7000 Apr04
7000 Apr04
SECTION PAGE
7100 TESTING OF MATERIALS AND
WORKMANSHIP 7000-2
7200 QUALITY CONTROL 7000-12
7300 SETTING OUT AND TOLERANCES7000-17
7400 RECTIFICATION OF EARTHWORKS AND
PAVEMENT LAYERS OUTSIDE PERMITTED
GEOMETRIC TOLERANCES 7000-19
THE REPUBLIC OF UGANDA, MINISTRY OF WORKS, HOUSING AND COMMUNICATIONS PAGE 7000 - 1
GENERAL SPECIFICATIONS FOR ROAD AND BRIDGE WORKS SERIES 7000 - TOLERANCES, TESTING AND QUALITY CONTROL
THE REPUBLIC OF UGANDA, MINISTRY OF WORKS, HOUSING AND COMMUNICATIONS PAGE 7000 - 2
GENERAL SPECIFICATIONS FOR ROAD AND BRIDGE WORKS SERIES 7000 - TOLERANCES, TESTING AND QUALITY CONTROL
All materials supplied for use in the Works shall specifications. All costs of providing such certificates
conform within specified tolerances, to the quality of the shall be borne by the Contractor.
approved samples, which will be retained at the
Engineer’s office until the completion of the Contract. (c) Testing materials and products covered by
certificates
Where a material has been specified by a The Engineer shall be entitled to take samples of, and
manufacturer’s trade name, the product of another order tests to be made on, products and materials in
manufacturer will be accepted provided that, in the respect of which certificates of compliance may be
opinion of the Engineer, it is in all respects of an required. The Contractor shall only be paid at the
equivalent or higher quality. appropriate rates if the costs of such tests are itemised
in the Bill of Quantities.
THE REPUBLIC OF UGANDA, MINISTRY OF WORKS, HOUSING AND COMMUNICATIONS PAGE 7000 - 3
GENERAL SPECIFICATIONS FOR ROAD AND BRIDGE WORKS SERIES 7000 - TOLERANCES, TESTING AND QUALITY CONTROL
called for or implied, they shall be carried out according is made to one of the above standards in the
to test methods listed in SECTION 7502 (a), unless the Specification.
test in question is not covered within this Section. When
a particular test is not listed in SECTION 7502 (a), then The Contractor shall have on the Site all the relevant
the method shall be an equivalent standard called for in standards required for the work he is to undertake
the contract documents or as directed by the Engineer. under the Contract. The Engineer shall be provided a
In addition to the above standard methods of testing, copy of such standards.
equivalent standard specifications or test methods of
other bodies may be used in these specifications if
approved by the Engineer.
TABLE 7109/1
SAMPLING FREQUENCIES
Layer and nominal class of material Tests to be carried out Sampling frequency, minimum
1)
Roadbed CBR 1 sample per 10000 m2
MDD, PI, grading 1 sample per 5000 m2
Earthworks fill using soils: (G3) CBR, PI, grading 1 sample per 2000 m3
MDD 1 sample per 1000 m3
Backfill to culverts and structures CBR, PI, grading 1 sample per 500 m3
MDD 1 sample per 200 m3
Improved subgrade (G7, G15) or CBR, PI, grading 1 sample per 10000 m2
Gravel wearing course (GW) MDD 1 sample per 5000 m2
Subbase: (G30, G45) CBR, incl. swell, grading 1 sample per 5000 m2
MDD, PI, LL, LS 1 sample per 5000 m2
Subbase: (CM, C0.7, C1.0) UCS, PI 1 sample per 5000 m2
MDD 1 sample per 5000 m2
Base course: (G60, G80) CBR, PI, grading 1 sample per 5000 m2
MDD 1 sample per 2500 m2
Base course: (C1.0, C1.5) UCS, PI 1 sample per 5000 m2
MDD 1 sample per 2500 m2
Base course using crushed aggregate: (CRS) LS, grading 1 sample per 5000 m2
MDD 1 sample per 2500 m2
Base course using crushed aggregate: (CRR) LL, LS, grading, flakiness 1 sample per 5000 m2
MDD, TFV, CBR 1 sample per 10000 m2
Base course of a bituminous mix or asphalt concrete Extraction, grading 1 sample per 10000 m2
surfacing Marshall test / Gyratory 1 sample per 5000 m2
Compaction Test
Surface treatments TFV 1 sample per 20000 m2
Grading, flakiness 1 sample per 5000 m2
Tray Test 2 1 sampler per 500 m²
The referred tests shall be carried out in accordance with standards test methods indicated in the special specifications or
other standards approved by the Engineer. Tray test shall be performed for both bitumen spraying rate and chipping
spreading rate.
THE REPUBLIC OF UGANDA, MINISTRY OF WORKS, HOUSING AND COMMUNICATIONS PAGE 7000 - 4
GENERAL SPECIFICATIONS FOR ROAD AND BRIDGE WORKS SERIES 7000 - TOLERANCES, TESTING AND QUALITY CONTROL
Accelerated tests shall be carried out to determine the Fill the mould halfway and vibrate it and spade it on
potential alkali reactivity of aggregates where this is all four sides with a suitable trowel to remove air
considered appropriate by the Engineer. bubbles. Stop the vibration as soon as a wet sheen
appears on the surface. Fill the mould and repeat
(b) Test for cementitious- binder content the procedure, but stop when again a wet sheet
The test method used for determining the cementitious appears on the surface.
binder content of soils, gravels or crushed stone mixed (ii) Stiff Concrete
with a chemical stabilising agent shall be determined by The same procedure is followed, except that the
the Engineer and may be any test method currently mould is filled in three to four steps instead of in
recognised by the Engineer as being acceptable. two. The vibration is stopped for each layer when a
wet sheen appears.
Where the cementitious binder content is determined,
due allowance shall be made for the presence in the (g) Consistency
un-stabilised material of naturally occurring MgO or The test method described in shall apply in regard to
CaO which affects the result of such tests. If the the slump test.
standard deviation of the natural CaO plus MgO content
of the untreated material exceeds 0.35% any (h) Air content
determination of the cementitious- binder content shall The air content of the freshly mixed concrete shall be
be ignored. tested by the method given in BS 1881, Part 106 or
equivalent. Air content tests shall be conducted on the
Sample holes shall be randomly (as defined in same samples of concrete from which cubes were
SUBCLAUSES 7203(b) and 7204(b)) spaced transversely made for the 28 – day compressive strength tests.
as well as longitudinally over the area to be tested, or
as directed by the Engineer, and if the material is road (i) Drilling and testing the cores
– mixed, samples shall be taken from the top and Where sections of concrete which have failed to comply
bottom of each hole. The minimum number of samples with the Specifications are required to be further
per test shall be 10. investigated by extracting and testing concrete cores,
100 mm or 150 mm cores shall be drilled and tested.
