Distributed Generation Impact and Cost Analysis
Distributed Generation Impact and Cost Analysis
Priyanka Priyadarshini Padhi, R. K. Pati & Akhilesh Arvind Nimje
School of Electrical Engineering, KIIT University, Bhubaneswar -751024, India
E-mail : [email protected] ,[email protected]
Abstract - This paper presents the reason for the current interest in distributed generation and the challenges that are faced while
increasing its share in the electricity generation mix. Under the present centralized generation paradigm, electricity is mainly
produced in bulk amount at large generating stations, wheeled though the transmission and distribution grids to the end consumers.
However, the recent quest for energy efficiency and reliability and reduction of greenhouse gas emissions led to explore possibilities
to alter the existing generation paradigm and increase its overall performance with the implementation of distributed generation.
Keywords - Distributed generation, grid, solar PV cells, voltage regulation, reliability, renewable energy sources, and cost
effectiveness.
Special Issue of International Journal of Power System Operation and Energy Management, ISSN (PRINT): 2231 – 4407, Volume - 1, Issue-3
91
Distributed Generation: Impacts and Cost Analysis
reduction of losses and the impacts of DG on over- network using commercial software tools that shows
current protection. The rules for modeling DG improvement in the reliability indices [12]. The
interaction and its zero point analysis have been analytical approach to calculate the reliability of the
reported in the literatures so far. The 1547 series of system that included some intrinsic attributes of the DG
IEEE standards for interconnecting distributed resources and the distribution system including DG failure,
to the power system is a set of standards consisting of 6 component failure, change in load demand etc [21].
parts [2]. The standards provide criteria and requirement Many factors were considered for the reliability indices
for interconnecting distributed resources to the power calculation in the proposed technique The location for
system. The IEEE 1547.1 defines the requirement for the placement of DGs is of key importance. In [14], the
interconnecting equipment that connects the DG to the authors studied the effects of DG on system reliability
electric power system is presented [3]. The IEEE 1547.2 on an Iranian Distribution system. The positive impacts
provides technical details and application to understand included faster restoration and reduced voltage sags
the IEEE standard is presented [4]. The IEEE 1547.3 while the negative impacts could be sympathetic
guide addresses engineering concerns for design, tripping, increased fuse blowing etc. A few papers had
operation and integration of DG island systems [5]. The presented validation models for calculating reliability
IEEE 1547.6 standard focuses on criteria, test and indices . In [17], the basic data for reliability assessment
requirements for interconnection distribution secondary of distribution system was presented. The paper also
network of area electric power system (Area EPS) with contained basic results of continuity studies for a range
Local EPS having Distributed Resource generation [6]. of sensitivity analysis and alternate configurations. The
The impacts of installing DG on voltage, losses and impact of installing DG as backup at various locations
reliability indices of a residential distribution network on the distribution circuit is also explored in this
are studied based on various criteria. research.
A. Losses C. Voltage Impacts
Installation of DG impacts the losses and overall The DG installation can impact the overall voltage
power factor of the total system. The reduction of profile of the system. Inclusion of DG can improve
transmission losses with DG using power summation feeder voltage of distribution networks in areas where
method have been reported [7]. The loss analysis at voltage dip or blackouts are of concern for utilities. The
various penetration levels of DG and distributing were DG has a greater impact on electric losses, voltage
presented [8]. profile, flicker, harmonics, short circuit levels, islanding
and reliability. The optimal location of DG allocation is
B. Reliability
an important aspect. wer system were analyzed. The
Distribution system reliability is an important factor paper also addresses DG impacts on short circuit levels
in system’s planning and operation. The reliability and the islanding operation of DG. The approach makes
indices such as System Average Interruption Duration use of controlling DGs reactive power based on its real
Index (SAIDI), System Average Interruption Frequency power to satisfy system voltage requirements. The DG is
Index (SAIFI), Customer Average Interruption installed at the lowest voltage location and distributing it
Frequency Index (CAIFI), Customer Average across several locations to explore the impacts. Also, the
Interruption Duration Index (CAIDI), Average Service implication of installing DG on one phase and its impact
Availability Index (ASAI), Average Service on the other phases has been investigated.
