Real Time Scheduling Algorithms

Rate monotonic scheduling and earliest deadline first are two real-time scheduling algorithms. Rate monotonic scheduling assigns higher priority to processes with shorter periods, while earliest deadline first assigns higher priority to processes with earlier deadlines. Rate monotonic scheduling can fail if a lower priority process does not meet its deadline. Earliest deadline first addresses this issue by changing priorities dynamically based on deadlines.

Uploaded by

Chandra
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
32 views

Real Time Scheduling Algorithms

Rate monotonic scheduling and earliest deadline first are two real-time scheduling algorithms. Rate monotonic scheduling assigns higher priority to processes with shorter periods, while earliest deadline first assigns higher priority to processes with earlier deadlines. Rate monotonic scheduling can fail if a lower priority process does not meet its deadline. Earliest deadline first addresses this issue by changing priorities dynamically based on deadlines.

Uploaded by

Chandra
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 3

Real Time Scheduling Algorithms

Real time scheduling is of two types: Soft Real-Time scheduling which does not


guarantee when when a critical real-time process will be scheduled; Hard Real-Time
scheduling in which the process must be scheduled before the deadline. In this post
we will cover two real time scheduling algorithms: rate monotonic
scheduling and earliest deadline first.

Real Time Scheduling Algorithms

The foremost is that the processes are considered periodic i.e., the process will
repeat itself after a fixed period of time. The period of a process is denoted by p. The
next characteristic is the processing time t i.e., the time for which the process
requires the CPU within each period. In other words processing time refers to the
burst time. The final characteristic is the deadline d, i.e., the time before which the
process must be serviced. In general the relationship between these three
characteristics is

0≤t≤d≤p

Rate Monotonic Scheduling

In rate-monotonic scheduling algorithm a static priority policy with preemption is


used. Whenever a high priority process arrives it will preempt a lower priority
process. Every process gets the priority according to its period. Lower the period
higher is the priority. Also, the processing time remains the same in each period.

Example:

Suppose there are two processes, P1 and P2. The periods for P1 and P2 are 50 and
100. The processing times are t1 = 20 for P1 and t2 = 35 for P2. The deadline for
each process requires that it complete its CPU burst by the start of its next period.

Process Period/Deadline CPU Burst

P1 50 20

P2 100 35
Solution:

Since, it is mentioned that deadline for each process requires that it complete its
CPU burst by the start of its next period, therefore, the deadline is same as the
period of a process.

The priority of P1 is higher than P2 because P1 has smaller value for period.
Therefore, at time 0, P1 will begin its execution. P1 will finish at 20 and then P2 will
begin its execution (Refer Figure 1). At time 50 P1’s second period will start. At the
same time P2 has completed 30 nsec only. But since priority of P1 is higher, so P1
will preempt P2 and runs from 50-70. P2 completes the remaining 5 nsec from 70-75
but still meets its deadline of 100. The system remains idle till 100, when the 3rd
period of P1 and second period of P2 will start and P1 will begin the execution at that
time. The rest of the execution will follow the same execution order as was from 0-
100.

Failure of rate Monotonic Scheduling:

Assume that process P1 has a period of p1 = 50 and a CPU burst of t1 = 25. For P2,
the corresponding values are p2 = 80 and t2 = 35

Process Period CPU Burst

P1 50 25

P2 80 35

In the above example, if we use rate monotonic scheduling, the first process to begin
execution will be P1 (lower time period). P1 will execute till 25nsec and then P2 will
begin execution and run till 50 when P1 will begin its second period. Till time 50 P2
will finish 25nsec and will be left with 10nsec more. Now, the second peiord of P1 will
be between 50 – 75. Now, P2 will requires 10nsec more to finish but only 5nsec are
left for the deadline (which is 80). Hence, P2 is not able to finish its execution within
the deadline. Thus, Rate Monotonic Scheduling can not be used in this particular
scenario.
Earliest Deadline First Scheduling

The second algorithm under real time scheduling is Earliest Deadline First
Scheduling. This algorithm assigns priority to the process based on the deadline.
Earlier the deadline, higher is the priority. Thus, the priorities keep on changing in
this scheduling.

Example:

Assume that process P1 has a period of p1 = 50 and a CPU burst of t1 = 25. For P2,
the corresponding values are p2 = 80 and t2 = 35

Process Period/Deadline CPU Burst

P1 50 25

P2 80 35

Solution:
Since, the deadline for P1 (50) is earlier than P2 (80) hence, the initial priority of P1
is higher than P2. So, P1 executes from 0-25 (Figure 2). Then, P2 starts at 25. At 50
P1 also arrives for second period. At this point the deadline of P2(80) is earlier than
the deadline of P1 (which is 100 for second period), hence, P2 will continue till 60.
P1 starts at 60. P2 arrives for second period at 80. At this point P1 is having higher
priority because deadline for P1 is 100 whereas for P2 it is 160.
So, P1 continues will 85 after which P2 starts. At 100 P2 is preempted because
priority of P1 is higher as the deadline for its third period is 150 (which is earlier than
deadline of P1 which is 160). So P1 runs from 100-125 and then P2 completes its
second period from 125 to 145. The system remains idle till 150 and then P1
resumes its next period.