(c) Canvas patch test for the spreading rate of The sampling and testing procedure to be followed shall
cementitious binder be in accordance with the publication Concrete Core
The following method shall be used for determining the Testing for Strength – Concrete Society Technical
spreading rate of a chemical stabilising agent where Report No.11, published by the Concrete Society of
bulk distributors are used. Great Britain.
At least 10 clean canvas patches, each measuring 1.0 The instructions of this report shall be followed for
m x 1.0 m shall be placed flat on the road in selected determining the “estimated potential strength”, which
positions in relation to the bulk distributor’s track. After shall be compared with the 28 days cube strength
the stabilising agent has been spread by the bulk specified for each type of concrete. Corrections to the
distributor, the canvas patches shall be carefully lifted actual core strength to allow for excess voids, included
and all the material on the patches transferred to a steel and the length :diameter ratio of cores shall be as
container and weighed. The total mass of stabilising stated in this publication, and the correction for curing
agent on each patch is then recorded and the average shall be determined by the Engineer in accordance with
rate of application determined. Instead of canvas this publication and such other information as he may
patches, flat metal trays may be used for collecting the deem to be appropriate.
stabilising agent.
The Engineer’s decision regarding the degree to which
(d) Test for mix uniformity in chemically stabilised the concrete, which is represented by the cores tested
layers as described above, complies with the requirements
Where required by the Engineer, the Contractor shall and also regarding the properties and suitability of the
determine the mix uniformity in chemically stabilised concrete, shall be final and binding.
layers by means of unconfined compressive strength
tests, using an approved method.
7112 TESTING SOILS, GRAVEL AND
The Contractor shall without delay make the necessary
CRUSHED AGGREGATE FOR
arrangements to take samples in accordance with the
requirements in the method used. EARTHWORKS AND PAVEMENT
LAYERS
(e) Test for initial consumption of lime Specimens of soils, gravel and crushed stone materials
The objective of the gravel ICL test is the control of the in earthworks and pavement layers shall be taken in
pH in lime and cement stabilised soil in order to allow accordance with CLAUSE 7104, and subjected to tests
the possible formation of cement minerals, calcium as prescribed for each respective layer in the relevant
silica hydrate in particular, and for proper modification sections of SERIES 3000.
to take place. It is recommended that the stabiliser to
be used during construction (or the nearest equivalent)
should be used to carry out this test. 7113 TESTING BITUMINOUS BINDERS AND
MIXES
(f) Determining the compressive strength
Specimens of soils, gravel and crushed stone materials
The procedure for sampling and manufacturing, storing,
in earthworks and pavement layers shall be taken in
curing and testing test cubes shall be in accordance
accordance with SECTION 7105. And subjected to tests
with appropriate tests in SECTION 7502 (a).
as prescribed for each respective layer in the relevant
sections of SERIES 4000.
Where specified in the Special Specifications, the
compaction of concrete specimens in the moulds by
The Engineer shall be entitled to order the Contractor to
means of a vibrating table shall be obligatory. In such
have material tested by an approved laboratory for
case the method of compaction shall be as follows:
compliance with all of the requirements specified, and
the results of such tests shall be submitted direct to the
(i) Plastic concrete
Engineer by the testing laboratory with copies, if
requested, to the Contractor.
THE REPUBLIC OF UGANDA, MINISTRY OF WORKS, HOUSING AND COMMUNICATIONS PAGE 7000 - 5
GENERAL SPECIFICATIONS FOR ROAD AND BRIDGE WORKS SERIES 7000 - TOLERANCES, TESTING AND QUALITY CONTROL
TABLE 7114/1
TESTING FREQUENCIES FOR FIELD DENSITY TESTING
Earthworks fill using soils: (G3) 1 test per 200 m3 3 per section per layer
tests
Backfill to culverts and structures 2 10 m3 2 per section
per
Fill or improved subgrade layers using dump rock: (DR)
Method specification
Improved subgrade layers using gravel/soils: (G7, G15)
1 test per 1000 m2 4 per section per layer
Gravel wearing course used on gravel roads: (GW)
1 test per 1000 m2 4 per section
Subbase: (G30, G45, CM, C 0.7, C 1.0) 1 test per 750 m2 5 per section
Base course: (G60, G80, CRS, CRR) 1 test per 500 m2 6 per section
Base course of bituminous mix: (BEMIX, FBMIX, DBM40,
DBM30, 37.5, 25.0 Nominal mixes) 1 test per 500 m2 6 per section
Asphalt concrete surfacing
(AC20, AC14, AC10, 19.0, 12.5, 9.5 Nominal mixes) 1 test per 400 m2 6 per section
Initial calibration of the nuclear testing equipment shall (d) Field density requirements
be done by carrying out at least fifty tests in parallel with The required field densities for each material type shall
the sand replacement method for each different be as shown in TABLE 7114/2. The values shown are
material encountered. nominal values, or lower specification limits, to which an
THE REPUBLIC OF UGANDA, MINISTRY OF WORKS, HOUSING AND COMMUNICATIONS PAGE 7000 - 6
GENERAL SPECIFICATIONS FOR ROAD AND BRIDGE WORKS SERIES 7000 - TOLERANCES, TESTING AND QUALITY CONTROL
THE REPUBLIC OF UGANDA, MINISTRY OF WORKS, HOUSING AND COMMUNICATIONS PAGE 7000 - 7
GENERAL SPECIFICATIONS FOR ROAD AND BRIDGE WORKS SERIES 7000 - TOLERANCES, TESTING AND QUALITY CONTROL
.
TABLE 7114/2
MINIMUM FIELD DENSITY, NOMINAL VALUES
Layer and nominal class of material Field density, Lower Specification Limit
Fill or improved subgrade layers using dump rock: (DR) Method specification
Asphalt concrete surfacing: (19.0, 12.5, 9.5 Nominal mixes) > 93.5 % of Max. Theoretical Density G mm
1) Marshall density cannot be used on coarse bituminous material types, i.e. with nominal aggregate size 30 mm or larger.
