ARInt.20189.2-08
ARInt.20189.2-08
ARInt.20189.2-08
net/publication/324654080
CITATIONS READS
7 1,668
2 authors:
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by Mohammad Abazid on 19 January 2019.
ABSTRACT
The study was carried out in order to obtain a comprehensive conceptualization on
risk and the consequences it has in the fields of construction and the required
management operation. Along with the utilities and techniques adopted to control
risk in the construction industry, the effect of risk on the project assessment is also
discussed. The aspiration of the topic of research is to be able to enquire into the
productive method of implementing risk management in construction industry, to be
able to respect the various types of managing techniques manipulated to reduce risk,
to define the utility of implementation of the risk management, to resolve the
components that affect the execution of risk management in the life cycle of projects.
The following study discloses the research which focuses on distinguishing the
practices of risk management and construction projects in the Arab region.
Keywords: Risk management, management, construction, project
INTRODUCTION
The risk management of a certain project is considered as one of the major roles that is
undertaken by the project manager. Proper and systematic techniques, knowledge and
experience are required approaches to enable effective and efficient risk management. For
instance, knowledge of the unanticipated events that might prevail while execution of the
project is required (Serpella et al, 2014).
Considering that projects carried out in the construction division are widely complicated and
usually have significant budgets, the major priority of the project manager is to reduce the
associated risks. It should be noted that risk management is not a utility that ensures success
but rather aids in increasing the likelihood of acquiring success. Therefore, risk management
is a proactive concept as opposed to a reactive concept.
In compliance with the Project Management Institute (PMI, 2004), one of the nine most
critical parts of project authorization is project risk management which indicates a sturdy
relationship between risk managing and project success. The majority of the time, risk is
administered through the manipulation of contingencies or floats (respectively money or
time) which are not defined relying on a comprehensive analysis of the risks that can trigger a
certain project, which in many cases is insufficient to cover the outcomes of the risks that
take place during the project apprehension (Serpella et al, 2014).
The majority of the applications utilized in the project risk management pinpoint their
concentration on quantitative risk analysis. On the contrary, these systems do not allow
remedial measures for risks or problems (Tah and Carr, 2001).
(Lyons and Skitmore, 2004) discovered that the most conventional risk identification
methods utilized in the engineering construction industry is brainstorming. A matrix for
determining the suitable risk management approaches in the built environment of each stage
of risk was developed by (Forbes et al, 2008). Among several others; artificial intelligence,
decomposition, probabilistic analysis, sensitivity analysis and decision trees are some of the
techniques included.
In the construction industry, analyzing and managing risks is a significant part of the decision
making procedure. The high degree of risks from the nature of micro and macro
environments in particular to construction are greatly associated with the construction
industry and their clients (Zavadskas et al. 2010). Comparatively, the construction industry’s
reputation is very weak when concerned in coping with risks due to the failure of various
projects meeting the deadlines and budget targets.
It is commonly known that construction industry is one of the most treacherous, demanding
and dynamic industries across the globe (Hwang et al., 2017). This industry is vulnerable to a
variety of risks as a result of its monetary extremity, intricate procedures, long project
durations, eisky environment and relationships with associates (Panthi et al., 2009).
The purpose behind the process of risk identification is the ability to determine the probable
risks which may influence the project. In the literature works, there are various mechanisms
manipulated in order to categorize project risks and risk sources that can be utilized in
establishing those compilations. The following is a list of possible risks which can be found
in literature works (Smith et al. 2006), (Potts, 2008), (Lester, 2007).
Budgetary "Financial, Economical, Investment"
Bureaucratic " Legal, Political"
Environment "Environmental, Natural, physical
Technical "Technical"
Project "Contractual, client, Project objectives, Planning, scheduling, Construction,
Design, Quality, Operational, Organizational"
Human "Labor, stakeholder, Human factors, Cultural"
Market "Market"
Safety " Safety, Security, crime"
Materials "Resources, Logistics”
Furthermore, the complication of the socio-economics embraced in construction matters
causes it to be more prone to risk in which negative effects of the project sustainability might
be present (Zavadskas et al.,2010). The construction industry is greatly diverse and
miscellaneous, which is a result of several complicated circumstances, and in turn the
industry experiences a great matter of dynamic differentiation along with global sourcing and
inclination of the price competition. Generally, contractors have utilized high mark-ups in
order to prevail over these risks, but as their margins have become smaller, the techniques
have no longer been effective (Baloi and Price, 2003). The phases included in construction
projects during the later decades have become much more complicated in nature, which is the
outcome of technological upgrading and stakeholder pressure, and are classified by an
amount of riskiness that have a dissenting impact on the projects (Jafarnejad et al.,2014).
CONCLUSION
Projects, in the later decades, have become more complicated and risky in the construction
industry as a result of the multiplicity nature of the activities among worldwide organizations.
The feasibility of the elimination of all the risks affiliated with a certain project is unlikely.
