Substation-Design-Guide R0 Signed
Substation-Design-Guide R0 Signed
DESIGN GUIDE
2009 December
Revision 0
RECORD OF REVISIONS
Rev. No. Date By Pages Description
Revision 0 2009 Dec BCHE All First issue
Substation Design Guide
Disclaimer
This Substation Design Guide (the Guide) was prepared by the Engineering division of
British Columbia Hydro and Power Authority (BC Hydro) and by British Columbia
Transmission Corporation (BCTC). This Guide is not intended as a design specification
or as an instruction manual for substations built for BCTC and shall not be used by any
third party for those purposes. Persons using the information included in this Guide shall
do so at no risk to BCTC, and they rely solely upon themselves to ensure that their use
of all or any part of this Guide is appropriate in the particular circumstances.
Any third party, its employees or agents must recognize that they are, at all times, solely
responsible for the design and construction of any substation built for BCTC. BCTC, BC
Hydro nor any of their employees or agents shall be, nor become, the agents of any third
party, in any manner whatsoever arising.
BCTC’s review of the specifications and detailed plans shall not be construed as
confirming or endorsing the design or as warranting the safety, durability or reliability of a
substation built for BCTC. BCTC, by reason of such review or lack of review, shall be
responsible for neither the strength or adequacy of design of a substation built for BCTC,
nor shall BCTC, BC Hydro, or any of their employees or agents, be responsible for any
injury to the public or workers resulting from the design or construction of any substation
built for BCTC.
In general, the advice by BCTC, any of its employees or agents, that the design meet
certain limited requirements of BCTC does not mean, expressly or by implication, that all
or any of the requirements of the law or other good engineering practices have been met
by a third party, and such judgement shall not be construed by a third party and others
as an endorsement of the design or as a warranty, by BCTC, or any of its employees.
The information contained in this document is subject to change and may be revised at
any time. BCTC should be consulted in case of doubt on the current applicability of any
item.
R0 Page ii
Substation Design Guide
Table of Contents
1 Introduction ............................................................................................................................1
2 Abbreviations .........................................................................................................................1
3 Safety.....................................................................................................................................1
3.1 Safety Incident Response and Reporting .......................................................................2
3.2 Safety Review.................................................................................................................2
4 Environmental........................................................................................................................2
4.1 Equipment Replacements ..............................................................................................3
4.2 Work Planning and Management ...................................................................................3
4.3 Incident Response and Reporting ..................................................................................3
4.4 Spill Contingency and Environmental Plans ...................................................................3
5 Project Scope of Work ...........................................................................................................4
5.1 User Requirements.........................................................................................................4
5.2 Review points .................................................................................................................4
5.3 BC Hydro Engineering Standards ..................................................................................5
5.4 BCTC Maintenance Standards.......................................................................................6
5.5 Other Standards .............................................................................................................6
5.6 Special Tools ..................................................................................................................6
5.7 Materials and Auxiliary Equipment .................................................................................7
5.8 Spare Parts.....................................................................................................................8
6 Documentation.......................................................................................................................8
6.1 General...........................................................................................................................8
6.2 Substation Design Basis.................................................................................................8
6.3 System Information and Studies.....................................................................................8
6.4 Drawings.........................................................................................................................9
6.5 Manuals ........................................................................................................................10
7 Interfacing ............................................................................................................................10
7.1 Distribution Interface.....................................................................................................10
7.2 Transmission Interface .................................................................................................11
7.3 Telephone Interface......................................................................................................11
8 Properties ............................................................................................................................11
8.1 Acquisition ....................................................................................................................11
8.2 Permits .........................................................................................................................11
R0 Page iv
Substation Design Guide
9 Substation Planning.............................................................................................................11
10 Common Substation Requirements .................................................................................12
11 Equipment ........................................................................................................................12
11.1 General .....................................................................................................................12
11.2 Transformers.............................................................................................................13
11.3 Shunt Reactors (Oil Filled)........................................................................................13
11.4 VTs, CTs and CVTs, CCs and WTs..........................................................................13
11.5 Series and Neutral Air-Core Reactors ......................................................................13
11.6 Shunt Capacitor Banks .............................................................................................13
11.7 TRV Capacitor Units .................................................................................................14
11.8 Station Service Transformers ...................................................................................14
11.9 Station Service Batteries and DC Power Supplies ...................................................14
11.10 Voltage Regulators ...................................................................................................14
11.11 Gas Insulated Switchgear (GIS) ...............................................................................14
11.12 Static and Series Compensation Equipment ............................................................14
11.13 Switching Equipment ................................................................................................14
11.14 Disconnect Switch.....................................................................................................14
11.15 Surge Arresters.........................................................................................................14
11.16 Circuit Breaker ..........................................................................................................14
12 Civil Design ......................................................................................................................15
12.1 Site Selection ............................................................................................................15
12.2 Site Preparation ........................................................................................................15
12.3 Seismic .....................................................................................................................15
12.4 Flood Protection........................................................................................................16
12.5 Insulating Oil Spill Containment for Outdoor Equipment...........................................16
12.6 Cable Trenches, Manholes, and Pull boxes and Duct ..............................................16
12.7 Fence ........................................................................................................................17
12.8 Footings ....................................................................................................................17
12.9 Support Structures ....................................................................................................18
12.10 Access Roads ...........................................................................................................18
13 Electrical Design ..............................................................................................................18
13.1 Clearances................................................................................................................18
13.2 Switchyard ................................................................................................................18
13.3 Major Equipment Control Cabinets ...........................................................................19
R0 Page v
Substation Design Guide
R0 Page vi
Substation Design Guide
R0 Page vii
Substation Design Guide
1 INTRODUCTION
This guide is a high level summary of substation functional design and construction
requirements. The intended audience is Contractors who design, construct, and commission
substation projects for the British Columbia Transmission Corporation (BCTC).
This Substation Design Guide applies to all BCTC substation projects. Contractors shall notify
BCTC when the requirements of this guide cannot be met for a project. Any variances from this
guide must be accepted in writing by BCTC.
Other documents that Contractors will refer to include:
• Information Management Process for BCTC Consultants.