Unavailability Index (ASUI), Energy Not Supplied
(ENS) etc presented by the IEEE guide are used to IV. COST ANALYSIS
evaluate reliability of the system. The methods of data
A. The Levelized Cost of Energy
collection to calculate the reliability indices of system is
crucial [9]. It takes into account the power consumption The Levelized Cost of Energy (LCOE) is the most
pattern, selection of relevant index, outage data transparent metric used to measure electric power
collection and actual consumer perceptions and hence generating costs, and is widely used as a tool to compare
would contribute towards improving the reliability. The the generation costs from differing sources. The LCOE
results showed that SAIDI, SAIFI, CAIDI and ASAI is a measure of the marginal cost (the cost of producing
were the mostly used indices [10]. However, a general one extra unit) of electricity, over an extended period,
Distribution Reliability (DISREL) program can used to and is sometimes referred to as Long Run Marginal Cost
validate the impact of distributed generation on system or LRMC. The LCOE is representative of the electricity
performance improvement and its reliability [11]. It price that would equalize cash flows (inflows and
shows that DG is a cost-effective solution that could outflows) over the economic life time of an energy
benefit both utility and customers. The modeling generating asset. It is the average electricity price
techniques for DG, and its application to a radial needed for a Net Present Value (NPV) of zero when
Special Issue of International Journal of Power System Operation and Energy Management, ISSN (PRINT): 2231 – 4407, Volume - 1, Issue-3
92
Distributed Generation: Impacts and Cost Analysis
performing a discounted cash flow (DCF) analysis. With reports wind construction periods of 1 year (unlike
the average electricity price equal to the LCOE, an AEMO), and the effects of this are explored.
investor would breakeven and so receive a return equal
TABLE 1. Construction Periods and Economic
to the discount rate on the investment.
Lifetimes
= Technology
Construction
Period
Economic
Lifetime
Where: Wind 2year 30years
n = Project lifetime (yrs). Solar PV 1year 30years
t = Year in which sale or cost is incurred. Solar Thermal 2year 30years
r = Discount rate (%) D. The Capacity Factor
By definition this is the point at which the Net In the case of renewable energy generators the
Present Value (summation of the Present Values, PV, of assumed capacity factor of a facility has a significant
the cash flows) for a project is zero: impact on the LCOE. For renewable energy generators,
the capacity factor is generally dependant on the quality
NPV = = 0 of the renewable resource. In the interests of a consistent
approach, constant capacity factors were used for each
Where : technology type. These capacities were based on
reasonable resource qualities for Australian conditions,
PV = summarized below in Table 2, as used in the EPRI
study.
EBIT = Earnings Before Interest TABLE 2. Capacity Factors
Tax DEP = Depreciation Capacity
Technology Resource Quality
Factor
CAPEX = Capital Expenditure
Wind 6.8m/s 30%
T = Corporate Tax rate (%)
Solar PV 2445 KWh/m2/yr 20%
B. Global Assumptions
Varried by
Tax: The corporate tax rate is assumed to be 30% Solar
2400 KWh/m2/yr plant storage
for the purposes of all cash-flow analysis. Thermal
configuration
Depreciation : The electric utility industry typically uses
the straight-line method, which was used in this V. RENEWABLE ENERGY TECHNOLOGY
analysis. For a 25 year lifetime, the annual depreciation COST REVIEW
is 4%, and for a 30 year lifetime, the annual depreciation This paper has undertaken a review of current and
is 3.33%. future costs of three forms of renewable energy
Exchange Rate : In line with the Mid Year Economic technology, comparing data from a range of
Financial Outlook approach, the exchange rate is international and Australian-specific studies, taking care
assumed to remain around the levels seen at the time the to compare data on the same basis of financial
