Embankment Assignment Two
Embankment Assignment Two
By
Contents
1 INTRODUCTION .................................................................................................................................... 3
2 REFERENCES ....................................................................................................................................... 24
Embankment Dam
Figure1.1 Gradation curve of base soil before regarding ......................................................................... 11
4
Embankment Dam
Design a suitable section of an embankment dam for the following conditions. Also
draw cross section of the dam (Illustrate every component of the dam section and the
foundation you designed).
1. Hydrology
River bed level 103.0 m
Dead storage level 123.0 m
F.S.L. 125.0 m
H.F.L. 128.0 m
F = Fetch length at maximum reservoir level (km) = 0.8 km as measured from the topomap
Size of command area to be irrigated is 1000 ha with a duty of 2l/s/ha.
The river across where the dam is to be constructed has sufficient yearly flows for the demand.
2. Geology and geotechnical conditions
The foundation consists of sand mixed with gravel to a depth of 12m, which is accompanied
by a sound rock formation after this depth.
3. Construction material
Two types of materials have been identified at sufficient quantities at a distance of 1.5 km
from the dam site: Sand mixed with gravel and Silty clay.
Grain size analysis of samples collected from the Silty clay borrow area are given below.
Sieve No. Percent Passing
4 95
10 90
20 85
40 75
60 60
140 45
200 30
Data not given can be assumed appropriately, and when necessary sources of information
have to be cited.
5
Embankment Dam
INTRODUCTION
1.1 Embankment Dams
Depending on the environment, embankment dams can be designed with a wide range
of cross sections and materials. They must be the best possible products made from local
materials and they must complement their surroundings (Jansen, 1988).
The oldest types of embankments are earthen dams and levees because they can be made
from natural materials with little preparation and simple tools. However, the cost of
transportation and dumping the materials for the dam was quite high in the past.
However, the cost of transporting and laying the materials for the dam has significantly
decreased thanks to recent advancements in earth moving equipment. The cost of
gravity dams on the other hand, has gone up because of an increase in the cost of
concrete, masonry, etc. Earthen dams are still cheaper as they can utilize the locally
available materials, and less skilled labor is required for them (Garg, (2005).),Until
modern times, embankment dams were designed based on experience and precedence
(empirical means). However, the engineering literature is replete with accounts of
failures of embankment dams. These failures produced the realization that totally
empirical means must be replaced, or at least supplemented, by analytical engineering
procedures in both design and construction. (USBR, 2012.).
1.2 Foundation
There are two key requirements for an earth fill dam foundation: (1) it must should
provide stable support for the embankment under all saturation and loading
conditions, and (2) it must give enough seepage resistance to prevent internal erosion
or excessive water loss. Although the foundation isn't actually designed, certain
foundation-related provisions are included in designs to guarantee that the
fundamental requirements will be satisfied (USBR, 2012). A small to medium earth
dam and rock fill dams can be supported by the foundation, which is made of sand
6
Embankment Dam
and gravel. Depth of sand and gravel foundation (12m) is less than height of the dam
and it is also less than 50feet it is exposed shallow foundation (USBR, 2012.) Therefore,
provide positive complete cutoff up to impervious foundation(Garg, 1976).
Use silty clay material for core and positive cutoff.
The cut off shall be located such that its center line should be within the base of
impervious core. The positive cut off should be keyed at least to a depth of 0.4 meter
into continuous impervious sub stratum or in erodible rock formation and a minimum
bottom width of 4.0 meter is recommended. Side slopes of at least 1:1 or flatter may
be provided in case of over burden while 1/2:1 and 1/4:1 may be provided in soft rock
and hard rock respectively. For this specific dam for safety purpose 4m bottom width
with slope of 1/2:1 is taken. therefore, top width of cut off is 4m + 48m =52m
Cut off height should extend at least 1m above water level of the dam. therefore, its
height will be 31m.
The positive cut off should be taken at least one meter in to continue impervious
substratum (DAMS, 1979).
specifications, normal freeboard is the elevation difference between the top of the dam
without camber and the higher of the top of conservation storage or top of joint-use
storage.
Here additional parameters like wind speed in the area is not available simply
recommended free board for the dam is taken from the following table.
Table1.1 free board requirement
Given that the fetch length is 0.8 km, the normal free board can be calculated as 1.2 m,
while the free board for MWL is 0.9 m. free board F=2.1m,
finally, free board F=2.1m
Now total height of dam is
H = 25 + 5 + 2.1 = 32m
8
Embankment Dam
9
Embankment Dam
1.5.1 Sloping
The slope of embankment dam, it depends on the following items
Material type
Dam height
Previous experiences
Foundation condition
Table1.2 Tentative slopes of shoulder for different embankment materials
10
Embankment Dam
The earth embankment will most likely be built with a core made of relatively
impervious material surrounded by coarser shells in current practice. Zoning is a crucial
precaution against failure.