The best that can be achieved is the regulation of the risk allocated to various groups along
with the proper management of the risks. Chapman and Ward discussed that the choice
decisions of the contract are fundamental to both stakeholder management and the
management of the risks and unpredictability. Therefore, an integrated mechanism can be
established depending on a balanced inducement and risk sharing technique to contracting
alongside a better practice methodology to risk management in terms of the entire life cycle
of a project in which contractors usually are aimed at obtaining and acceptable scope of
excess margin.
REFERENCES
[1] Baloi, P., & Price, A. (2003). Modelling global risk factors affecting construction cost
performance. International Journal of Project Management, 21(4), 261–269.
[2] Cleland, D. I., & Gareis, R. (2006). Global project management handbook: Planning,
organizing, and controlling international projects. New York: McGraw-Hill.
[3] Del Caño, A., & De la Cruz, M. P. (2002). Integrated methodology for project risk
management. Journal of Construction Engineering and Management, 128(6), 473-
485.
[4] Forbes, D., Smith, S., Horner, M. (2008). Tools for selecting appropriate risk
management techniques in the built environment.Construction Management and
Economics, 26(11), 1241-1250.
[5] Gould, F. E., & Joyce, N.E. (2002). Construction project management.New Jersey:
Prentice Hall.
[6] Hasani, M., Tularam, G., & Regan, M. (2017). Impacts of cultural risk factors on
project success in the UAE construction industry. Australia: Modellling & Simulation
Society of Australia & New Zealand.
[7] Hillson, D. (2004). Effective opportunity management for projects – exploiting
positive risk. New York: Marcel Dekker.
[8] Hwang, B. G., Zhao, X., and Chin, E. W. Y. (2017). International construction joint
ventures between Singapore and developing countries: Risk assessment and allocation
preferences. Engineering Construction and Architectural Management, 24(2), 209-
228
[9] Kartam, N., & Kartam, S. (2001). Risk and its management in the Kuwaiti
construction industry: A contractors' perspective. International Journal of Project
Management, 19(6), 325-335.
[10] Lee, E., Park, Y., & Shin, J. (2009). Large engineering project risk management using
a Bayesian belief network. Academic Research International, 36(3), 5880-5887.
[11] Lester, A.(2007). Project management, planning and control. United States:
Butterworth-Heinemann.
[12] Li, B., Akintoye, A., Edwards, P. J., & Hardcastle, C.(2005). The allocation of risk in
PPP/PFI construction projects in the UK. International Journal of Project
Management, 23(1), 25-35.
[13] Lyons, T., & Skitmore, M. (2004). Project risk management in the Queensland
engineering construction industry: A survey. International Journal of Project
Management, 22(1), 51-61.
[14] Nouban, F., & Abazid, M. (2017). An overall of total quality management in the
construction engineering. Academic Research International, 8(4), 68-74.
[15] Olsson, R. (2007). In search of opportunity management: Is the risk management
process enough? International Journal of Project Management, 25(8),745-752.
[16] Panthi, P. (2009). Contingency estimation for construction projects through risk
analysis. International Journal of Construction Education and Research, 5(2), 79-94.
[17] PMI (Project Management Institute). (2004). A guide to the project management body
of knowledge: PMBOK. Pennsylvania: Project Management Institute.
[18] Potts, K.(2008). Construction cost management, learning from case studies.
Abingdon: Taylor Francis.
[19] Serpella, A., Ferrada, X., Howard, R., Rubio, L.(2014). Risk management in
construction projects: A knowledge-based approach.Social and Behavioral Sciences,
119 (2014),653–662.
[20] Smith. N.J., Merna, T., & Jobbling, P. (2006). Managing risk in construction projects.
New Jersey: Blackwell Publishing.
[21] Tah, J. H. M., & Carr, V. (2000). A proposal for construction project risk assessment
using fuzzy logic. Construction Management & Economics, 18(4), 491-500.
[22] Tah, J. Y., & Carr, V. (2001). Knowledge-based approach to construction project risk
management. Journal of Computing in Civil Engineering, 15(3), 170-177.
[23] Tohidi, H. (2011). The role of risk management in IT systems of organizations.
Procedia - Computer Science Journal, 3, 881-887.
[24] Tummala, V.M., & Burchett J. F. (1999). Applying a Risk Management Process
(RMP) to manage cost risk for an EHV transmission line project. International
Journal of Project Management, 17(4), 223-235.
[25] Uher, T. E., &Toakley, A. R. (1999). Risk management in the conceptual phase of a
project. International Journal of Project Management, 17(3), 161-169.
[26] Ward, S., & Chapman, C. (2003).Transforming project risk management into project
uncertainty management. International Journal of Project Management, 21(2), 97-
105.
[27] Yu, Z. (2002). Integrated risk management under deregulation. Power Engineering
Society Summer Meeting, 3, 1251-1255.
[28] Zavadskas, E. K., Turskis, Z., &Tamošaitiene, J. (2010). Risk assessment of
construction projects. Journal of Civil Engineering and Management, 16(1), 33–46.