• Drawing Management Process for BCTC Consultants.
• BC Hydro Engineering Standards.
• BCTC Maintenance Standards.
2 ABBREVIATIONS
BCH – British Columbia Hydro
BCTC - British Columbia Transmission Corporation
CC – Coupling Capacitor
CT – Current Transformer
CVT – Capacitive Voltage Transformer
LOO – Local Operating Order
MMBU – Material Management Business Unit, a division of BC Hydro
OSH – Occupational Safety and Health
PPE – Personnel Protective Equipment
PSSP – BCTC Power System Safety Protection
SA – Surge Arrester
SDA – Substation Distribution Asset. Substation assets associated with the supply of the
distribution system at 25 kV or below. The boundary of SDAs is the high side bushing of any
step down transformer and all associated equipment to connect to the distribution system.
SPR – BC Hydro Safety Practice Regulations
TA – Transmission Assets. Substation assets associated with the transmission system. See
boundary for SDA.
TRV – Transient Recovery Voltage
VT – Voltage Transformer
WT – Wave Trap
3 SAFETY
Safety is one of BCTC’s key operating considerations. It is consistently and visibly applied
throughout the corporation. Contractors shall follow this philosophy in substation projects by
R0 Page 1
Substation Design Guide
applying appropriate measures and all applicable statutory standards to eliminate the risk and
hazards that contribute to accidental injuries and occupational diseases.
The following documents provide a guide only in establishing safety requirements for
substation projects.
(a) WorkSafeBC Occupational Health & Safety Regulations
(b) BC Hydro Safety Practice Regulations (SPR)
(c) BCTC Power System Safety Protection (PSSP)
(d) BC Hydro Occupational Safety and Health (OSH) standards.
BCTC maintains a database of hazardous materials at substations. The Contractor will contact
the BCTC project manager to learn about known hazards at a substation. An example of this is
asbestos that may exist in a substation that does not pose a risk until disturbed.
4 ENVIRONMENTAL
BCTC requires that construction of a substation project be performed in an environmentally
responsible manner in accordance with the following key commitments of BCTC’s
Environmental Responsibility Principles and the Environmental Management System (EMS):
• Avoid and mitigate environmental impacts
• Meet or exceed environmental regulatory requirements
BCTC expects that if environmental incidents occur they will be mitigated in a duly diligent
fashion. The BCTC project manager is to be informed as soon as possible when an incident
occurs.
R0 Page 2
Substation Design Guide
R0 Page 3
Substation Design Guide
R0 Page 4
Substation Design Guide
BC Hydro holds all title and rights, including the copyright, in or to these
Engineering Standards.
These Standards have been prepared for or by BC Hydro to meet specific purposes
of BC Hydro. Any person receiving these Standards shall not use, copy, rely upon
or disclose them, in whole or in part, except:
(a) for the purpose of providing services to BC Hydro,
(b) with the prior written consent of BC Hydro, or
(c) as required by law.
BC Hydro, its servants or agents, regardless of fault or cause shall not be liable to
any person for injury, loss or damage arising out of the use of or reliance upon
these Standards, in whole or in part, except for those situations where the person
uses the Standards to provide services to BC Hydro.
Any person using these Standards thereby agrees to indemnify BC Hydro, its
servants or agents, regardless of fault or cause from any injury, loss, damage or
claim arising or alleged to be arising from use of or reliance upon the Standards, in
whole or in part, except for those situations where the person directly uses the
Standards to provide services to BC Hydro.
R0 Page 5
Substation Design Guide
Class Description
20 Tele-control
21 Tone Equipment and Test Panels
22 Microwave
23 Control and Telemetry
24 Data Collection Platforms
25 Power Line Carriers
29 Power Supplies
30 Security
32 Emergency Plans
33 Fiber Optics
34 Wire line /Wireless Equipment
40 General P&C
41 P&C Test Equipment
42 P&C Relays
43 Protection
47 Control systems
48 Recorders
49 Meters
n.a. Electrical, Mechanical and Civil
R0 Page 6
Substation Design Guide
The equipment shall be subjected to transmission from each of the following output
frequencies:
.1 15 W in the 47-48 MHz band
.2 10 W in the 158-173 MHz band
.3 5 W in the 450-470 MHz band
.4 0.6 W, 832 MHz (cellular phone region)
For the test, the equipment enclosure (chassis) that acts to shield the solid state
portions of the equipment shall be in the normal in-service (closed) condition and
also in the open condition.
R0 Page 7
Substation Design Guide
When the cabinet door is open, the radio antenna shall be brought to within
300 mm of the exposed operating circuits. The radio transmitter shall be operated
both continuously and interrupted once per second. Each test shall be performed
with the radio antenna oriented in each of the X, Y, and Z planes with respect to the
exposed operating circuits.
6 DOCUMENTATION
6.1 General
The Contractor shall provide complete project documentation. Documentation includes all
details pertaining to the project undertaken and all information required to allow BCTC to
maintain complete and accurate records of the power system.
The following procedures detail the exchange of information and drawings between BCTC and
the Contractor.
• Information Management Process for BCTC Consultants
• Drawing Management Process for BCTC Consultants
The documentation required to be submitted for a project is detailed below.
R0 Page 8
Substation Design Guide
further details refer to the “Information Coordination for BCTC Contractors” available from
BCTC.
(a) Protective Relay settings,
(b) CT Saturation Curves,
(c) Equipment Tender/Equipment Contracts,
(d) Equipment Test Reports,
(e) Equipment Commissioning Reports,
(f) P&C Software Code and Device Configurations (e.g. PLC, HMI),
(g) Aspen Bases Case model,
(h) PSS/E Case model,
(i) Harmonic Study,
(j) Short Circuit Study,
(k) Transient Recovery Voltage Study,
(l) Insulation Coordination Study,
(m) Geotechnical reports,
(n) Environmental Assessments,
(o) Environmental Management Plans,
(p) Contract Specifications,
(q) Protection and Control Application,
(r) Telecommunication Application,
(s) RTU setting files,
(t) Electro-Magnetic Field (EMF) study,
(u) Spare parts and special tools,
(v) Hazardous material identification,
(w) Noise level study,
(x) Security study, and
(y) Spill contingency plan (including spill contingency drawing)
6.4 Drawings
Drawings will completely detail the design of the project and Issued As-Built are required to
reflect the final as-constructed state. Typical subjects for drawing types are listed below. (Refer
to BC Hydro Engineering Standards ES 10-A0020 for subject descriptions.)