In the given site we have basically two types of material. Here it is better to zone part
in to two zones.
Use Sand mixed with gravel which is available near the site and excavated from
foundation for shell at U/S and D/S side and Sand mixed with clay as core of the
dam.
Pervious or impervious foundation with positive cut off -provide minimum core a
(top width 10ft=4m.
Core may be located centrally or inclined upstream. Inclined core reduces pore water
pressure at downstream and by it increases safety.
Slope of core can be now estimated from height of crest and bottom width and top
width of crest. Bottom width of core is equal to top width of positive cut off which
is equal to 52m.Slope is therefore approximately 1:2.5
Width of U/S Shell and D/S is 57m and 41m respectively
11
Embankment Dam
4 95
10 90
20 85
40 75
60 60
140 45
200 30
Solution
Step 1: draw the gradation curve of the base soil, by using the given sieve size and
percentage finer.
12
Embankment Dam
13
Embankment Dam
Step-2: check if base soil contains no gravel (>No 4-sieve size or 0.075mm)
The base soil contains gravel since percentage of fineness at sieve number 4 (large
sediment size) is not 100 % (95%).
Table1.4 Regarding Base soil
Sieve No Sieve Size(mm) Percentage finer Percentage finer (Regraded)
4 4.75 95
95/95*100=100.000
10 2 90 90/95*100=94.737
20 0.85 85 85/95*100=89.474
40 0.425 75 75/95*100=78.947
60 0.25 60 60/95*100=63.158
Step 3: prepare adjusted gradation curves for base soils that have particles larger than the No 4
sieve
14
Embankment Dam
Step-4: place the base soil in the category determined by the percentage passing the
No-200 (0.075mm) sieve from the re-graded gradation curve data according to
(Table5)
Since the percentage passing the No- 200 (0.075mm) sieve from the re-graded
gradation curve is 30 (from table) which is between 15-39 it is under base soil category
of 3.
15
Embankment Dam
Step-5: Determine the max allowable D15 for the filter according to Table 6 and
label it as tentative control point 1
Table 1.6 filtering criteria maximum D15
A=31.579%
mm = 1. 16mm
Step-6: Determine the minimum allowable D15 in accordance with (Table-7) and label it
Table 1.7 permeability criteria
Since we don’t have significant D15 passing (as shown in gradation curve of
base soil), take the minimum possible value=0.1mm from the table above.
16
Embankment Dam
Step 7 : Preventing the use of gap graded filter materials by narrowing the width of the
allowable filter design band by determining the ratio of max.D15 to min D15 sizes by using
table 8 i.e. ( max.D15/min.D15 less than or equal to 5 )
In this case > 5 (max D15 and min D15 are determined in steps 5 and 6
respectively), therefore it need adjustment. Since the main purpose of the filter is to
serve as a filter material the minimum D15 is kept controlled. But some modification
should be taken for the maximum D15 value.
17
Embankment Dam
Step 8: to prevent gap-graded filters both sides of the design filter band will have a coefficient of
uniformity (CU), defined as:
CU=
Step 9: Determine the Min D5 & Max. D100 sizes of the filter according to table 9 and label it as
control 5 and 6 respectively.
Table 1.9 maximum and minimum particle size criteria
18
Embankment Dam
Step 10: Determine Max. D90 & Min. D10 to minimize segregation during
construction.
Calculate a preliminary minimum D10 size by dividing minimum D15 size by1.2
Determine maximum D90 using table 10 and label it as control point 7
19
Embankment Dam
Step 11: connect control points4,2&5 to form a partial design for the fine side of the filter band.
Connect control point 6,7,3 & 1for the coarse side of the filter band.
20
Embankment Dam
Experience has shown that, in the majority of cases, properly graded and placed riprap
with adequate durability properties furnishes the best type of upstream slope protection
at the lowest cost (USBR, 2012).
The thickness of riprap should be sufficient to accommodate weight and size of
stones necessary to resist wave action.
A 3feet, which is about 1m, minimum thickness is used.
21
Embankment Dam
These need to be protected against erosion by wind and rainfall runoff and the
burrowing animals. This also needs to be protected against possibility of seeping of
rain water and forming internal erosion (piping and sloughing of inside of
embankment).
NB. Sizing and layer thickness of rip rap is not done here due to in availability of wind
speed which is useful to compute wave height.
D/s slopes are provided protection by covering the surface with a layer of rock fill or
by establishing grass cover. Provide berms to limit the vertical distance over which
runoff can concentrate.
If grasses or other vegetation are planted, those suitable for a given locality should be
selected, and a layer of topsoil is usually required.
In this dam establishing grass cover is sufficient
22
Embankment Dam
23
Embankment Dam
24
Embankment Dam
2 REFERENCES
DAMS, G. L. (1979). Guide Lines for Design of Large Earth And Rock Fill
Dams. New Delhi:.
25