Project 306 Transformer Report
Project 306 Transformer Report
Project 306 Transformer Report
Design Project
Due Date: December 4 th, 2022 @ 10:00pm
Design & Specifications of a Single -phase
Transformer
Section #7
Serial #9
Name Family Name First Name
ALALMIE NAYEF
KFUPM ID#: 2 0 1 7 5 2 5 1 0
1.1 Background:
1.2 Objectives:
The main objective of this project is to determine the transformer’s kVA rating
based on the standard sizes as well as to determine the primary and secondary
current of the chosen transformer. In addition, efficiency of the transformer under
different loading conditions (LD’s) must be determined.
1.3 Design Requirements and information
Specifying the customer needs is one of the most important steps in the design
process of a single-phase transformer. However, some of these needs are
presented in constrains to be followed. Which are:
The selection of the transformer is restricted on given standard sizes on the market:
The first step of selecting a proper transformer from the standard sizes is to
calculate all possible loads in the building:
The total KVA capacity required for the transformer (including the additional future
loads and the starting factor) is 𝟑𝟑 𝐊𝐕𝐀. Therefore, a transformer of 𝟑𝟕. 𝟓 𝐊𝐕𝐀
must be selected.
Based on the selected standard transformer size, the Primary current can be found
from the relation:
𝟑𝟕𝟓𝟎𝟎
𝐈𝑷 = = 𝟔𝟐. 𝟓 𝑨
𝟔𝟎𝟎
Similarly, the Secondary current is found as:
𝟑𝟕𝟓𝟎𝟎
𝐈𝒔 = = 𝟏𝟕𝟎. 𝟒𝟓𝟓 𝑨
𝟐𝟐𝟎
There are two approaches to find the full load output power in kW, the first by
assuming that the full load is for the existing devices in the building (not including
future loads), Therefore, the full load capacity will be calculated as:
The second approach is to consider the future 10% load. But it cannot be directly
found since the power factor for the future loads is not known.
In order to find the efficiency of the transformer when all devices in the building
are running (Not including future loads), The following assumptions are made:
𝐏𝒐𝒖𝒕 𝟐𝟏𝟗𝟓𝟎
𝜼= × 100 = × 100 = 𝟗𝟑. 𝟓𝟒%
𝐏𝒐𝒖𝒕 + 𝐏𝒍𝒐𝒔𝒔𝒆𝒔 𝟐𝟏𝟗𝟓𝟎 + (𝟗𝟎𝟕) + (𝟔𝟎𝟗)
The efficiency of the transformer when all existing loads are connected has been
calculated. Nevertheless, it is possible that not all loads are plugged in at the same
time resulting in different copper losses and different efficiencies. Therefore, the
efficiency of the transformer considering the following three scenarios is calculated
as:
𝑺 𝟒𝟎𝟎𝟎 + 𝟏𝟒𝟎𝟎𝟎
𝐈𝒍𝒐𝒂𝒅−𝑨 = = = 𝟖𝟏. 𝟖𝟐 𝑨
𝐕𝒔 𝟐𝟐𝟎
𝟐
𝐏𝒄𝒖−𝑨 = 𝐈𝒍𝒐𝒂𝒅−𝑨 × 𝑹 = 𝟖𝟏. 𝟖𝟐𝟐 × 𝟎. 𝟎𝟑𝟏𝟐𝟏𝟕 = 𝟐𝟎𝟖. 𝟗𝟖𝟏 𝑾
𝐏𝒐𝒖𝒕−𝑨 𝟏𝟓𝟗𝟎𝟎
𝜼𝑨 = = × 100 = 𝟗𝟓. 𝟏𝟎𝟕%
𝐏𝒐𝒖𝒕−𝑨 + 𝐏𝒍𝒐𝒔𝒔𝒆𝒔 𝟏𝟓𝟗𝟎𝟎+(𝟐𝟎𝟖.𝟗𝟖𝟏)+(𝟔𝟎𝟗)
Case B - Kitchen equipment & Dishwasher:
𝑺 𝟐𝟎𝟎𝟎 + 𝟓𝟎𝟎
𝐈𝒍𝒐𝒂𝒅−𝑩 = = = 𝟐𝟎. 𝟒𝟓𝟓 𝑨
𝐕𝒔 𝟐𝟐𝟎
𝟐
𝐏𝒄𝒖−𝑩 = 𝐈𝒍𝒐𝒂𝒅−𝑩 × 𝑹 = 𝟐𝟎. 𝟒𝟓𝟓𝟐 × 𝟎. 𝟎𝟑𝟏𝟐𝟏𝟕 = 𝟏𝟑. 𝟎𝟔𝟏 𝑾
𝐏𝒐𝒖𝒕−𝑩 𝟑𝟗𝟎𝟎
𝜼𝑩 = = × 100 = 𝟖𝟔. 𝟐𝟒𝟒%
𝐏𝒐𝒖𝒕−𝑩 + 𝐏𝒍𝒐𝒔𝒔𝒆𝒔 𝟑𝟗𝟎𝟎+(𝟏𝟑.𝟎𝟔𝟏)+(𝟔𝟎𝟗)
𝑺 𝟐𝟎𝟎𝟎 + 𝟓𝟎𝟎
𝐈𝒍𝒐𝒂𝒅−𝑪 = = = 𝟏𝟏. 𝟑𝟔𝟒 𝑨
𝐕𝒔 𝟐𝟐𝟎
𝟐
𝐏𝒄𝒖−𝑪 = 𝐈𝒍𝒐𝒂𝒅−𝑪 × 𝑹 = 𝟏𝟏. 𝟑𝟔𝟒𝟐 × 𝟎. 𝟎𝟑𝟏𝟐𝟏𝟕 = 𝟒. 𝟎𝟑𝟏𝟏 𝑾
𝐏𝒐𝒖𝒕−𝑪 𝟐𝟏𝟓𝟎
𝜼𝑪 = = × 100 = 𝟕𝟕. 𝟖𝟏𝟑%
𝐏𝒐𝒖𝒕−𝑪 + 𝐏𝒍𝒐𝒔𝒔𝒆𝒔 𝟐𝟏𝟓𝟎+(𝟒.𝟎𝟑𝟏𝟏)+(𝟔𝟎𝟗)
2.7 Determination of Maximum efficiency
The Maximum efficiency of a transformer occurs when the copper losses are equal
to core losses. Therefore, the maximum efficiency of the transformer considering
power factor of 0.9 can be calculated as:
𝑽𝑨 × 𝑷𝑭
𝜼𝒎𝒂𝒙 = × 100
(𝑽𝑨 × 𝑷𝑭) + (𝟐 × 𝐏𝒄𝒐𝒓𝒆 )
𝟑𝟕𝟓𝟎𝟎 × 𝟎. 𝟗
𝜼𝒎𝒂𝒙 = × 100 = 𝟗𝟔. 𝟓𝟏𝟕%
(𝟑𝟕𝟓𝟎𝟎 × 𝟎. 𝟗) + (𝟐 × 𝟔𝟎𝟗)
Chapter 3
Conclusion and Recommendation
To conclude, this report has gone through the steps of designing a single-phase
transformer following the standard sizes, and under some constraints. Also, it has
found different parameters of the transformer such as its Capacity and efficiency.
It was observed that there was no further information regarding the future loads
added for the transformer. Hence, this info helped only in deciding the size of the
transformer. I recommend that more specific details are given in the future
regarding the future loads to be added.