(a) Civil and structural (typically subject 05)
(b) Electrical (typically subjects 05, 06, 16 and 60)
(c) Environmental (typically subjects 50 & 51)
(d) Mechanical (typically subjects 05 & 28)
(e) Planning (typically subject 06)
(f) Protection and Control drawings (typically subjects 05, 06, 16 and 27)
(g) Telecommunication (typically subjects 05 and 16).
All substation drawings are to be updated for a project. The objective is to have a concise,
accurate and easy to understand drawing set. When a project involves work that is covered by
existing drawings, the existing drawings must be updated to show the new work. The new work
should not be shown on new drawings unless drawing constraints prevent this. In this case,
consideration should be made to revising the drawing(s) in some way (e.g., change scale to
allow more to be shown, make into more than one drawing with approximately equal parts
shown on each drawing) to improve the presentation.
R0 Page 9
Substation Design Guide
Drawings are continually revised to show new work. An exception is station planning drawings
(i.e., P06), which only show the work for a single project. Planning drawings a revised for
changes for that project only.
To allow for ongoing substation operation, the contractor shall leave a complete set of As-Built
drawings at the substation once a construction project is complete. It is understood that Issued
As-Built drawings will not be available immediately, so this set of these drawings may be hand
marked to show the as-built changes. The expectation is that Issued as-built drawings will
follow in a reasonable time.
6.5 Manuals
The following manuals are to be provided for all projects.
• Major Equipment
• Heating, Ventilation and Air Conditioning
• Fire detection and protection.
• General substation operation and maintenance
The original copy of all manuals is to be numbered like a drawing and stored in the BC Hydro
drawing vault.
7 INTERFACING
Substations interface with areas such as roadways, area drainage, communications systems,
and electric power lines. Sufficient lead time has to be allowed to coordinate activities with
public agencies for roadway access and with communications agencies for communications
facilities.
When locating a new substation, coordinate the location, design and construction with other
utilities operating in the vicinity. Other utilities include but are not limited to:
(a) Telecommunications,
(b) Cable television,
(c) Water,
(d) Sewer,
(e) Natural gas, and
(f) Radio and television stations.
R0 Page 10
Substation Design Guide
Above ground cable supports, bus connection points and isolating links are also to be
provided. The isolating link shall have bolted type connections with ground studs at
each that allow the link to be removed with safety grounds attached to the ground
studs.
BC Hydro Field Operations is responsible for installing and terminating feeder cables in
the substation.
8 PROPERTIES
8.1 Acquisition
All substation property matters are handled through BC Hydro Properties. Contact the BCTC
project manager for more information.
8.2 Permits
It is the Contractor’s responsibility to obtain all permits required to complete a project. In
general, BC Hydro and BCTC are exempt from electrical permits when the design is signed by
a Professional Engineer.
9 SUBSTATION PLANNING
Substation planning will consider the location, size, voltage, sources, loads, short term function
and ultimate function of a substation. If adequate planning is not done, a substation may
require unnecessary and costly modification in the future.
R0 Page 11
Substation Design Guide
The planning basis will follow N-1 scenarios. That is, the substation will continue to operate and
fully serve its design function when one component fails. If auxiliary systems are used for
equipment operation, then these systems shall also have the same redundancy. For example,
an indoor substation with glycol cooling for its transformers shall have independent systems
and controls so that a common failure does not result an N-2 or worse scenario.
The planning will allow for the installation, operation, maintenance and removal of all
equipment without interruption of service to other nearby equipment. An example of this would
the addition of isolating disconnect switches on either side of a circuit breaker.
Planning should be based on an ultimate configuration or plan. Work shall not be done on a
substation project that jeopardizes the ultimate configuration without BCTC approval.
Circuit breakers used to switch 500 kV transmission lines and reactive equipment at 230 kV
and higher will use point on wave controllers.
All equipment shall have a full load rating suitable for the full overload rating of the transformer.
For winter peaking stations, the transformer overload rating is normally 133% of the fully forced
rating.
Station transformers used to supply 12 kV distribution systems shall have dual voltage (re-
connectable) secondary windings rated for both 12 kV and 25 kV operation. The 25 kV
provision will eliminate the need to replace the transformer if voltage conversion occurs in the
future.
BCTC’s transformer spares strategy requires that all substation transformers have a spare
available to establish N-1 within 3 weeks after the failure of a transformer. Restoration to N-1
can be established by offloading or transfer of all load to another source. The restoration to N-1
can also be established by permanent installation of a spare. The purchase of a spare shall be
part of a capital upgrade project and will occur when this requirement is not met through normal
station operation or load transfer capability.
11 EQUIPMENT
Substation projects will use equipment that is accepted by BCTC when available. The BCTC
accepted equipment list is given in Appendix D. This list may change and it is the Contractor’s
responsibility to obtain the latest BCTC accepted equipment list. All equipment purchases on
the BCTC accepted list must be processed through BCTC Procurement.
Equipment with Catalogue Ids (Cat Id) are to only used for emergency purposes except with
the permission of BCTC.
11.1 General
All equipment specifications are to be reviewed and accepted by BCTC.
Oil filled equipment shall have containment in accordance with Section 12.5.
R0 Page 12
Substation Design Guide
All hazardous areas of the equipment must have manufacturer supplied barriers to prevent
safety incidents during normal operation. For example, electrical energized parts must be
suitably insulated or isolated and moving parts must have a barrier to prevent injury.
Equipment manuals shall be filed in accordance with Section 6.5.
When non-standard equipment is used, BCTC shall be consulted to determine if spare
equipment should be procured for the project.
11.2 Transformers
Transformers of various MVA ratings with primary voltages of 230, 130 and 64 kV are a part of
BCTC Major Equipment Blanket Contracts. Transformers rated 500 kV are not a part of BCTC
Major Equipment Blanket Contracts and, therefore must be tendered. Specifications for this
equipment must be in accordance with the latest revision of BCTC Standard Technical
Specification E-844.
