LV Panel Installation
LV Panel Installation
LV Panel Installation
Doc. No.: MOS‐ Panel
METHOD OF STATEMENT Installation
Revision: Rev. 01
Al Haram Road Substation Electrical panel /equipment installation
Date: 07‐02‐2018
CONTENTS
1.0 SCOPE
2.0 REFERENCE DOCUMENTS
3.0 CONTACT PERSONS
4.0 RESOURCES
5.0 MATERIAL FOR PANEL / EQUIPMENT INSTALLATION
6.0 DESCRIPTION OF WORK METHOD
7.0 ORGANIZATION OF MANPOWER
8.0 HEALTH AND SAFETY
9.0 SUPPORTING DOCUMENTS
Doc. No.: MOS‐ Panel
METHOD OF STATEMENT Installation
Revision: Rev. 01
Al Haram Road Substation Electrical panel /equipment installation
Date: 07‐02‐2018
1.0 SCOPE
This procedure outlines the methods to be followed for the erection of Electrical Panels / Equipment.
2.0 REFERENCE DOCUMENTS
PTS NO
Construction Quality Plan
Material Inspection reference
FAT REFERENCE
3.0 CONTACT PERSONS
Site Manager
Project Manager
Safety Engineer
QC Engineer
Site Engineer
Site Supervisor
4.0 EQUIPMENT
In general the main equipment to be used for the erection are listed below :‐
Crane for lifting as per supplier recommendation
Hydraulic lifter
Crow Bar
Ratchet & Torque Wrench, Rolling pipe, D‐shacle, Sling Belt, sprit level
Any other items as per Supervisor requirement.
5.0 MATERIAL FOR PANEL / EQUIPMENT INSTALLATION
As per attached Project Schedule and Project Drawings Pertaining to the Electrical Scope.
6.0 DESCRIPTION OF WORK METHOD
The work method to install the above mentioned Panels / Equipment shall be in the following sequence.
Doc. No.: MOS‐ Panel
METHOD OF STATEMENT Installation
Revision: Rev. 01
Al Haram Road Substation Electrical panel /equipment installation
Date: 07‐02‐2018
A. Pre‐Installation Checks
Verification of Equipment layout from relevant Construction Drawings.
Check drawings are of current revised status.
Site released for Panel Installation.
Conform readiness of the area.
Location of the Panels / Equipment shall be determined and the covered false flooring shall be removed to
expose the main structural steel. This will however be done in phases depending on the panel that is going to
be installed.
Review Vendor drawings of the Panels and familiarize the installation method recommended by the
Vendor.
Exposed floor areas shall be cordoned by means of hazard identifying tape.
Confirm that all Tools & Tackles required for installation are available. As a minimum the following shall be
made available.
Slings
D‐Shackles
Crowbars
Pipe‐Rollers
Fitter’s Tool Box
Electrician Tool Box Welding Machine
Abrasive Cutting Machine Drill
Machine
Grinding Machine
Check adequate place for Unloading the Panels.
Confirm the Height and Width of the entrances.
Personnel involved in the activity are made aware of the risks and the steps to be taken to mitigate any
hazard or unsafe situation.
Foundation frame shall be made and properly aligned for the installation of the Panels.
The tentative sequence for the Panel / Equipment erection will be as per the attached Project Schedule.
B. Material withdrawn from ware‐house
Material inspection will be carried out to ascertain that no damage has occurred to the equipment. Incase of
any damages common inspection and report will be issued.
Store material requisition shall be made.
The material shall be transported in their Original packing to location.
The Crane shall be positioned in such a way that there is no obstruction to movement of vehicles or
hindrance to works of other companies.
Doc. No.: MOS‐ Panel
METHOD OF STATEMENT Installation
Revision: Rev. 01
Al Haram Road Substation Electrical panel /equipment installation
Date: 07‐02‐2018
C. Support prefabrication
The supports required, if any, for the installation of the Panels will
be prefabricated in the workshop in accordance with the vendor recommendations.
Frame supports supplied by vendor shall be placed in position aligned and installed.
Frame installation will be carried out by ensuring that correct level has been achieved.
D. Description of sequence
Equipment packages shall be unpacked outside the sub‐station room just prior to the installation.
Shortages or damages if any shall be brought to the attention of the Engineer immediately.
Each and every loose item shall be properly identified before installation.
Panels shall be lifted by the chain hoist and off‐loaded outside the entrance of the control room
It shall be ensured that the chain hoist range will be within the specified limited capacity.
From here the Panels will be slide on Pipe rollers and or Trans pallets over Plywood sheets and taken to
location.
They will then be placed in position over the foundation frame already installed.
The Panels will then be aligned using Spirit level & Water level.
Interconnection of wires or Bus‐Bars between panels shall be completed.
Bus‐Bars will be tightened with suitable Torque Wrench as per manufacturer recommendation.
Inspection of the installation and punch list.
As‐Built mark‐up drawings certified by Contractor/Engineer.
7.0 ORGANIZATION OF MANPOWER
Team for Panel Installation
Site Engineer Mr. ……………….
Supervisor Mr. ………………..
8.0 HEALTH & SAFETY
All the workers shall be provided with safety equipments to all workers ensure that the same worker using
them in a properly way.
All worker should be made aware about the hazard and risk involved in activity. TBT should be conducted and
PTW should be issued clearly mentioning the responsibilities for manpower.
Our staff has the responsibility to check workmen wearing proper PPE at site daily.
Doc. No.: MOS‐ Panel
METHOD OF STATEMENT Installation
Revision: Rev. 01
Al Haram Road Substation Electrical panel /equipment installation
Date: 07‐02‐2018
If some worker will be found not wearing proper PPE, the supervisor will stop him and provide for those
immediately.
The item issued to the worker must be periodically inspected and changed in case that they are found
damaged or they do not meet the specified conditions.
Personal Protection Equipment
1. Helmet, Hard‐Hat.
2. Hand Gloves (Leather or Cotton)
3. Dust Mask respiratory protection.
4. Safety Shoes.
5. Equipment and Clothing for body protection
Any other, as recommended by Supervisor/engineer.
9.0 SUPPORTING DOCUMENTS
9.1.1 Electrical equipment Layouts.
9.1.2 Electrical Panel Fixing Details.
9.1.3 Vendor Drawings for Installation of the Panels.
9.1.4 Risk Assesment
9.1.5 PTW
Planned Schedule of Activities
As per approved 3‐week Schedule