common type.
Activity A Activity B
Start to Start (SS) – Activity A must Start before Activity B may Start or start together.
The lag value is usually greater than zero. SS is a less common type.
Activity A Activity B
Time Management
PDM Time Calculations
Once the Network is constructed and duration of each activity
is estimated, we can determined the following four time
values:
– Earliest Start (ES) – The earliest possible time an activity can begin
– Earliest Finish (EF) – The earliest possible time an activity can finish
– Latest Start (LS) – The latest possible time an activity can start
without delaying project completion
– Latest Finish (LF) – The latest possible time an activity can start
without delaying project completion
Time Management
PDM Time Calculations
8 E 9 11 G 18
1 7
14 K 18 18 I 22
20 4 24 24 4 28
18 J 19
Late Finish Calculations
33 1 34
(H to K) 25
(I to K) 24
(J to K) 33
Time Management
Floats and slack
Total Float: The amount of time that an activity may be delayed from its
early start without delaying the project finish date. Float is a mathematical
calculation, and can change as the project progresses and changes are made
to the project plan. Also called slack and path float.
Free Float (FF): The amount of time that an activity can be delayed
without delaying the early start of any immediately following activities.
Start Completion
Project duration = 24 days
FT = 15
21 V 31
FF = 5
36 10 46
FT = 10 FT = 10 FT = 0
FF = 0 FF = 10 FF = 0
29 W 36 36 X 41 51 Z 61
39 7 46 46 5 51 51 10 61
FT = 0
FF = 0
44 Y 51
44 7 51
Time Management
B
A E
A B E
Start Finish
C F Start
D Finish
D F
C
Example
Task/Duration/Predecessor
TASK Duration Predecessor
A 2 ----
ID – Task ID B 2 A
D- Duration
C 1 A
ES – Early Start
D 3 A
EF – Early Finish ES EF
LS – Late Start E 1 C,D
F ID D F 3 B
LF – Late Finish
F - Float/Slack LS LF G 2 E,F
TASK Duration Predecessor
0 0 A 2 ----
2 4 4 7 B 2 A
C 1 A
0 B 2 0 F 3 D 3 A
2 4 4 7 E 1 C,D
F 3 B
2
7 9
0 2 2 3
0 A 2 3 C 1 0 G 2
0 2 5 6 7 9
0 1 FF
ES EF
2 5 5 6
1 D 3 1 E 1 F ID DR
3 6 6 7 LS LF
0/0 3 6 2/0 6 10 10 16 4/4
B E H
3 4 6
3 6 8 12 14 20
1 G 1 01 October 2021 5 H, I
2 H 2 08 October 2021 8 (4+4) J
3 I 3 10 October 2021 15 (4+5+5+1) K
4 J 2 22 October 2021 4 (2+2) K
5 K 2 05 November 2021 3 -
Bar Chart
Week
No Activity Duration People
1 2 3 4 5 6
1/10 8/10 15/1 22/1 29/1 5/11 12/1
0 0 0 1
1 G 1 5 5
2 H 2 8 4 4
3 I 3 15 4 5 5 1
4 J 2 4 2 2
5 K 1 3 3
10
Resources
(People)
0
Duration (week)
Work Breakdown Structure (WBS)
▪ Usually, the project managers use this method for simplifying the
project execution.
▪ Small project activities possibly with very short durations and definable results.
▪ In some complex projects, work packages may be at a lower level, say Level 5
or Level 6.
▪ The smallest level in a project that can be monitored, managed, and controlled
by a project manager effectively.
▪ The time frame for a work package may be 40 hours or 4 weeks depending up
on the size and complexity of the project.
• Mutually-exclusive elements. Work should only appear in one place in the WBS.
▪ The analogy approach: Review WBSs of similar projects and tailor to your
project.
▪ The top-down approach: Start with the largest items of the project and
break them down.
▪ The bottom-up approach: Start with the specific tasks and roll them up.
Work Breakdown Structure (WBS)
WBS Dictionary
▪ A WBS dictionary is a document that describes detailed information
about each WBS item.
▪ Many WBS tasks are vague and must be explained more so people
know what to do and can estimate how long it will take and what it
will cost to do the work.
Work Breakdown Structure (WBS)
Sample WBS – Product Type Project
Work Breakdown Structure (WBS)
Sample WBS
Work Breakdown Structure (WBS)
WBS is the link to project design and the first project planning activity.
Work Breakdown Structure (WBS)
Activity Planning Steps
Activity Planning typically three steps that allow the project schedule to be created.
Work Breakdown Structure (WBS)
Organization Breakdown Structure OBS
BOARD OF DIRECTORS
PRESIDENT
B. Blank
Responsibility Chart Executive
The PM job is to ensure that everyone in the project team has what he
needs to do the job well.
A PM must exercise both leadership and management skills.
Attributes of
Project Manager
7 Essential Characteristics of
Project Managers
Project Managers
Scorecards
7 Essential Scorecards of
Project Managers
Project Managers
Scorecards
7 Essential Scorecards of
Project Managers
Project Managers
Scorecards
7 Essential Scorecards of
Project Managers
Types of Project Organizations (OBS)
There are two fundamentally different ways of organizing
projects within the parent organization
The project as part of the Functional Organization
The project as a free-standing part of the parent organization (pure
project organization)
A third type, called a Matrix Organization is a hybrid of the
two main types
Each has advantages and disadvantages
Types of Project Organizations (OBS)
1-The Project as Part of the Functional Organization
Types of Project Organizations (OBS)
2-Pure Project Organization
Types of Project Organizations (OBS)
1-The Project as Part of the Functional Organization