R0 Page 13
Substation Design Guide
R0 Page 14
Substation Design Guide
12 CIVIL DESIGN
12.1 Site Selection
All sites should be fully investigated and selected to meet the goals of supplying and
maintaining a safe, efficient, and reliable electric system. All government and municipal
regulations shall be complied with and public safety and other concerns shall be considered
through public consultation. Site shall be selected based on safety, environmental, electrical,
topography, soil conditions, and socio-economical criteria. See BC Hydro Engineering
Standards ES 21 Section B for guidance.
Boundaries around substations must be cleared to meet station protection and public safety
requirements taking into consideration
(a) Danger trees
(b) lie of land
(c) allowance for access roads
(d) allowance for ground grid
(e) need to conceal station
(f) environmental concerns
(g) other site specific requirements
12.3 Seismic
Stations must be designed and constructed such that they meet the performance requirements
of BCTC Performance Criteria. In general all substation structures and engineered sub-grades
R0 Page 15
Substation Design Guide
shall be designed to resist the appropriate site specific seismic forces such that the substation
can meet the Level 1 Facility, 72 hour return to service standard after the Design Earthquake
BC Hydro Engineering Standards ES 44 Section E – Seismic Design Practices and ES 21
Section S – Seismic Hazard Abatement Details provide additional information on specific
requirements. It should be noted that BC Hydro standards may not be current and it is the
Contractor’s responsibility to use appropriate industry or national standards for design and
construction such as IEEE Std. 693 - Recommended Practices for Design of Substations or the
National Building Code of Canada 2005.
The designer of equipment layout for new stations shall call in the Seismic Specialist as
needed for equipment and rigid bus proximity to avoid secondary damage from debris falling
onto adjacent equipment.
R0 Page 16
Substation Design Guide
12.7 Fence
All stations must be secured against access by unauthorized persons. The Contractor shall
design a Substation Perimeter Barrier (Fence) that reduces the risk of unauthorized entry and
does not invite attempts to penetrate the security.
All new sites shall be assessed to achieve secure fence protection. Consideration shall be
given to the following factors:
(a) site topography
(b) annual precipitation (snow)
(c) geographic location – proximity to residential areas, schools and playgrounds
(d) potential for vandalism to cause widespread system impact
(e) manned or unmanned sites
(f) frequency of site visits by maintenance personnel
(g) local conditions
12.8 Footings
Footings must be designed and constructed to carry the applied design loads from the
equipment they support to the foundation level such that the support does not fail (i.e. slide or
overturn). Footings shall be designed to meet the general requirements of the Canadian
Foundation Engineering Manual. BC Hydro Engineering Standards ES 21 provides guidelines
on standard footing designs for use in BCTC substations. The following sections of ES 21
detail footing designs that may be used to support equipment after site specific conditions are
checked:
(a) Section H – Footings, General Notes and Design Criteria,
(b) Section K – 25 kV Footings,
(c) Section L – 69 kV Footings,
(d) Section M – 138 kV Footings,
(e) Section N – 230 kV Footings, and
(f) Section Q – 500 kV Footings (in progress).
For substation switchyards with poor or fine grained soils, consideration shall be given to the
use of augered concrete foundations or spread footings with frost protection and adequate sub-
base drainage.
R0 Page 17
Substation Design Guide
13 ELECTRICAL DESIGN
13.1 Clearances
The layout must consider the electrical and physical clearances required to ensure personnel
safety, proper system operation and adequate equipment and vehicle access for construction,
operation and maintenance. Minimum electrical clearances shall follow BC Hydro Engineering
Standard ES 44-C0051 (outdoor) and ES 44-C0052 (indoor). Stations shall be designed to
allow for the operation and maintenance with Column 4 Limits of Approach as defined in
BC Hydro Safety Practice Regulations, Table 401.
13.2 Switchyard
Criteria for outdoor substations are found in BC Hydro Engineering Standard ES 44-C0020.
Equipment and bus work must be arranged to satisfy the equipment and transmission and
distribution connections defined by the station one line diagram.
Station design and construction must incorporate design features that reduce animal induced
outages. To achieve effective animal deterrent, substations may incorporate increased
clearances between electrical components, increased insulation using insulating covers, use
barriers to deny animal access to energized parts and install perching and climbing deterrent
devices at susceptible locations, Animal and bird protection for a station shall be in accordance
R0 Page 18
Substation Design Guide
13.6 Lighting
All lighting levels shall comply with WorksafeBC regulations as a minimum requirement.
Switchyard lighting shall provide illumination levels described in BC Hydro Engineering
Standard ES 44-N0016. Outdoor switchyard lighting will normally be turned off and are
manually switched on to provide general lighting only when required at night. Outdoor lighting
controls will be interlocked with both daylight photocells and the unoccupied status of the
control room.
R0 Page 19
Substation Design Guide
Indoor lighting shall be supplied by a minimum of two circuits to ensure some lighting is
available if one circuit trips. Indoor lighting should have an acceptable level of redundancy so
that if a single bulb burns out workers will still have sufficient light to replace the bulb.
R0 Page 20
Substation Design Guide
Panels should be supplied with main circuit breakers for protection and isolation purposes. All
circuit positions shall be filled in new panels with a range of circuit breakers expected to be
used in the future.
Near transformers (or other large oil filled equipment), a station service power connection
suitable for running oil processing plant shall be provided. For power transformers less than or
equal to 75 MVA, a 60 A, 208/120 V ac, 4 wire plug shall be provided. For power transformers
greater than 100 MVA, a 100 A, 208/120 V ac, 4 wire supply will be terminated on junction bars
in a cabinet not far from a suitable location for the treatment equipment.
Plugs should not be located where they may be confused with other equipment in the dark.
(e.g., keyholes)
R0 Page 21
Substation Design Guide
Above grade cables are to be adequately protected from damage, vandalism and sunlight.
Conduit and cableways emerging from the grade should be designed to be immune to frost
heave.