Whether or not Marshall compaction can be applied for a specific type of cold bituminous mix shall be decided by the
Engineer.
THE REPUBLIC OF UGANDA, MINISTRY OF WORKS, HOUSING AND COMMUNICATIONS PAGE 7000 - 8
GENERAL SPECIFICATIONS FOR ROAD AND BRIDGE WORKS SERIES 7000 - TOLERANCES, TESTING AND QUALITY CONTROL
Subbase 30
TABLE 7115/2
SURFACE LEVELS
H90 value 1) Absolute max Hmax H90 value 1) Absolute max Hmax
value value
Base course, when 10 15 10 15
followed by a seal only
Base course, when NIL NIL 10 20
followed by AC surfacing
Subbase NIL NIL 25 35
1) H90 is the limit within which 90% of the measurements shall fall when assessing 50 or more measurements against the
specified level at the respective locations the measurements were taken.
THE REPUBLIC OF UGANDA, MINISTRY OF WORKS, HOUSING AND COMMUNICATIONS PAGE 7000 - 9
GENERAL SPECIFICATIONS FOR ROAD AND BRIDGE WORKS SERIES 7000 - TOLERANCES, TESTING AND QUALITY CONTROL
THE REPUBLIC OF UGANDA, MINISTRY OF WORKS, HOUSING AND COMMUNICATIONS PAGE 7000 - 10
GENERAL SPECIFICATIONS FOR ROAD AND BRIDGE WORKS SERIES 7000 - TOLERANCES, TESTING AND QUALITY CONTROL
Base course, 10 20
aggregate or natural
gravel
Subbase 15 25
Improved subgrade 20 35
layers
Gravel wearing 15 25
course
1) T90 is the value with which 90% of the
measurements shall comply when assessing 20 or
more measurements against the specified layer
thickness.
THE REPUBLIC OF UGANDA, MINISTRY OF WORKS, HOUSING AND COMMUNICATIONS PAGE 7000 - 11
GENERAL SPECIFICATIONS FOR ROAD AND BRIDGE WORKS SERIES 7000 - TOLERANCES, TESTING AND QUALITY CONTROL
The Contractor shall not proceed with the placing of the The bleeding of grout shall be measured in a metal or
layer tried in the trial section until the methods, glass container with an internal diameter of
materials and procedures established in the trials have approximately 100 mm and a height of approximately
been approved. Such approval shall be based on a 120 mm. The grout and water levels in the container
detailed trial section report prepared by the Contractor shall be controlled with a metal bridge into which two
including all observations and test results. Should the adjustable studs A and B are secured.
trial fail, the Contractor shall perform additional trials at
his own cost until a trial and the trial section report has The procedure for determining the bleeding of grout
been approved by the Engineer. shall be as follows:
If during the execution of the works, the construction Studs A and B in the metal bridge shall be adjusted and
control tests indicate that the requirements for a locked so that the distance from the lower tips of studs
material are not being consistently achieved, then work to the bottom of the container will be approximately 100
on that layer shall stop until the cause is investigated by mm and 107 mm respectively. The volume V a and Vb for
the Contractor. Such investigation may include, effect of the container at the respective levels of the stud
using other compaction methods, further laboratory and settings shall then be determined to the nearest
site trials on the material to determine a revised set of millilitre.
data as above which, when agreed, shall be the basis
on which all subsequent material will be provided and The container shall be filled with freshly mixed grout to
processed to achieve the specified requirements. a level where the grout will just touch the tip of stud A
which points downwards. The bridge shall then be
Agreement by the Engineer to a set of data recorded in removed and the container tightly sealed to prevent
a site trial shall not relieve the Contractor of any evaporation. The container shall then be stored at 20°C
responsibility to comply with the requirements of this and kept free from vibrations for the entire duration of
Specification and the Special Specification. the test.
Material represented by samples which do not The test load shall be applied to the top of the pile with
comply with the specified requirements shall be a hydraulic jack. Where more than one jack is used for
removed and replaced with suitable material. applying the load, all the jacks in the circuit shall be
THE REPUBLIC OF UGANDA, MINISTRY OF WORKS, HOUSING AND COMMUNICATIONS PAGE 7000 - 12
GENERAL SPECIFICATIONS FOR ROAD AND BRIDGE WORKS SERIES 7000 - TOLERANCES, TESTING AND QUALITY CONTROL
THE REPUBLIC OF UGANDA, MINISTRY OF WORKS, HOUSING AND COMMUNICATIONS PAGE 7000 - 13
GENERAL SPECIFICATIONS FOR ROAD AND BRIDGE WORKS SERIES 7000 - TOLERANCES, TESTING AND QUALITY CONTROL
SERIES 7000: TOLERANCES, TESTING AND For the purposes of this SECTION the following words
and symbols shall have the following meanings:
QUALITY CONTROL
(a) Lot
SECTION 7200: QUALITY A lot is a sizeable portion of work or quantity of material
which is assessed as a unit for the purpose of quality
CONTROL control, and selected to represent material or work
produced by essentially the same process and from
essentially the same materials.
CONTENTS:
CLAUSE PAGE (b) Random Sample
Random samples are test measurements at separate
7201 SCOPE 7000-12 test positions or on separate sample portions obtained
7202 JUDGEMENT PLANS: GENERAL 7000-12 from the lot in an unbiased manner.
7203 DEFINITIONS 7000-12
7204 GENERAL REQUIREMENTS 7000-12 (c) Nominal value or specification limit
7205 PROCEDURES AND ACCEPTANCE LIMITS7000-13 This is the limit value of the property of any material
7206 CONDITIONAL ACCEPTANCE 7000-14 outside which not more than a specified percentage of
7207 ROUTINE TESTS AND INSPECTION BY the population of values representing an acceptable
THE ENGINEER. 7000-15 material is allowed to lie. The nominal value may be a
7208 PROCESS CONTROL BY THE single lower limit or a single upper limit or a double limit
CONTRACTOR 7000-15 consisting of a lower limit and an upper limit.
7209 MEASUREMENT AND PAYMENT 7000-15
(d) Acceptance limit for sample mean
This is the limit value of a product property within which
the sample mean shall lie for a product to be
7201 SCOPE acceptable.
This Section describes the scheme used for
determining, by means of tests and measurements and (e) Acceptance limits for individual test values
by applying statistical judgement plans, whether certain These are the limit values of a product property within
specified requirements in regard to the properties of which the sample values representing a product shall lie
materials and workmanship are being complied with. for the product to be acceptable.