forecasts were prepared3. As of March 01 2011, a US$ assumptions (discount rates) and resource quality. The
exchange rate was $0.985 used, and an EU€ exchange purpose was to compare both the current costs, along
rate of $0.70 was used. with the rate of decrease, and the reason for differences
between the studies. The Australian-specific datasets are
C. Construction Period and Economic Lifetime the ‘Australian Energy Generation Technology Costs’
The construction period and economic lifetime can report by EPRI, and the 2010 dataset used by the
have a considerable affect on the levelized cost of Australian Energy Market Operator (AEMO), largely
generation. This is particularly important for protracted based on the EPRI data with a review from ACIL
construction periods (lead times). The economic and Tasman. The assessment reviewed technical and
lifetimes and construction periods used are presented in economic parameters of wind, photovoltaic and solar
Table 1, and are based on the AEMO dataset. The IEA thermal energy generation technologies, considering
technology specific learning rates and cost reduction
potentials. It includes a detailed exploration of the
Special Issue of International Journal of Power System Operation and Energy Management, ISSN (PRINT): 2231 – 4407, Volume - 1, Issue-3
93
Distributed Generation: Impacts and Cost Analysis
Special Issue of International Journal of Power System Operation and Energy Management, ISSN (PRINT): 2231 – 4407, Volume - 1, Issue-3
94
Distributed Generation: Impacts and Cost Analysis
[1] Willis, H.L., "Analytical Methods and Rules of [11] H. Falaghi; M.-R. Haghifam, "Distributed
Thumb for Modeling DG-Distribution Generation Impacts on Electric Distribution
Interaction," Power Engineering Society Summer Systems Reliability: Sensitivity Analysis,"
Meeting, 2000. IEEE, vol.3, no., pp.1643-1644 Computer as a Tool, 2005. EUROCON 2005.The
vol. 3, 2000.
Special Issue of International Journal of Power System Operation and Energy Management, ISSN (PRINT): 2231 – 4407, Volume - 1, Issue-3
95
Distributed Generation: Impacts and Cost Analysis
International Conference on , vol.2, no., pp.1465- [16] Borges, C.L.T.; Falcao, D.M., "Impact of
1468, 2005. distributed generation allocation and sizing on
reliability, losses and voltage profile," Power
[12] McDermott, T.E.; Dugan, R.C., "Distributed
Tech Conference Proceedings, 2003 IEEE
generation impact on reliability and power
Bologna , vol.2, no., pp. 5 pp. Vol.2-, 23-26 June
quality indices," Rural Electric Power
2003.
Conference, 2002. 2002 IEEE , vol., no., pp.D3-
D3_7, 2002. [17] Barker, P.P.; De Mello, R.W., "Determining the
impact of distributed generation on power
[13] Allan, R.N.; Billinton, R.; Sjarief, I.; Goel, L.;
systems. I. Radial distribution systems," Power
So, K.S., "A reliability test system for
Engineering Society Summer Meeting, 2000.
educational purposes-basic distribution system
IEEE , vol.3, no., pp.1645-1656 vol. 3, 2000.
data and results," Power Systems, IEEE
Transactions on , vol.6, no.2, pp.813-820, May [18] ] Le, A.D.T.; Kashem, M.A.; Negnevitsky, M.;
1991. Ledwich, G., "Control Strategy of Distributed
Generation for Voltage Support in Distribution
[14] Brown, R.E.; Ochoa, J.R., "Distribution system
Systems," Power Electronics, Drives and Energy
reliability: default data and model validation ,"
Systems, 2006. PEDES '06. International
Power Systems, IEEE Transactions on , vol.13,
Conference on , vol., no., pp.1-6, 12-15 Dec.
no.2, pp.704-709, May 1998.
2006.
[15] R. Billinton, R, N. Allan, “Reliability Evaluation
[19] Chensong Dai; Baghzouz, Y., "Impact of
of Power Systems”, 2nd edition, Plenum Press,
distributed generation on voltage regulation by
New Yorkm 1996.
LTC transformer," Harmonics and Quality of
Power, 2004. 11th International Conference on ,
vol., no., pp. 770-773, 12-15 Sept. 2004.
Special Issue of International Journal of Power System Operation and Energy Management, ISSN (PRINT): 2231 – 4407, Volume - 1, Issue-3
96