Control panels are to be clearly labelled. Test blocks should be labelled both on the front and
on the back of the panel. Control cables are labelled with engraved and stamped tags available
from MMBU that provides visible contrast between lettering and rest of the tag. In addition, tags
should be attached to control cables securely to prevent slippage along the cables.
The installation of cables should allow for future re-terminations by providing extra length at
both ends. For the field end, this should be provided in the cable trench or near the equipment
for direct buried cables. For the building end, this should be provided through a longer, by tidy,
routing below the floor.
13.11 Grounding
13.11.1 General
A substation is grounded with a ground mat and ground rods to meet the requirements of
IEEE Std. 80.
All metal surfaces, if can be contact by personnel are bonded to ground. Some structures
that cannot be contacted are still a path for fault current (example: insulation supports in
ceiling). These are also bonded to ground.
Use of copper above grade is minimized to reduce attraction of theft. Copper weld
conductor is used for rises above grade and steel cable is used for fence grounding. See
BC Hydro Engineering Standards ES 44-G0211 and G0230 for typical details.
Fence gates shall not swing outwards unless the ground grid is extended beyond the
extent of the swinging gate.
See BC Hydro Engineering Standard ES 44-G0205 for details of typical outdoor ground
details.
R0 Page 22
Substation Design Guide
using formulas in IEEE Std. 80 for a maximum conductor temperature of 450°C for
compression or exothermic connections.
R0 Page 23
Substation Design Guide
14 CONTROL BUILDINGS
14.1 General
Adequate space shall be provided in the control room for the following:
• one desk (minimum surface 2.5 m x 1.0 m),
• one office (roller) chair,
• one-four drawer filing cabinet,
• one phone,
• fire extinguishers as required,
• wall space (1.0 m x 0.6 m) for a full size single line diagram to be posted,
• wall space for storage of safety grounds as required for maintenance, and
• storage space for spare parts recommended to be kept at site.
Control room illumination shall be adequate for office work, with consideration to have
illumination of both sides of panels. Careful attention shall be given to provide non-obstructive
light for work on the back of protection and control panels. Refer to BC Hydro Engineering
Standards ES 44-N0020 and N0021.
The control building shall have at least one large door that will accommodate the largest panels
without disassembly. The main entrance door shall have a luminaire mounted above the door
on the outside. The luminaire shall have a motion and light sensor.
Stairs and access to the control building will accommodate the test equipment to be carried into
the room. The main entrance of the control building will have space for service vehicle parking
and consideration for transport of test equipment into the building.
When possible, the main entrance door shall open inwards (so it can be opened in snowy
conditions). Entrances shall have provision to shield personnel from falling snow or ice from the
roof. Inside the building, a key switch will be located to enable or disable the security system.
Operation of the door switch will indicate the OCCUPIED / UNOCCUPIED status of the control
room. That status will be reported to the control centre as an alarm and also turn on the
building lighting and heating and enable the outdoor switchyard lighting. When staff are
leaving, the alarm system is enabled, which will also turn off all control room lights except for a
small light inside the building and above the doorway, and reduce the building temperature to
the value of the setback thermostat, nominally 5 ºC.
A raised floor system and bottom entry of cables into protection and control panels is preferred.
R0 Page 24
Substation Design Guide
Panels, lights and auxiliary equipment are secured as per IEEEE Std. 693 to withstand BCTC
seismic criteria.
Working space for protection and control panels shall be provided in accordance with Section
15.2. Working space for other panels shall be in accordance with the CEC.
Doors are sealed against draft and moisture. In high snow areas, entrances shall be designed
to protect personnel from falling snow or ice from the roof or other nearby structure (e.g.,
communication tower). This may be accomplished by door location, roof slope, overhang or
covered entrance way.
A minimum of two separate circuits shall be allowed for wall and outdoor receptacles. Refer to
BC Hydro Engineering Standard ES 44-N0020, Section 14 for details.
Emergency lighting shall be provided in the control building. Refer to BC Hydro Engineering
Standard ES 44-N0021, Section 4 for details.
Consult BCTC Project Manager for washroom requirements.
R0 Page 25
Substation Design Guide
Protection and control circuit supplies must provide sufficient independence so the loss of one
supply does not impact the station’s ability to serve load. Example, control and power circuits
for transformer cooling pumps must all be independent to allow any of them to be out of service
without affecting other uints. Also see Section 9.
16 TELECOMMUNICATION DESIGN
Telecommunication requirements will be in accordance with BC Hydro Engineering Standards
ES 46 Series.
R0 Page 26
Substation Design Guide
17 MECHANICAL DESIGN
17.1 Heating, Ventilation and Air Conditioning (HVAC)
BC Hydro Engineering Standards ES 44 Section C states the general criteria for ambient air
temperature in substations.
A HVAC system is installed in control and other substation buildings to ensure the equipment
inside operates within its design parameters.
Substation buildings will be designed to have temperature set points for OCCUPIED and
UNOCCUPIED conditions. The control of the set points is dependent on the status of the
building security system. Design of heating, ventilation, and air conditioning systems for
unmanned or manned substation control buildings, feeder buildings, and compressor buildings
should consider the following design factors:
(a) Building location, elevation and construction
(b) Building manned or unmanned
(c) Electrical equipment and lighting heat gains
(d) Battery location, type, capacities and maximum charge rate
(e) Building fabric insulation
(f) In the case of Compressor Buildings the type and number of compressors; heat
dissipation rate and anticipated hours of operation.
(g) Any other site specific requirements such as site boundary noise levels or atmospheric
pollution.
Refer to BC Hydro Engineering Standards ES 31 Section C for details.
The battery rooms will have independent temperature control to ensure a constant temperature
for maximum battery life. Ventilation will be provided in battery rooms as required to prevent
the accumulation of gases. Refer to Sections14 and 13.9 for more details.
Ventilation equipment will be shut off when the fire detection system is activated.
R0 Page 27
Substation Design Guide
The power supply to a battery room exhaust fan should be supplied by the station essential
services bus which is backed by emergency generator. This is to ensure exhaust fan
continuously operative.
The battery room exhaust fan may be a variable frequency drive (VFD) type or a 2-speed
control for energy conservation, such as low speed (50%) on floating charge and high speed
(100%) only for equalization charge.