It also covers the requirements in regard to the control (f) Conditional acceptance
to be exercised by the Contractor for monitoring the This is the acceptance of a lot at conditions that specific
quality of his work and materials and the routine tests rectification measures are taken and carried through to
and inspections to be carried out by the Engineer. completion to the satisfaction of the Engineer before the
lot can be approved in the permanent Works and
certified for payment. Conditional acceptance shall be
7202 JUDGEMENT PLANS: GENERAL subject to the provisions of CLAUSE 7202.
Certain requirements and nominal limit values are laid
down in the Specifications in regard to the properties of (g) Outliers
materials and workmanship to be supplied. Tests shall Where, in a sample, one or more test results differ
be conducted and measurements taken for controlling significantly from the other values obtained, this
the relevant properties of the workmanship and difference could be ascribed to an assignable cause if
materials supplied, and the results of such tests and so deemed by the Engineer, in which case such test
measurements shall be assessed on the basis of the result shall be regarded as an outlier and disregarded
prescribed criteria for compliance with the specified when assessing the lot.
requirements.
THE REPUBLIC OF UGANDA, MINISTRY OF WORKS, HOUSING AND COMMUNICATIONS PAGE 7000 - 14
GENERAL SPECIFICATIONS FOR ROAD AND BRIDGE WORKS SERIES 7000 - TOLERANCES, TESTING AND QUALITY CONTROL
concrete structures could therefore vary The first and second sets of test values shall then be
considerably, and, particularly in the case of small compared with each other to determine whether their
structures, it could be necessary to combine properties differ significantly.
samples of the same grade of concrete from
different structures at the discretion of the Engineer, Where in the opinion of the Engineer a significant
provided that the concrete has been obtained from difference does occur, the submission of the lot shall be
the same concrete plant and has been cast in the regarded as a first submission and assessed as such,
same period. and only the second set of test values shall then be
used for this purpose.
(iii) Other
In certain cases, as for example in material
stockpiles, others where the definition of a lot in TABLE 7204/1
accordance with this Section does not apply directly VALUES OF T FOR DIFFERENT SAMPLE SIZES
in the opinion of the Engineer, the Engineer will
determine lot sizes in accordance with Number of observations n Critical value T
circumstances pertaining to each case.
1
(b) Random sampling 2
When any lot is tested, whether a normally sized lot or 3
an isolated section that clearly exhibits an abnormal
4 1.46
variation of the properties under consideration, all
samples shall be taken in a random pattern. 5 1.67
6 1.82
For this purpose use shall be made of tables of random
numbers according to standard instructions approved 7 1.94
by the Engineer. 8 2.03
9 2.11
(c) Sample Sizes
For purposes of acceptance control, the Engineer will 10 2.18
determine sample size, i.e. the number of values to be 11 2.23
assessed in a lot.
12 2.29
(d) Outliers 13 2.33
Test results shall be scanned for possible outliers. 14 2.37
Where there is reason to believe that a test result may
be erroneous, it shall, if possible, be re-examined by 15 2.41
further testing, and, if there is reasonable evidence to 16 2.44
suggest that the test result is erroneous, it shall be
17 2.47
regarded as an outlier, rejected and replaced with a
fresh result. 18 2.5
19 2.53
Where reinvestigation of a test result is not possible, the
procedure described below shall be used for identifying 20 2.56
outliers:
(a) General
The statistical judgement procedures described below
shall apply to the corresponding product properties for
Where Xn and Sn are the arithmetic mean and the the purpose of acceptance control. Outliers shall be
sample standard deviation respectively, and Xo is the identified, disregarded, and, if possible, replaced at the
value of the test differing most from the mean. discretion of the Engineer.
Compare the value of To with the value of T for the (b) Straight edge measurements
applicable value of n from TABLE 7204/1. Six straightedge measurements shall be taken in the
longitudinal direction and six measurements shall be
If To is greater than T, then Xo is an outlier. taken in the transversal direction every 25 m along the
road or as otherwise directed by the Engineer. The
Every outlier shall be disregarded and replaced by measurements shall be taken at offsets as agreed with
another random test value. The sample mean and the the Engineer. All measurements taken shall fall within
sample standard deviation shall then be recalculated. If the limits given in TABLE 7115/1 including the
an outlier cannot be replaced, the sample mean and the requirement for surface dressing.
standard deviation shall be calculated using the
remaining test results. The final number of test results (c) Surface levels
used in the assessment, after the elimination of outliers, At least 5 points across road shall be taken every 25 m.
shall never be less than three. The levels shall be taken at the centreline, at the edge
of the carriageway and at the edge of the shoulders or
(e) Resubmission as directed by the Engineer. The levels may be taken at
Where a lot has been accepted conditionally, or has shorter intervals than 25 m, see CLAUSE 7303.
been rejected, the Engineer may agree to its
resubmission for approval if it has been rectified to the At least 50, but preferably more, levels shall be
satisfaction of the Engineer. In such case a fresh determined for each lot of completed work The lot will
sample shall be taken, and a fresh (second) set of test be considered to comply with the requirements in
values determined. respect of surface levels if, before any repair work is
undertaken, at least 90% of the level measurements
show a deviation from the specified levels which is
THE REPUBLIC OF UGANDA, MINISTRY OF WORKS, HOUSING AND COMMUNICATIONS PAGE 7000 - 15
GENERAL SPECIFICATIONS FOR ROAD AND BRIDGE WORKS SERIES 7000 - TOLERANCES, TESTING AND QUALITY CONTROL
After outliers have been examined and replaced as (1) Take 50 samples according to a random pattern
directed by the Engineer, compliance with the specified (as defined in SUBCLAUSES 7203(b) and
density requirements shall be determined by the 7204(b)) and determine their cementitious
statistical method specified below unless a fixed binder content.
minimum average value and/or absolute minimum value (2) Examine the results for outliers and replace
has been specified for the compaction elsewhere in them if any in the opinion of the Engineer.
these Specifications.
(ii) Analysis
The lot will be considered to comply with the The lot will be considered to comply with the
requirements for field density if the following conditions requirements for cementitious binder content if the
are fulfilled: following conditions are both fulfilled:
(1) For a lower limit specification, LLs (1) The mean cementitious-binder content shall be
not less than 91% of the specified binder
Xn > LLs + Sn*K content.
