F. Project Finance Specialist Module
F. Project Finance Specialist Module
F. Project Finance Specialist Module
2
Learning objectives
4
Overview of what will be covered
5
1
What is Project Finance?
7
1
Who are the relevant players: Sponsors
Sponsors Description
Industrial sponsors with PF These firms want to use PF to extend their value chain activities (upstream or
linked to core business downstream), but want to minimize risk
8
1
What is Project Finance?
• The project company is legally and financially independent from the sponsors
• Debtors have very limited or no recourse to the sponsors in the case of cash
flow shortfalls etc.
• Project risks are allocated equitably among all parties involved (different risk
profiles than usually for debt vs. equity)
• Cash flows generated from the project must be sufficient to cover operating
expense AND debt service. Only after those payments funds flow to sponsors.
• Collateral to lenders is often the asset created in the project
9
1
A typical contract structure of a PF deal
Legend:
• FSA (Fuel Supply Agreement)
• RMSA (Raw Material Supply Agreements)
• O&MA (Operations and Maintenance Agreement)
• TKCC is Turnkey Construction Contract (build the plant)
11
Overview of what will be covered
12
2 NOT EXHAUSTIVE
Differences between PF and normal financing
Cost of Capital
Normally, the cost of capital for a new project depends on existing investment
projects and how they are financed
requity = cost of equity
rdebt = cost of debt
𝑊𝐴𝐶𝐶 = 𝑟𝑒𝑞𝑢𝑖𝑡𝑦 ∙ + 𝑟𝑑𝑒𝑏𝑡 ∙ ∙ (1 − 𝑇𝐶 ) V = E + D = total market value of the firm’s financing (equity and debt)
E/V = percentage of financing that is equity
𝑉 𝑉 D/V = percentage of financing that is debt
Tc = corporate tax rate
Problems arise:
1. How sound is the project? 1. If the new project is large compared to firm size
2. How sound is the company 2. If risk in the new project is substantially higher than in the
realizing a project? firm average
3. If there is a strong link to existing firm activities (lack of
diversification)
14
2A
Cost of Capital
15
2A
Cost of Capital
16
2B
If the three issues covered in page 14 come together, a special complication arises:
The risk underlying the portfolio (σA+B) of the two projects is more complicated. The risk
depends on the correlation between the two projects (ρAB) and the wA and wB are the
weights (relative size of the projects e.g. 20% and 80%)
What is the risk on the portfolio (project A has a value of 1,000, project B a value of 4,000),
the risk of A is 5% and the risk of B is 20%, and correlation is zero?
17
2B
If the new project is heavily related to existing firm activities. Risk increases as correlation increases
• Return rises from 10% to 18% in all cases.
• Risk, however, rises in all cases (from 5%), depending on correlation to 15% to 17%.
If the increase in risk leads to an increase in average cost of capital greater than the increase in ROI, the project
reduces firm value.
• That is (one reason) why projects get financed off balance sheet
*does not necessarily mean this is the best case overall for every investor
19
2C
22
3
23
3 NOT EXHAUSTIVE
Common risks in complex projects
24
3 NOT EXHAUSTIVE
Common risks in complex projects
Underestimation of project related features such as costs, delays, contingencies and changes in quality,
price, project specifications, designs, exchange rates, and external environmental factors
Demand prediction failures due to methodology weaknesses, poor databases, unexpected changes, and
the effect of appraisal bias
Complexity
leads to Conflict of interests
Despite all of these risks, it is unlikely that a project will be cancelled. Why?
Sunk Deeper into a highly visible project, partners have invested more money and time
eventually reaching a point of no return. The risk of being viewed as unsuccessful
and wasteful, puts at risk credibility and positions of decision makers. They then
cost escalate their commitment to avoid criticism or loss of reputation.
Consider the following situation:
effect When 85% of your project for a radar-blank plane is completed to be $15 million,
another firm begins marketing a plane which is much faster and far more
economical than the plane your company is building. The question is: should you
invest the last 15% of the research funds to finish your radar-blank plane?’’
Trained Training ensures new technology is used effectively and reduces resistance to change.
workforce Managers and employees should possess the skills and knowledge to use the necessary
technology for a complex project.
Clear goals Managers can avoid disagreements that might distract from the already complex project.
Management should allocate time to clarification of goals and interpretations and
revelation of hidden agendas using transparent information flows.