Ambient temperatures should be maintained in accordance with manufacturer’s
recommendations for optimal performance and life. For Lead-Calcium batteries, the normal
range is 20 °C to 25 °C and for sealed type batteries it is 18 °C to 20 °C.
R0 Page 28
Substation Design Guide
18 CONSTRUCTION
18.1 Coordination
All construction work shall be planned and coordinated with BCTC System Operations and
BC Hydro Field Operations.
R0 Page 29
Substation Design Guide
Operators for manual and motor operated disconnect switches shall be placed above grade to
minimize ergonomic strain on workers. All outside cabinets shall be lockable, accepting a
padlock with a 10 mm (3/8 in) hoop.
Ramps or platforms are to be provided when equipment cabinets cannot be accessed from
ground level.
19.2 Training
The Contractor shall provide training to BCTC and its operating and maintenance staff. The
Contractor shall propose the outline of the training but consider the following topics.
(a) location and identification of major equipment components,
(b) demonstration of equipment maintenance techniques,
(c) demonstration of equipment operation, both locally and remotely,
(d) overview of the indicating instruments in panels,
(e) overview of the protective relay system,
(f) review of the equipment operation and manuals, and
(g) review of the substation operation and maintenance manuals.
R0 Page 30
Substation Design Guide
R0 Page A1
Substation Design Guide
1.0 PURPOSE
This Standard describes the BCTC procedure and system for recording and posting
Environmental Incidents as they occur. This procedure ensures timely communication and
reporting to senior management and to appropriate technical individuals that may be impacted
by the incident.
Incident reporting benefits all Business Groups within BCTC by:
• alerting managers so they can manage contacts and pressures (e.g. from
employees, agencies, communities or media) with timely and accurate information;
• meeting specific obligations and legal standards of care;
• providing a source of data that can be used to identify trends and to provide
justification for actions to correct the underlying problem and prevent future
incidents.
This Standard applies to all work, including work performed by contractors, and all events
which affect BCTC.
2.0 REPORTING REQUIREMENTS
All environmental incidents are required to be reported in the Environmental Incident Reporting
System.
This Standard specifies BCTC Environmental Incident Reporting requirements only. Additional
legal obligations to report certain spills to regulatory agencies are specified in Best
Management Practices (BMPs) General References – Reportable Spill Quantities
Releases of gases that are sudden and uncontrolled are considered spills and must be
reported internally. Controlled release of gases or release of gases through maintenance are
not considered incidents and are thus not reportable in the EIR system.
In the event of an emergency (e.g. flood, forest fire, extreme storm, earthquake or dam breach,
etc.) the reporting responsibilities governed by Emergency Preparedness Plans take
precedence.
3.0 DEFINITION
An Environmental Incident is one that has caused, or has the potential for causing, one or more
of the following:
• Adverse impact on the quality of air, land or water, wildlife, aquatic species or
species at risk;
• Exceedence of permit or external reporting requirement;
• Notification of external agencies due to emergency/beyond normal circumstances;
• Adverse publicity with respect to environment;
• Legal or regulatory action with respect to violation of statutes or environmental
damage; or
• Alteration of, or damage to, heritage or archaeological resources.
At the request of the Audit and Risk Management Committee of the Board, criteria were
established for defining environmental incidents as severe.
R0 Page A2
Substation Design Guide
R0 Page A3
Substation Design Guide
fined unless they can prove they were duly diligent in trying to prevent the incident. The
associated penalties are significant, and may apply not only to corporations but also to their
directors, officers, managers and persons directly involved with or causing environmental
damage. The Environmental Incident Reporting procedure assists in demonstrating due
diligence where strict liability laws apply. Some examples of applicable legislation include:
FEDERAL
• Fisheries Act
• Canadian Environmental Protection Act
• Species at Risk Act
• Migratory Birds Convention Act
PROVINCIAL
• Pesticide Control Act
• Waste Management Act
• Water Act
• Wildlife Act
• Heritage Act
Other acts also apply, and statutes are revised and new statutes are added from time to time.
For summary information on the environmental acts most relevant to BCTC, visit or print the
Legislation section of the Sustainability Intranet.
5.0 PROCEDURE
NEW ENVIRONMENTAL INCIDENT REPORTS
• Environmental Incident Reports (EIR) are to be prepared as soon as possible. The
target timeline for reporting is within 24 hours of the occurrence. Some incidents
may have a higher degree of sensitivity, severity, or critical circumstances. In those
cases, senior management must be notified immediately.
• The Environmental Incident Report is to be prepared on a form available from BCTC
and filed as per instructions on the form.
• The responsible supervisor or manager at the site of the incident (with input from
any subsequent operations or environmental staff that become involved) shall
prepare the EIR and notify the appropriate personnel based on the severity of the
incident. A preset list of people including vice-presidents, managers, environmental
specialists, Legal, and Corporate communications and environmental staff is
available within the EIR system.
CRITICAL NOTIFICATION
• On certain occasions, an incident may be elevated in stature by site specific
circumstances, the severity of its environmental impact, the public, the media, or
government representatives. When this happens, immediate notification of senior
management must be initiated.
R0 Page A4
Substation Design Guide
• The target for this type of notification is within one hour of the incident, or its
escalation to severe status.
• Notification may be made via Telephone, Fax or email, but preference is for
personal contact.
EIR UPDATES
• The responsible supervisor or manager at the site of the incident (with input from
any subsequent operations or environmental staff that become involved) shall
maintain a record of incident updates. This person is also responsible for exercising
discretion and forwarding the significant updates on the incident to appropriate
personnel. A preset list of people including vice-presidents, managers,
environmental specialists, Legal, Corporate communications and environmental
staff is available within the EIR system
EIR CLOSURE
• All EIRs will require closure. The closure fields of the EIR reports must be
completed by the responsible manager. Before closure, the Regional
Environmental Coordinator (REC), Environmental & Social Issues Manager (ESIM),
or other applicable environmental specialist must verify that the environmental
response is appropriate and complete (i.e. to review cleanup, waste disposal,
lessons learned, accuracy of report).