(2) The cementitious binder content in not more
Accept the lot if the sample mean satisfies the than 12 of the 50 samples may be lower than
expression, otherwise reject the lot. 70% of the specified binder content.
THE REPUBLIC OF UGANDA, MINISTRY OF WORKS, HOUSING AND COMMUNICATIONS PAGE 7000 - 16
GENERAL SPECIFICATIONS FOR ROAD AND BRIDGE WORKS SERIES 7000 - TOLERANCES, TESTING AND QUALITY CONTROL
TABLE 7205/1:
VALUES OF STUDENT’S-T AND K FOR DIFFERENT SAMPLE (i) Method
SIZES Take at least the minimum number of samples as
given in Table 7205/3 according to a random
pattern (as defined in SUBCLAUSES 7203(b) and
n Student's-t 7204(b)) and make test cubes. Test them for cube
compressive strength after 28 days.
3 1.89 1.09
4 1.64 0.82 TABLE 7205/3
5 1.53 0.68 MINIMUM NUMBER OF TESTS OF STRUCTURAL CONCRETE
FOR COMPRESSION STRENGTH
6 1.48 0.60
7 1.44 0.54 Volume of lot (m3) Minimum number of
8 1.42 0.50 tests in lot 1)
9 1.40 0.47 0 – 20 4
21 – 40 6
10 1.38 0.44
41 – 70 9
11 1.37 0.41
71 – 100 12
12 1.36 0.39
101 – 150 14
13 1.36 0.38
> 150 16
14 1.35 0.36
1) Each test consists of the average value of a set of
15 1.34 0.35
three cubes.
16 1.34 0.34
17 1.34 0.32 (ii) Analysis
Examine the results for outliers and disregard as
18 1.33 0.31
required in the opinion of the Engineer. The results
19 1.33 0.31 are then assessed according to the criteria set out
below. A lot will comply with the requirements for
the characteristic strength denoted X, if it meets the
(h) Binder content of bituminous mixes following requirements by using the acceptance
factors A and B given in TABLE 7205/4:
(i) Method
(1) Take at least four specimens of bituminous mix Mean value: minimum ( X + A )
in a random pattern (as defined in SUBCLAUSES Single test value: minimum ( X - B )
7203(b) and 7204(b)) and determine the binder
content.
(2) Examine the results and replace any outliers as TABLE 7205/4
directed by the Engineer. Determine the sample ACCEPTANCE FACTORS FOR STRENGTH OF STRUCTURAL
mean and assess the lot by using the following CONCRETE
criteria.
Number of Acceptance factors for strength of
(ii) Analysis tests in lot structural concrete
The binder content of bituminous mixes shall A B
not deviate from the specified binder content by (MPa) (MPa)
more than the values given in Table 7205/2 or 3 2.7 3.9
according to the Special Specifications. 4 2.7 4.2
5 2.6 4.5
TABLE 7205/2 6 2.5 4.7
ACCEPTANCE LIMITS FOR BITUMINOUS BINDER CONTENT 7 2.4 4.9
IN MIXES
8 2.3 5.0
Number of Maximum deviation from the 9 2.2 5.2
tests in lot specified binder content 10 2.1 5.3
(% of binder)
11 1.9 5.4
Sample mean Single values
12 1.7 5.5
2 0.37 0.54
13 1.4 5.6
3 0.33 0.58
14 1.1 5.7
4 0.30 0.60
15 0.5 5.8
5 0.28 0.62
6 0.27 0.64
7 0.26 0.65
8 or more 0.25 0.66
THE REPUBLIC OF UGANDA, MINISTRY OF WORKS, HOUSING AND COMMUNICATIONS PAGE 7000 - 17
GENERAL SPECIFICATIONS FOR ROAD AND BRIDGE WORKS SERIES 7000 - TOLERANCES, TESTING AND QUALITY CONTROL
THE REPUBLIC OF UGANDA, MINISTRY OF WORKS, HOUSING AND COMMUNICATIONS PAGE 7000 - 18
GENERAL SPECIFICATIONS FOR ROAD AND BRIDGE WORKS SERIES 7000 - TOLERANCES, TESTING AND QUALITY CONTROL
SERIES 7000: TOLERANCES, TESTING AND After completion of the setting out and site clearance
the Contractor shall take ground cross sections at
QUALITY CONTROL intervals of 25 m along the road centreline and along
the centreline of all culverts and structures. These shall
SECTION 7300: SETTING OUT be plotted to a natural scale of 1:100 on a stable
transparent material or other approved material and a
AND TOLERANCES copy of the plot submitted to the Engineer for
agreement. If the Contractor fails to take requisite
levels, levels determined by the Engineer shall be taken
CONTENTS: as correct.
CLAUSE PAGE The Contractor shall programme for a period of 30 days
7301 SCOPE 7000-17 between submitting the ground cross sections and
7302 GENERAL 7000-17 being issued with final road, culvert and structure levels.
7303 DETAILED SETTING OUT 7000-17 A minimum 5 km section of road shall be submitted, but
7304 TOLERANCES 7000-17 where the Contractor submits cross sections for more
7305 MEASUREMENT AND PAYMENT 7000-18 than 10 km of road within the same 30 day period the
initial 30 days shall be extended by 30 days for each
additional 10 km or part thereof. Final road, culvert or
structure levels will be determined by the Engineer and
7301 SCOPE may be different from the levels shown on the
This Section covers the procedures for setting out and Drawings.
gives the limits for geometric tolerances for earthworks
and layer work. On receipt of the final road levels the Contractor shall
mark up the details on the transparencies and the
original and one print of the cross-sections shall be
provided free of charge by the Contractor for the
7302 GENERAL Engineer.
The Engineer will provide sufficient basic survey
information to enable the contractor to set out the works On completion of the earthworks but before starting
and the Contractor shall be responsible for setting out formation or pavement layers the Contractor shall
all necessary reference points and for the maintenance establish steel pins at a constant offset to the edges of
thereof. the carriageway shoulders. The offset may however
vary between sections in cut and those in fill. The steel
The Contractor shall satisfy himself as to the accuracy pins will be clearly and indelibly marked with all the
in line, level and dimension of the basic survey and relevant information necessary to directly establish the
setting out details provided and should the Contractor centreline and level at any point across the carriageway
discover any error in the information provided by the by using either boning rods or a string line.
