Project 1

This document outlines the timeline for an e-commerce website development project. It is broken into several phases including requirements analysis, design and development, integration of payment and shipping functionality, inventory management, testing and launch, and marketing and promotion. The project begins with requirements analysis in June 2023 and concludes with ongoing maintenance and support starting in November 2023. Key milestones include platform selection, functionality development, integration of payment and shipping, testing and launch, and various marketing tasks.

Uploaded by

Sotu Kdapt
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
9 views9 pages

Project 1

This document outlines the timeline for an e-commerce website development project. It is broken into several phases including requirements analysis, design and development, integration of payment and shipping functionality, inventory management, testing and launch, and marketing and promotion. The project begins with requirements analysis in June 2023 and concludes with ongoing maintenance and support starting in November 2023. Key milestones include platform selection, functionality development, integration of payment and shipping, testing and launch, and various marketing tasks.

Uploaded by

Sotu Kdapt
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 9

E-commerce Website Development and Design: Requirements analysis

Start: 6/14/23 ID: 1 Start: 6/14/23 ID: 2 Start: 6/14/23 ID: 3 FS


Finish: 11/14/23 Dur: 22 wks Finish: 10/3/23 Dur: 16 wks Finish: 6/27/23 Dur: 2 wks
Comp: 0% Comp: 0% Res:

FS

Page 1
Ongoing Maintenance and Support
Start: 6/14/23 ID: 19
Finish: 6/27/23 Dur: 2 wks
Comp: 0%

Page 2
Platform selection/development Functionalitydevelopment Payment andshipping integration
FS Start: 6/28/23 ID: 4 FS Start: 7/26/23 ID: 6 FS Start: 9/20/23 ID: 7
Finish: 7/25/23 Dur: 4 wks Finish: 9/19/23 Dur: 8 wks Finish: 10/3/23 Dur: 2 wks
Res: Res: Res:

FS

Inventory management
Start: 9/20/23 ID: 9
FS FS
Finish: 10/3/23 Dur: 2 wks
Res:

FS

Testingand launch
Start: 9/20/23 ID: 10 FS
Finish: 10/3/23 Dur: 2 wks
Res:

FS FS FS

UI/UX design Wireframes/mockups


Start: 6/28/23 ID: 5 FS Start: 7/26/23 ID: 8 FS
Finish: 7/25/23 Dur: 4 wks Finish: 8/22/23 Dur: 4 wks
Res: Res:

Page 3
Page 4
Marketing and Promotion Market research Marketing strategydevelopment
Start: 10/4/23 ID: 11 Start: 10/4/23 ID: 12 FS Start: 10/18/23 ID: 13 FS
Finish: 11/14/23 Dur: 6 wks Finish: 10/17/23 Dur: 2 wks Finish: 10/31/23 Dur: 2 wks
Comp: 0% Res: Res:

FS

Page 5
FS

FS

FS

Page 6
SEO
Start: 11/1/23 ID: 14
Finish: 11/14/23 Dur: 2 wks
Res:

Page 7
Social media marketing
Start: 11/1/23 ID: 15
Finish: 11/14/23 Dur: 2 wks
Res:

Emailmarketing
Start: 11/1/23 ID: 16
Finish: 11/14/23 Dur: 2 wks
Res:

Data analysis
Start: 11/1/23 ID: 17
Finish: 11/14/23 Dur: 2 wks
Res:

Influencer/partner collaboration
Start: 11/1/23 ID: 18
Finish: 11/14/23 Dur: 2 wks
Res:

Page 8
Critical Critical Summary Critical Marked Project Summary

Noncritical Summary Marked Highlighted Critical


Project: Project1
Date: W 6/14/23 Critical Milestone Critical Inserted Critical External Highlighted Noncritical

Milestone Inserted External

Page 9