• An EIR should be closed only after completing all of the following actions:
1. verification that physical aspects of the incident have been remediated,
2. verification that any associated wastes have been disposed of legally,
3. lessons learned (if any) have been captured and transmitted,
4. root cause analysis and corrective action plan (if applicable) have been
identified and initiated, and
5. report has been reviewed for consistency and completeness (e.g. lab results,
regulators notified)
• The closed EIR must be forwarded to the preset list (including Environmental
Managers, Environmental Specialists and Legal) within the EIR and the applicable
Area Manager and environmental coordinator (i.e. REC or ESIM). Pending the
nature of the incident and the involvement of other staff during its resolution; the
notification of closure should also be communicated to other applicable staff. The
latter is left to the discretion of the originator and subsequently Area Manager and /
or environmental coordinator.
R0 Page A5
Substation Design Guide
Responsible Supervisor or
NEW EIR Manager at site of incident
Responsible Supervisor or
EIR UPDATE(S) Manager at site of incident
R0 Page A6
Substation Design Guide
R0 Page B1
Substation Design Guide
GENERAL REFERENCES
Reportable Spill Quantities
The table shows the quantities of spilled substances that are reportable under the BC Spill
Reporting Regulation, the federal Transport of Dangerous Goods (TDG) Regulations and the
federal PCB Regulations. The quantities vary according to the type of substance and in some
cases whether the spill occurs during transport or not.
Note:
Reportable Quantity*
Substance TDG
Examples
Spilled Class Spill NOT During Spill During Transport§
Transport†
Substances Classified under TDG Regulations
Explosive Class 1 Any dangerous release, Any dangerous release, or
or 50 kg 50 kg,
or, for Class 1.1, 1.2, 1.3
or 1.5, as specified in the
Table in section 8.1 of the
TDG Regulations
Natural gas Class 2.1 10 kg when the release is Any dangerous release, or
uncontrolled and sudden any release for more than
as a result of a failure of 10 min, or
a pipeline or fitting 10 kg when the release is
operated above 100 psi uncontrolled and sudden
as a result of a failure of a
pipeline or fitting
operated above 100 psi
Hydrogen Class 2.1 10 kg when the release is Any dangerous release,
uncontrolled and sudden or
any release for more
Flammable gas, Class 2.1 Propane 10 kg than 10 min, or
other than any release more than
hydrogen or 10 kg
natural gas
Compressed air, Class 2.2 Reporting not required
nitrogen
CO2 Class 2.2 10 kg when the release is
R0 Page B2
Substation Design Guide
Reportable Quantity*
Substance TDG
Examples
Spilled Class Spill NOT During Spill During Transport§
Transport†
uncontrolled and sudden
SF6 Class 2.2 10 kg when the release is
uncontrolled and sudden;
detailed annual report for
other losses
Non-flammable, Class 2.2 Halon 1301, 10 kg
non-toxic gas other refrigerant gases
than compressed other than R140
air, nitrogen, CO2, (same as
or SF6 trichloroethane)
Toxic or corrosive Class 2.3 Chlorine 5 kg Any dangerous release,
gas or
any release for more
than 10 min, or
any release more than
5 kg
Flammable liquid Class 3 Varsol, diesel, 100 L 100 L
gasoline
Solid that is Class 4 Waste sorbent 25 kg 25 kg
flammable or containing oils or
spontaneously fuels
combustible, or
that emits
flammable gases
on contact with
water
Oxidizer Class 5.1 Hydrogen peroxide, 50 kg or 50 L 50 kg or 50 L
many nitrates
Organic peroxide Class 5.2 Some fiberglass 1 kg or 1 L 1 kg or 1 L
catalysts
Toxic liquid or solid Class 6.1 Tetrachloromethane 1 kg 1 kg
(same as carbon
tetrachloride)
Tetrachloroethylene 5 kg or 5 L 5 kg or 5 L
(same as
perchloroethylene
or perc),
trichloroethane
R0 Page B3
Substation Design Guide
Reportable Quantity*
Substance TDG
Examples
Spilled Class Spill NOT During Spill During Transport§
Transport†
(same as R140)
Infectious Class 6.2 Any dangerous release, All
substance or 1 kg, or 1 L
Radioactive Class 7 Any dangerous release Any dangerous release
substance (an emission level (an emission level
greater than specified in greater than specified in
section 20 of the section 20 of the
Packaging and Transport Packaging and Transport
of Nuclear Substances of Nuclear Substances
Regulations) Regulations)
Corrosive liquid or Class 8 Battery fluid, 5 kg or 5 L 5 kg or 5 L
solid mercury
Friable asbestos Class 9 Asbestos that 50 kg 25 kg or 25 L
releases fibres or
crumbles easily
Other Class 9 25 kg or 25 L 25 kg or 25 L
miscellaneous
dangerous goods
Materials Containing PCBs
Solids containing Class 9 Any quantity Any quantity
50 ppm or more
PCBs
Oil or liquids, Any quantity if released Any quantity
containing 2 ppm from equipment not in
or more PCBs use or from stored
containers
1 g of pure PCBs if
released from equipment
in-use.
Click for table
Other Substances and Wastes
Oil (non PCB) and — Class 1 or 2 and 100 L 100 L
waste oil waste insulating oil
less than 2 ppm
PCBs, new and
waste hydraulic and
R0 Page B4
Substation Design Guide
Reportable Quantity*
Substance TDG
Examples
Spilled Class Spill NOT During Spill During Transport§
Transport†
lube oil
Waste containing — Wastes containing Any dangerous release, Any dangerous release,
dioxin more than 100 ppb or 1 kg, or 1 L or 1 kg, or 1 L
dioxin toxicity
equivalents (TEQ)
Leachable toxic — Waste abrasive 25 kg or 25 L 25 kg or 25 L
waste blasting material,
antifreeze or
coolant
Waste containing — Creosote or coal tar 5 kg or 5 L 5 kg or 5 L
polycyclic aromatic contaminated soil
hydrocarbons containing more
(PAH) than 100 ppm PAH
TEQ
Waste containing a — Unrinsed empty 5 kg or 5 L 5 kg or 5 L
pest control containers for pest
product control products,
soil or sorbent
contaminated with
pest control
products
Waste containing — Wastes containing 50 kg or 50 L 50 kg or 50 L
tetrachloroethylene more than 500 ppm
tetrachloroethylene
(same as
perchloroethylene
or perc)
Biomedical waste — Any dangerous release, Any dangerous release,
or 1 kg, or 1 L or 1 kg, or 1 L
Hazardous waste — 25 kg or 25 L 25 kg or 25 L
not covered
elsewhere
Other substance — Wash water 200 kg or 200 L 200 kg or 200 L
not covered
elsewhere that can
cause pollution
* Where the quantity is shown as kilograms or litres, the quantity in kilograms applies for solids
and the quantity in litres applies for liquids.
