Lecture 4 - Project Cost Management
Lecture 4 - Project Cost Management
Lecture 4
This is the instructor’s notes and student has to read the textbook for complete material.
3. Determine Budget
4. Control Costs Monitoring & Control
2. Data analysis
Alternative Analysis: can include reviewing strategic funding options such as: self funding, funding with equity,
or funding with debt. It can also include consideration of ways to acquire project resources such as making,
purchasing, renting, or leasing.
3. Meetings
Project teams may hold planning meetings to develop the Cost management plan. Attendees may include the
project manager, the project sponsor, selected project team members, selected stakeholders , anyone with
responsibility for project cost.
2. Parametric Estimating
Uses a statistical relationship between relevant historical data and other variables
3. Three-Point Estimating
The accuracy of single-point cost estimates may be improved by considering estimation uncertainty and
risk. Used when there is a limited amount of detailed information and insufficient historical data.
M : Most Likely Cost
O : Optimistic Cost
P : Pessimistic Cost
Triangular distribution: E = (M + O + P) / 3
Beta distribution: E = (O + 4M + P) / 6
Project Cost Management Slide 12
Estimate Costs (Cont.)
Tools & Techniques:
4. Bottom-up Estimating
A method of estimating project cost by aggregating the estimates of the lower level components of the
WBS.
When an activity’s cost cannot be estimated with a reasonable degree of confidence, the work within the
activity is decomposed into more detail. The detail costs are estimated. These estimates are then
aggregated into a total quantity for each of the activity’s costs.
Most accurate technique
5. Data Analysis
Alternatives analysis:
Used to evaluate identified options in order to select which options or approaches to use to execute
deliverable
Project Cost Management Slide 13
Estimate Costs (Cont.)
Tools & Techniques (Cont.):
5. Data Analysis (Cont.)
Reserve Analysis
Cost estimates may include contingency reserves to account for cost uncertainty
Contingency reserves budget is included within the cost baseline that is allocated for identified risks
Contingency reserves are often viewed as the part of the budget intended to address the known unknowns that
can affect a project. For example, rework for some project deliverables could be anticipated, while the amount of
this rework is unknown.
Cost of Quality
6. Project Management Information System (PMIS)
Can include spreadsheets, simulation software, and statistical analysis tools to assist with cost estimating.
7. Decision Making
The decision making techniques that can be used in the Estimate Costs process include voting
Voting is an assessment process having multiple alternatives with an expected outcome in the form of
future actions. These techniques are useful for engaging team members to improve estimate accuracy and
commitment to the emerging estimates.
Indirect costs
2. Basis of Estimates
Documentation of the basis of the estimate (i.e., how it was developed)
Documentation of all assumptions made
Documentation of any known constraints
Documentation of identified risks included when estimating costs
Indication of the range of possible estimates (e.g., US$ 10,000 ±10% to indicate that the item is
expected to cost between a range of values)
2. Data Analysis
Reserve Analysis
Contingency Reserve
Management Reserve:
Address the unknown unknowns that can affect a project.
Is not included in the cost baseline but is part of the overall project budget
the amount of management reserve used is added to the cost baseline, thus
requiring an approved change to the cost baseline.
Project Cost Management Slide 18
Determine Budget (Cont.)
Tools & Techniques (Cont.):
3. Funding Limit Reconciliation
The expenditure of funds should be reconciled with any funding limits on the commitment of
funds for the project.
A variance between the funding limits and the planned expenditures will sometimes necessitate
the rescheduling of work to level out the rate of expenditures.
4. Financing
Financing entails acquiring funding for project
It is common for long-term infrastructure and industrial to seek external sources of funds. If a
project is funded externally, the funding entity may have certain requirements that are required
to be met
Earned Value (EV): It is the budget associated with the authorized work that has been completed
Actual Cost (AC): Is the realized cost incurred for the work performed on an activity during a specific
time period
Variance Analysis
Schedule Variance (SV): ( SV = EV - PV )
PV =1000x180 = 180,000
EV =1000x160 = 160,000
AC =1200x160 = 192,000
Variance
SV = EV - PV = 160,000 – 180,000 = -20,000 (Behind Schedule)
CV = EV - AC = 160,000 – 192,000 = -32,000 (Over Budget)
Performance Index
SPI = EV / PV = 160,000 / 180,000 = 0.88 (Behind Schedule)
CPI = EV / AC = 160,000 / 192,000 = 0.83 (Over Budget)
AC= $ 900
Variance
SV = EV - PV = 600 - 800 = - 200 (Behind Schedule)
Performance Index
SPI = EV / PV = 600 / 800 = 0.75 (Behind Schedule)
The most common three ways used for calculating EAC (forecasting):
If future work will be accomplished at the planned rate, use:
EAC = AC + BAC - EV
If the CPI is expected to be the same for the remainder of the project:
EAC = BAC / CPI
This is the instructor’s notes and student has to read the textbook for complete material.