Clear contracts Contracts should clearly define goals, rights and obligations for all partners and sponsors.
They can introduce backup plans for critical elements in the supply chain
Transparency Decrease the risk of overestimating manager competence and minimizing project
complexity by using external checks to maintain transparency. Greater transparency,
independent project appraisals, and scrutiny can help overcome the “illusion of control”.
Pay attention to the soft criteria, such as partner and people selection. Detailed knowledge of potential partner’s
Collaboration management culture, strong relationships, effective communication, trust and confidence, cross-cultural
communication, evaluation and monitoring of the relationship quality, and creating a cooperative environment are
necessary to ensure success.
Maintaining lasting mutual interests can contribute to success. Collaborations based on gain-sharing and risk-
Structure sharing. This can mean creating a specific project structure to achieve this - ‘‘sink or swim together’’.
Prior Prior cooperative experience between partners and the reputation of the companies before the partnership are
key determinants of relationship quality.
experience
Balance control and commitment. Too much control increases the possibility of self-serving behavior and distrust,
Balance while lack of commitment can make contributions unforthcoming.
Start out with a viable project idea and thoroughly shape projects during the early stages since most projects have
Shape early little flexibility after start. Investments in the early stages of the project can help alleviate problems and improve
quality. Therefore, cost reduction is secured and better outcomes are achieved
32
4A
Risk identification Risk analysis Risk transfer and allocation to actors Residual risk management
• What are the risks? • How high are the risks? suited ensure coverage • What to do if additional risk or uncoverable
• How can risks be collateralized / managed? risks materialize?
Bounded rationality (limitations to individual decision making), makes PF contracts difficult. There need
to be for something a to solve residual issues
33
4A
Risk Contamination
Problems:
• A high risk project can potentially drag a healthy corporation into distress. Short of actual failure, the
risky project can increase cash flow volatility and reduce firm value. Conversely, a failing corporation can
drag a healthy project along with it.
Structural Solutions:
• Through project financing, sponsors can share project risk with other sponsors. Pooling of capital
reduces each provider’s distress cost due to the relatively smaller size of the investment and therefore
the overall distress costs are reduced. This is an illustration of how structuring can enhance overall firm
value.
• Project financed investment exposes the corporation to losses only to the extent of its equity
commitment, thereby reducing its distress costs.
• Co-insurance benefits are negative (increase in risk) when sponsor and project cash flows are strongly
positively correlated. Separate incorporation eliminates increase in risk.
1. Risk retention
• Corporate finance: if the project is on-balance-sheet, and does not perform, cashflows from other
projects can be used to compensate the shortfalls
• Project finance: only one source of revenue
35
4B
Legend:
EPC: Engineering, Procurement, and
Construction
O&M: Operations and Maintenance
Engineering, Procurement, and Construction (EPC) agreements transfers construction risk to the constructing entity
Constructor guarantees completion date, cost of the works, and plant performance
Additional risk (like interest rate or exchange rate) is Penalties for non-delivery of the constructor or
covered by specialized entities subcontractors are less than project value
37
4B
Legend:
EPC: Engineering, Procurement, and
Construction
O&M: Operations and Maintenance
Operations and Maintenance (O&M) agreements allocate operational risk to the contractor
in charge of running a facility
• Fixed price contract: the operator assumes the risk of fluctuating operating cost
• Pass-through contract: the SPV pays performance bonuses to the operator depending on plant
efficiency
42
5
45
6
Key Issues:
• How to assess the project risk and allocation of risks.
• How can project the project be structured to best manage risk?
• Project finance involves many different parties, each balancing their own
interests
• Project finance can protect company’s assets, even if the project is not
successful
• Project finance allows for higher debt levels
• Project finance can be used to manage complex projects
• There is a strategy to manage almost every kind of risk…
• Contamination risk can be avoidable by using project finance
• Project finance requires extensive contracting and lots of communication
51
Overview of what will be covered
52
AES case study
53
General question structure
The past: What does the firm do and how did we get to the problem?
The suggestion: How does the case suggest to solve the problem?
The evaluation: What does the suggestion imply, particularly regarding the past?
Where would we be if we had followed the suggestion in the past?
The analysis: What do we get if we apply the suggestion to an element in the case
Take aways: Key learnings and relate the case back to other class materials
54
Questions for the case report
1. How would you evaluate the capital budgeting method used historically by
AES? What‘s good and bad about it?