R0 Page B5
Substation Design Guide
§ The least of quantities under the TDG Regulations, PCB Regulations or Spill Reporting
Regulation.
R0 Page B6
Substation Design Guide
R0 Page C1
Substation Design Guide
R0 Page C2
Substation Design Guide
R0 Page C3
Substation Design Guide
R0 Page C4
Substation Design Guide
R0 Page C5
Substation Design Guide
R0 Page C6
Substation Design Guide
R0 Page D1
Substation Design Guide
R0 Page D2
Substation Design Guide
R0 Page D3
Substation Design Guide
R0 Page D4
Substation Design Guide
R0 Page D5
Substation Design Guide
R0 Page E1
Substation Design Guide
Good design will minimize safety hazards, and provide barriers to hazards that cannot be
designed out. This increases safety for the public and employees, and the quality of work
delivered.
Types of safety hazards include: gravity, electricity, mechanical, kinetic, chemical, pressure, and
human factors (e.g., ergonomics). The treatment of safety hazards in order of preference
include: elimination, minimizing to safe levels, physical barriers, protective equipment, barriers,
procedures and training.
All projects require a Safety Review which involves the systematic identification of hazards and
failure modes and elimination or reduction of safety risks to workers and the public. Design
alternatives are selected based on regulatory requirements and safety criteria, and
consideration of safety is embedded into the design of the asset over its full life cycle. The
Consultant must consider not only the intended purpose of the asset being designed, but also
how that asset will be constructed or installed, how testing and commissioning will be
performed, how operation and maintenance will be performed, and how the asset will be dealt
with at end-of-life.
R0 Page E2
Substation Design Guide
Transmission Asset (TA) projects. These differences will be outlined throughout the procedure
laid out in this Appendix. For projects that involve both SDA and TA work, the Safety Review
shall be carried out independently for each portion of the project.
1. Identify Hazards
The Contractor considers and documents all hazards, as well as their source, using
scenarios (a combination of events and/or conditions that could occur). The Contractor
consults with as appropriate, construction, operating and maintenance personnel (including
trades’ staff) who know the facility or activity best, to assess the operation of the facility or
activity and its proposed modifications or additions.
The Contractor may use both proactive and reactive hazard identification techniques:
Fundamental methods • Structured brainstorming (eg using the Delphi technique)
• What If Analysis
• Hazard and Operability Studies (HAZOP)
• Failure Mode and Effect Analysis (FMEA),
• Modeling
• SWOT
• process mapping.
Comparative methods • Checklists
• hazard indices
• reviews of historical or incident data
• physical audits and inspections
Deductive or inductive • Fault Tree Analysis (FTA)
reasoning techniques • Event Tree Analysis (ETA)
• Root Cause Analysis (RCA)
In defining a particular hazard, the Contractor states the cause and effect using
words/phrases like “causes”, “leads to”, “prevents”, hinders”, etc.
2. Analyze Hazards
The Contractor analyzes hazards starting at an early stage in the design of the project to
avoid precluding them from further analysis and leaving personnel exposed. Revising the
design to address a hazard during the construction or operational phase of the project will
incur additional cost. When designing additions or extensions to existing facilities as many
hazards as possible should be identified, regardless of whether they are currently being
treated or controlled, because it is important to understand why certain hazard treatments
are in place, and whether they are effective.
3. Evaluate Hazards
a. For SDA
Risk levels are determined based on BC Hydro’s Corporate Risk Matrix (copy provided in
Hazard Log template). The Contractor groups or ranks hazards identified in the identification
and analysis phases in consideration of BCTC’s policy and tolerance to them:
Unacceptable (Zero tolerance)
• Solution obvious and easily implemented – do it.
• Solution not obvious and requires engineering analysis – eliminated through design.
R0 Page E3
Substation Design Guide
Acceptable
• With treatment (design, safety devices, signs, controls, personal protective
equipment (PPE), etc.).
Inconsequential
• Not worth treating (but may be monitored).
b. For TA
Risks levels are determined based on a subjective evaluation.
4. Treat Hazards
After evaluating the identified hazards, the Contractor considers the treatment options,
bearing in mind their strengths and limitations.
Eliminating hazards in the design stage of a project is the most effective way to improve
worker safety, rather than reducing hazards or providing protective equipment. Hazard
treatment with a high initial cost (e.g. an engineering solution) can be more cost effective in
the long term than one with a low initial cost that needs high levels of effort or ongoing
maintenance (e.g. the development of procedures with associated training, supervision and
enforcement).
If the hazard cannot be eliminated, the Contractor reduces it to a level as low as reasonably
practical (ALARP). The hierarchy of hazard treatment follows.
The Contractor’s Project Manager ensures that the project’s Communication Plan
addresses how stakeholders will provide input to hazard identification and assessment and
R0 Page E4
Substation Design Guide
how they will be addressed. It must also provide a mechanism for communicating senior
management’s tolerance for acceptance of certain hazards to the Contractor.
b. For TA
Hazard identification, assessment and treatment information shall be documented and
maintained in a Safety Treatment Plan. A Safety Treatment Plan template is provided and is
to be used unchanged.
Hazard Examples
Table E.1 provides a sample of common safety hazards in a substation and possible
treatments. This table is not complete and it’s the Contractor’s responsibility to ensure all
hazards are dealt with appropriately.
R0 Page E5
Substation Design Guide
R0 Page E6
Substation Design Guide
R0 Page E7