Engineer, he should at once notify the Engineer. If the
information is confirmed to be in error the Engineer will The interval between pins shall not be more that 12.5 m
issue amended drawings or instructions regarding the and the pins shall be maintained by the Contractor for
correction of the error. as long as they are needed by the Engineer to check
the work.
Prior to commencing construction, the Contractor shall
establish the road reserve boundary posts, or if no
boundary posts are instructed, then the Contractor shall
establish reference points to define the road reserve at 7304 TOLERANCES
100 m intervals on both sides.
(a) General
The Contractor shall establish temporary benchmarks In addition to the requirements set out in this Clause
along the road at intervals not exceeding 200 m and attention is drawn to the requirements of CLAUSE 7115
shall provide the Engineer with a schedule of their which shall all be fulfilled.
levels and locations.
(b) Horizontal alignments
The Contractor shall not remove, damage, alter or Horizontal alignments shall be determined from the
destroy in any way plot beacons or survey beacons. centreline of the pavement surface as constructed, and
Should the Contractor consider that any beacon will be all other parallel alignments shall be corrected within a
interfered with by the works he shall notify the Engineer tolerance of ±13 mm therefrom.
who, if he considers necessary, will make arrangements
for the removal and replacement of the beacon. (c) Thickness of pavement layers
The thickness of any pavement layer as specified or
If the Contractor removes or disturbs a beacon without ordered by the Engineer, measured at five points in any
permission of the Engineer, he shall be liable for the full length of 100 m, shall meet the requirements given in
cost of its replacement and any legal consequences TABLE 7115/4.
thereof.
(d) Surface levels of payment layers and formation
The level measured at any point on the surface of a
pavement layer or the formation level shall not deviate
7303 DETAILED SETTING OUT from the corresponding level calculated from the
The Contractor shall set out the line and level of the Drawings by more than the tolerances shown in TABLE
works at intervals of not more than 25 m or such lesser 7115/2.
intervals as are required to construct the Works to the
tolerances specified in this Specification. Reference For checking compliance with TABLE 7115/2
pegs and batter rails clearly and indelibly marked with measurements of surface levels will be taken at points
all the relevant information shall be provided clear of the to be selected by the Engineer at 12.5 m centres
road and at right angles to it from which the centreline, longitudinally and at 2 m centres transversely. At
level and batter slope can be directly established at any junctions, the grid point spacing shall be determined by
time. These shall be maintained by the Contractor for the Engineer.
as long as they are needed to check the work.
THE REPUBLIC OF UGANDA, MINISTRY OF WORKS, HOUSING AND COMMUNICATIONS PAGE 7000 - 19
GENERAL SPECIFICATIONS FOR ROAD AND BRIDGE WORKS SERIES 7000 - TOLERANCES, TESTING AND QUALITY CONTROL
(e) Surface regularity The tolerance permitted in the width of the bottom of
The surface regularity of pavement layers and the cuttings shall be 200 mm between the centreline of the
formation shall be tested at points decided by the road and the toe of the cutting slope.
Engineer with a rigid, steel straightedge 3 m long
placed at any angle to the centreline of the road. The The width of embankments measured as the horizontal
maximum allowable deviation of the surface below the distance from the centreline of the road to the top of the
straightedge shall be as given in TABLE 7115/1. embankment shall not be less than that shown on the
Drawing or more than that shown on the Drawings plus
In addition the longitudinal slope or transverse crossfall 0.25 m.
shall not deviate from that shown on the Drawings by
more than the tolerances given in TABLE 7115/3. (i) Depth of side drains
The depth of side drains measured as the vertical
(f) Shoulders height difference from the centreline of the finished
Shoulders shall be constructed to the same thickness, pavement and the invert of the side drain shall not be
level and surface regularity requirements as for the less than that shown on the Drawings nor more than
adjacent pavement layers. that shown on the Drawings plus 0.15 m.
THE REPUBLIC OF UGANDA, MINISTRY OF WORKS, HOUSING AND COMMUNICATIONS PAGE 7000 - 20
GENERAL SPECIFICATIONS FOR ROAD AND BRIDGE WORKS SERIES 7000 - TOLERANCES, TESTING AND QUALITY CONTROL
THE REPUBLIC OF UGANDA, MINISTRY OF WORKS, HOUSING AND COMMUNICATIONS PAGE 7000 - 21
GENERAL SPECIFICATIONS FOR ROAD AND BRIDGE WORKS SERIES 7000 - TOLERANCES, TESTING AND QUALITY CONTROL
Guide to sampling and testing aggregates BS 812: Part 101 and BS 5835
Methods of sampling US 145:2000 or BS 812: Part 102
Determination of physical properties US 146:2000
Moisture content of aggregates BS 812: Part 109:1990 and BS 5835
Relative density BS EN 1097-3: Part 3: 1998
Determination of loose bulk density and air voids BS EN 1097-3: Part 3: 1998
THE REPUBLIC OF UGANDA, MINISTRY OF WORKS, HOUSING AND COMMUNICATIONS PAGE 7000 - 22
GENERAL SPECIFICATIONS FOR ROAD AND BRIDGE WORKS SERIES 7000 - TOLERANCES, TESTING AND QUALITY CONTROL
TESTING CEMENT
Determination of strength US 100-1/ EAS 148-1: Part 1
Chemical analysis of cement US 100-2 / EAS 148-2: Part 2
Determination of standard consistency, setting time and soundness US 100-3 / EAS 148-3: Part 3
Determination of chloride, carbon dioxide and alkali content US 100-4 / EAS 148-8: Part 4
Pozzolanicity test for pozzolanic cements soundness US 100-5:2001 / EAS 148-5: Part 5
Determination of fineness US 100-6:2001 / EAS 148-6: Part 6
Methods of taking and preparing samples of cement US 100-7:2001 / EAS 148-7
THE REPUBLIC OF UGANDA, MINISTRY OF WORKS, HOUSING AND COMMUNICATIONS PAGE 7000 - 23
GENERAL SPECIFICATIONS FOR ROAD AND BRIDGE WORKS SERIES 7000 - TOLERANCES, TESTING AND QUALITY CONTROL
(b) Uganda National Bureau of Standards (UNBS) (c) American Association of State Highway and
US 100 Cement - methods of testing Transport Officials (AASHTO)
US 101: 2000 Aggregates from natural sources M – 85 Ordinary Portland cement
for concrete M – 140 Bituminous prime coat
US 104: 1993 Pozzolanas for use with lime M – 153 Joint filler
US 144: 2000 Aggregates-particle size and M – 154 Air entraining agents.