2. If Venerus implements the suggested methodology, what would be the range
of discount rates that AES would use around the world?
3. Does this make sense as a way to do capital budgeting? How do the underlying
assumptions under the new methodology differ from the old ones?
4. What is the value of the Pakistan project using the cost of capital derived from
the new methodology? If this project was located in the US, what would its
value be?
5. How does the adjusted cost of capital for the Pakistan project reflect the
probabilities of real events? What does the discount rate adjustment imply
about expectations for the project because it is located in Pakistan and not the
US?
55
AES’s business and its historic approach to
capital budgeting
56
AES‘s business and history
57
AES‘s business and history
Revenues Costs
1980s
AES
Revenues Costs
2000s
AES
58
Capital budgeting at AES (historically)
59
Capital budgeting at AES (historically)
60
The new methodology for determining discount
rates
61
Capital budgeting at AES (proposed)
𝐸 𝐷
𝑊𝐴𝐶𝐶 = 𝑟𝑒𝑞𝑢𝑖𝑡𝑦 ∙ + 𝑟𝑑𝑒𝑏𝑡 ∙ ∙ (1 − 𝑇𝐶 )
𝑉 𝑉
62
Capital budgeting at AES (proposed)
• What is the levered beta for the Lal Pir project given the target capital structure?
𝛽𝑢𝑛𝑙𝑒𝑣𝑒𝑟𝑒𝑑 0.25
𝛽𝑙𝑒𝑣𝑒𝑟𝑒𝑑 = = = 0.38
𝐸 0.65
𝑉
• What does it mean to use US-based comparables here?
63
Capital budgeting at AES (proposed)
64
Capital budgeting at AES (proposed)
65
Capital budgeting at AES (proposed)
Operational
Weight
3.5%
Score
Regulatory 10.5% 2
Construction 14.5% 0
Currency 21.5% 2
Risk Score
25.0% 2
1.4
66
Capital budgeting at AES (proposed)
• What is the Lal Pir project value at the Lal Pir discount rate?
• $277.52
• What is the Lal Pir project value at the Red Oak discount rate (6.5%)?
• $730.34
67
What is the range of discount rates?
68
Evaluating the new methodology
69
Capital budgeting at AES (evaluation)
• If you were on the board of AES, what would you say? Does any of
this make sense?
70
Expropriation in politically unstable countries
𝐶1 ∗ 𝑆1 𝐶𝑚 ∗ 𝑆𝑚 𝐶𝑚 ∗ (1 + 𝑔) ∗ 𝑆𝑚 𝐺ℎ ∗ 𝑆ℎ
𝑁𝑃𝑉 = 𝐶0 ∗ 𝑆0 + +⋯+ + − 𝑝ℎ ∗
1+𝑟 1+𝑟 𝑚 𝑟−𝑔 ∗ 1+𝑟 𝑚 1+𝑟 ℎ
71
Expropriation of Lal Pir
𝐶1 𝐶𝑚 𝐺ℎ
𝑁𝑃𝑉 = + ⋯+ 𝑚
− 𝑝ℎ ∗ ℎ
1+𝑟 1+𝑟 1+𝑟
730.34
277.52 = 730.34 − 𝑝ℎ ∗ 6
1 + 0.065
𝑝ℎ = 0.905
72
A 50% reduction in Lal Pir cashflows
𝐶1 ∗ 0.5 𝐶𝑚 ∗ 0.5
𝑁𝑃𝑉 ′ = + ⋯+ = 0.5 ∗ 𝑁𝑃𝑉 = 0.5 ∗ 730.34 = 365.17
1+𝑟 1+𝑟 𝑚
• This is still more than under the “appropriate“ Lal Pir discount rate
(NPV=277.52)
73
AES and international CAPM
74
Relating this back to previous content
75
Risk adjustment for cross-border investment (I)
𝑟 = 𝑟𝑓 + 𝛽(𝑟𝑀 − 𝑟𝑓 )
𝑟 = 𝑟𝑓 + 𝛼𝐶 + 𝛽𝑊𝑀 ∙ (𝑟𝑊𝑀 − 𝑟𝑓 )
Source: https://www.msci.com/world
76
A continuum in the degree of integration
77
Risk adjustment for cross-border investment (II)
78
Capital budgeting at AES (proposed)
79
The new approach in the context of S2
80
In summary
81
The key take aways from the AES case
82