particle shape determination M – 173 Thermoplastic hot poured sealant
US 145: 2000 Aggregates-methods of sampling M – 194 Concrete Admixtures
US 146: 2000 Aggregates-determination of M – 213 Joint filler
physical properties M – 216 Road lime
US 288: 2001 Lime for soil stabilisation M – 240 Portland blast furnace cement
US 290: 2001 Glossary terms used in lime T – 87 Atterberg limits test method
products T – 89 Atterberg limits test method
US 310: 2001 Compositions, specifications, T – 90 Atterberg limits test method
conformity criteria and evaluation T – 132 Sealant tests
for common cements T – 180 Maximum dry density test method
US 320: 2001 Cement-Definition of terminologies
US 401: 1993 Reflective sheeting materials for (d) American Society for Testing and Materials
traffic control signs (ASTM)
A – 252-68 Pile castings
C – 156 Curing agents
THE REPUBLIC OF UGANDA, MINISTRY OF WORKS, HOUSING AND COMMUNICATIONS PAGE 7000 - 24
GENERAL SPECIFICATIONS FOR ROAD AND BRIDGE WORKS SERIES 7000 - TOLERANCES, TESTING AND QUALITY CONTROL
C – 260 Air entraining agents BS – 6677 Clay and calcium silicate paver for
C – 309 Curing agents flexible pavements
C – 494 Concrete admixtures BS – 6699 Ground granulated blast-furnace slag
C – 719 Sealant tests for use with Portland cement
C – 920 Thermosetting chemically cured sealant BS – 6717 Precast concrete paving blocks
C – 227-90 Test method for alkali reactivity of BS – 7263 Precast concrete kerbs, edgings,
aggregates channels and quadrants
D – 36 Bitumen tests (Softening point) Bs – 7373 Preparation of specifications
D – 244 Bitumen tests (binder content test) BS – 7533 Pavement design-clay or concrete
D – 1557 Maximum dry density tests pavers
D – 4402 Bitumen tests (dynamic viscosity) BS – 7583 Portland and Limestone cement
BS – 7755 Soil quality
(e) British Standards Institute (BS) BS – 7850 Total Quality Management
BS – 4 Structural steel hot rolled sections BS – 7903 Selection and use of gully trops and
BS – 63 Road aggregates manholes
BS – 76 Tars BS – 8000 Code of practice for concrete work
BS – 162 Working under power lines BS – 8004 Code of practice for foundations
BS – 146 Portland blast furnace cement with BS – 8006 Strengthened / reinforced soils and
strength properties outside the scope of other fills
BS EN 197 BS – 8110 Structural use of concrete
BS – 410 Test sieves for particle analysis
Bs – 434 Bitumen road emulsions (f) Standard Coordination Specification (CKS)
BS – 594 Hot rolled asphalt CKS – 82 Steel sections
BS – 470 Aluminium plate CKS – 176 Corrugated metal culverts
BS – 709 Welding CKS – 191 Retro-reflective materials
BS – 812 Fillers for asphalt CKS – 192 Retro-reflective road marking paint
BS – 873 Traffic signs, road studs and bollards CKS – 388 Natural rubber water stops
BS – 881 VEBE test BS - 915 High alumina CKS – 389 PVC rubber water stops
cement CKS – 437 Corrugated metal culverts
BS – 970 Stainless steel CKS – 564 Bonding liquid for concrete surfaces
BS – 1134 Stainless steel plate CKS – 592 Barbed tape concertina wire
BS – 1154 Natural rubber
BS – 1474 Aluminium sections (g) Deutshe Ingineur Norme (DIN)
BS – 1707 Hot binder distributors for road surface DIN – 52013 Bitumen tests (ductility and elastic
dressing recovery)
BS – 1721 Fire extinguishers
BS – 1780 Pressure gauges (h) South African Bureau of Standards (SABS)
BS – 2499 Hot applied joint sealants SABS – 044 Welding procedures
BS – 2752 Synthetic rubber SABS – 064 Abrasive blasting
BS – 2994 Cold rolled steel sections SABS – 094 Holes for friction grip fasteners
BS – 3262 Hot applied thermoplastic road marking SABS – 0100 Concrete cores
materials SABS – 0142 Electrical installations
BS – 3662 Plastic road marking paint SABS – 0162 Design of work/codes of practice
BS – 3690 Specification of bitumens for road SABS – 05 Timber treatment
purposes SABS – 82 Steel reinforcing bars
BS – 3837 Joint filler (rigid foams) SABS – 92 Roofing felt (bridge bearings)
BS – 3892 Pulverised fuel ash SABS – 113 pH test (Water)
BS – 3921 Clay bricks SABS – 134 Paint
BS – 4246 Low heat Portland blast-furnace cement SABS – 135 Bolts and nuts
BS – 4254 Joint sealant SABS – 136 Bolts and nuts
BS – 4360 Structural steel SABS – 141 Paint thickness test
BS – 4447 Anchorages and couplers SABS – 202 Chloride content (Water)
BS – 4486 High tensile alloy steel bars SABS – 212 Sulphate content (Water)
BS – 4840 Joint filler (rigid foams) SABS – 213 Total dissolved solids (Water)
BS – 4987 Coated macadams for roads and other SABS – 227 Bricks
paved areas SABS – 307 Penetration grade bitumen
BS – 5047 Polymised types of butadiene rubber SABS – 308 Prime
(BR) SABS – 309 Bitumen emulsion
BS – 5075 Concrete admixtures SABS – 435 Rivets
BS – 5268 Timber SABS – 455 Welding electrodes
BS – 5135 Welding SABS – 457 Timber Posts
BS – 5212 Cold applied joint sealants SABS – 471 Ordinary Portland Cement
BS – 5328 Specifying concrete SABS – 533 Pipes
Bs – 5273 Dense tar surfacing SABS – 538 Timber treatment
BS – 5400 Bridge bearings SABS – 539 Timber treatment
BS – 5750 Quality systems SABS – 548 Bitumen emulsion
BS – 5896 Steel wire SABS – 558 Manhole covers
BS – 5911 Precast concrete pipes SABS – 626 Portland blast-furnace cement
BS – 5930 Site investigation SABS – 630 Finishing coats (paint)
BS – 6031 Earthworks SABS – 634 Finishing coats (paint)
BS – 6044 Rubber lattices SABS – 657 Steel tubes
BS – 6088 Glass beads SABS – 673 Timber treatment
BS – 6089 Concrete strength in existing structures SABS – 675 Wire
BS – 6543 Recycling SABS – 677 Pipes
BS – 6572 Specification for High Density SABS – 679 Primer (paint)
Polyethylene (HDPE) pipes SABS – 681 Undercoat (paint)
BS – 6588 Portland pulverised fuel ash cements SABS – 684 Finishing coats (paint)
BS – 6610 Pozzolanic pulverised fuel ash cement SABS – 723 Primer (paint)
SABS – 731 Road marking paint
THE REPUBLIC OF UGANDA, MINISTRY OF WORKS, HOUSING AND COMMUNICATIONS PAGE 7000 - 25
GENERAL SPECIFICATIONS FOR ROAD AND BRIDGE WORKS SERIES 7000 - TOLERANCES, TESTING AND QUALITY CONTROL
SABS – 741 Sulphate content (cementitious binders) BS EN 125 Gully and manhole tops-loading,
SABS – 748 Prime design and dimensions
SABS – 1519 Paint BS EN 197 Cement-Composition,
SABS – 1555 Delineation signs specifications, conformity criteria
SABS – 1580 Wire mesh and conformity evaluation
SABS – 749 Prime BS EN 206 Concrete-guidance to
SABS – 754 Timber posts specifier/specification for the
SABS – 763 Galvanishing constituent materials and concrete
SABS – 772 Abrasive blasting BS EN 410-2 Test sieves
SABS – 783 Finishing coats (paint) BS EN 512 Fibre-cement products, pressure
SABS – 791 Pipes pipes and joints
SABS – 801 Epoxy tar paint BS EN 1423 Road marking materials-glass
SABS – 802 Finishing coats (paint) beads, antiskid aggregates and
SABS – 821 Road Lime mixtures of the two
SABS – 831 Rapid hardening cement (OPC15) BS EN 1424 Road marking performance for
SABS – 836 Aggregate test road users and premix glass beads
SABS – 837 Sugar Content (Water) BS EN 1456-1 UPVC pipes
SABS – 838 Sand equivalent test BS EN 1463 Road marking materials - Retro
SABS – 841 Alkali carbonates and bicarbonates reflective road studs
(water) BS EN 1824 Road trials
SABS – 844 Relative density tests BS EN 1871 Physical properties for paint,
SABS – 845 Compacted bulk density thermoplastic and cold plastic
SABS – 848 Polished stone value tests EN – 10113 Structural steel
SABS – 850 Sulphate content (aggregates) EN – 10155 Structural steel
SABS – 855 Free water content (aggregates) BS EN 1916 Precast concrete pipes
SABS – 856 Bulking of fine aggregates BS EN 12271 Surface dressing
SABS – 862 Slump (concrete) BS EN 12591 Specification for pavement grade
SABS – 864 Flexure strength test (concrete) bitumens
SABS – 865 Compression strength (Concrete cores) BS EN 12597 Bitumen and bituminous binders-
SABS – 878 Ready mix concrete terminology
SABS – 912 Primer (paint) BS EN 12889 Trench less construction and
SABS – 920 Steel reinforcing bars testing of drains and sewers
SABS – 921 Pipes BS EN 13055-1 Lightweight aggregates for
SABS – 926 Zinc rich epoxy concrete
SABS – 927 Kerbing BS EN 13249 Geotextiles-characteristics required
SABS – 934 Galvanising fro use in construction of roads and
SABS – 967 Rubber joints for pipes other trafficked areas
SABS – 986 Culverts BS EN 13251 Geotextiles-characteristics required
SABS – 1024 Welded steel fabric for use in earthworks, foundations
SABS – 1058 Paving blocks and retaining structures
SABS – 1077 Joint sealant BS EN 13252 Geotextiles-characteristics required
SABS – 1083 Aggregate for use in drainage systems
SABS – 1085 Sand BS EN ISO 10320 Geotextiles-Identification on site
SABS – 1091 Paint
SABS – 1143 Steel bolts and nuts
SABS – 1149 Washers 7503 ADDRESSES
SABS – 1223 Pipes The Ugandan, AASHTO, ASTM, BS, BS EN, ISO, CKS,
SABS – 1260 Prime DIN, SABS, SIS and US Federal specification and test
SABS – 1282 Friction grip nuts and bolts method documents referred to in this document can be
SABS – 1350 Guardrails obtained from the following sources:
SABS – 1373 Diamond mesh
SABS – 1391 Galvanising Central Materials Laboratory, Ministry of Works,
SABS – 1413 Finishing coats (paint) Housing and Communications
SABS – 1431 Structure steel P.O.Box 7188
SABS – 1442 Road Studs Kampala
SABS – 1500 Electrical installations Uganda
Phone: +256 41 28 57 12
(i) Technical Methods for Highways (TMH), South Fax: +256 41 28 60 56
Africa
TMH – 1 Standard methods of testing road Uganda National Bureau of Standards
construction material P. O. Box 6329
TMH – 5 Sampling methods for road construction Kampala
materials Uganda
TMH – 6 Special methods for testing roads Tel +256 41 22 23 67/50 59 95
Fax +256 41 28 61 23
(j) International Standards Organisation
ISO / R – 161 Specification for High Density South African Bureau of Standards
Polyethylene (HDPE) pipes Private Bag x 191
BS ISO 8349 Road vehicles-measurement of Pretoria
road friction by direct liquid 0001
injection method Tel +27 12 428 6925
Fax +27 12 428 6928
THE REPUBLIC OF UGANDA, MINISTRY OF WORKS, HOUSING AND COMMUNICATIONS PAGE 7000 - 26
GENERAL SPECIFICATIONS FOR ROAD AND BRIDGE WORKS SERIES 7000 - TOLERANCES, TESTING AND QUALITY CONTROL
South Africa
8012
Tel +27 21 421 2577
Fax +27 21 425 1279
THE REPUBLIC OF UGANDA, MINISTRY OF WORKS, HOUSING AND COMMUNICATIONS PAGE 7000 - 27