LV Panel Installation

Download as pdf or txt
Download as pdf or txt
You are on page 1of 5

 

Doc. No.: MOS‐ Panel 
METHOD OF STATEMENT  Installation    
   
Revision: Rev. 01 
Al Haram Road Substation  Electrical panel /equipment  installation 
Date: 07‐02‐2018 
 
CONTENTS 
 

1.0  SCOPE 
 
2.0  REFERENCE DOCUMENTS 
 
3.0  CONTACT PERSONS 
 
4.0  RESOURCES 
 
5.0  MATERIAL FOR PANEL / EQUIPMENT INSTALLATION 
 
6.0  DESCRIPTION OF WORK METHOD 
 
7.0  ORGANIZATION OF MANPOWER 
 
8.0  HEALTH AND SAFETY 
 
9.0  SUPPORTING DOCUMENTS 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
  Doc. No.: MOS‐ Panel 
METHOD OF STATEMENT  Installation    
   
Revision: Rev. 01 
Al Haram Road Substation  Electrical panel /equipment  installation 
Date: 07‐02‐2018 
 
1.0  SCOPE 
 
This procedure outlines the methods to be followed for the erection of  Electrical Panels / Equipment. 
 
2.0   REFERENCE DOCUMENTS 
 
 PTS NO 
 Construction Quality Plan   
 Material Inspection reference   
 FAT REFERENCE         
 
3.0  CONTACT PERSONS 
 
Site Manager       
Project Manager       
Safety Engineer       
QC Engineer       
Site Engineer       
Site Supervisor       
 
 
4.0  EQUIPMENT 
 
In general the main equipment to be used for the erection are listed below :‐ 
Crane for lifting as per supplier recommendation 
Hydraulic lifter 
Crow Bar 
Ratchet & Torque Wrench, Rolling pipe, D‐shacle, Sling Belt, sprit level 
Any other items as per Supervisor requirement.
5.0  MATERIAL FOR PANEL / EQUIPMENT INSTALLATION 
 
As per attached Project Schedule and Project Drawings Pertaining to the Electrical  Scope. 
 
6.0         DESCRIPTION OF WORK METHOD 
 

The work method to install the above mentioned Panels / Equipment shall be in the  following sequence. 

 
 
  Doc. No.: MOS‐ Panel 
METHOD OF STATEMENT  Installation    
   
Revision: Rev. 01 
Al Haram Road Substation  Electrical panel /equipment  installation 
Date: 07‐02‐2018 
 
A. Pre‐Installation Checks 
 
 Verification of Equipment layout from relevant Construction Drawings. 
 Check drawings are of current revised status. 
 Site released for Panel Installation. 
 Conform readiness of the area. 
 Location of the Panels / Equipment shall be determined and the covered false flooring  shall be removed to 
expose the main structural steel. This will however be done in  phases depending on the panel that is going to 
be installed. 
 Review Vendor drawings of the Panels and familiarize the installation method  recommended by the 
Vendor. 
 Exposed floor areas shall be cordoned by means of hazard identifying tape. 
 Confirm that all Tools & Tackles required for installation are available. As a minimum  the following shall be 
made available. 
Slings 
D‐Shackles  
Crowbars   
Pipe‐Rollers 
Fitter’s Tool Box 
Electrician Tool Box  Welding Machine  
Abrasive Cutting Machine  Drill 
Machine 
Grinding Machine 
 Check adequate place for Unloading the Panels. 
 Confirm the Height and Width of the entrances. 
 Personnel involved in the activity are made aware of the risks and the steps to be taken  to mitigate any 
hazard or unsafe situation. 
 Foundation frame shall be made and properly aligned for the installation of the Panels. 
 The tentative sequence for the Panel / Equipment erection will be as per the attached  Project Schedule. 
 
B. Material withdrawn from ware‐house 
 

 Material inspection will be carried out to ascertain that no damage has occurred to the  equipment. Incase of 
any damages common inspection and report will be issued. 
 Store material requisition shall be made. 
 The material shall be transported in their Original packing to location. 
 The Crane shall be positioned in such a way that there is no obstruction to movement  of vehicles or 
hindrance to works of other companies. 
  Doc. No.: MOS‐ Panel 
METHOD OF STATEMENT  Installation    
   
Revision: Rev. 01 
Al Haram Road Substation  Electrical panel /equipment  installation 
Date: 07‐02‐2018 
 
C. Support prefabrication

 The supports required, if any, for the installation of the Panels will 
be prefabricated in the workshop in accordance with the vendor recommendations. 
 Frame supports supplied by vendor shall be placed in position aligned and installed. 
 Frame installation will be carried out by ensuring that correct level has been achieved. 
 
D. Description of sequence 
 

 Equipment packages shall be unpacked outside the sub‐station room just prior to the  installation. 
 Shortages or damages if any shall be brought to the attention of the Engineer immediately. 
 Each and every loose item shall be properly identified before installation. 
 Panels shall be lifted by the chain hoist and off‐loaded outside the entrance  of the control room 
 It shall be ensured that the chain hoist range will be within the specified limited capacity. 
 From here the Panels will be slide on Pipe rollers and or Trans pallets over Plywood  sheets and taken to 
location. 
 They will then be placed in position over the foundation frame already installed. 
 The Panels will then be aligned using Spirit level & Water level. 
 Interconnection of wires or Bus‐Bars between panels shall be completed. 
 Bus‐Bars will be tightened with suitable Torque Wrench as per manufacturer recommendation. 
 Inspection of the installation and punch list. 
 As‐Built mark‐up drawings certified by Contractor/Engineer. 
 
7.0   ORGANIZATION OF MANPOWER

 Team for Panel Installation 
 
Site Engineer  Mr. ………………. 
Supervisor  Mr. ……………….. 
 
 
8.0   HEALTH & SAFETY 
 
 All the workers shall be provided with safety equipments to all workers ensure that the  same worker using 
them in a properly way. 
 All worker should be made aware about the hazard and risk involved in activity. TBT should be conducted and 
PTW should be issued clearly mentioning the responsibilities for manpower. 
 Our staff has the responsibility to check workmen wearing proper PPE at site daily. 
  Doc. No.: MOS‐ Panel 
METHOD OF STATEMENT  Installation    
   
Revision: Rev. 01 
Al Haram Road Substation  Electrical panel /equipment  installation 
Date: 07‐02‐2018 
 
 If some worker will be found not wearing proper PPE, the supervisor will stop him and  provide for those 
immediately. 
 The item issued to the worker must be periodically inspected and changed in case that  they are found 
damaged or they do not meet the specified conditions. 
 Personal Protection Equipment
1. Helmet, Hard‐Hat. 
2. Hand Gloves (Leather or Cotton) 
3. Dust Mask respiratory protection. 
4. Safety Shoes. 
5. Equipment and Clothing for body protection 
 
Any other, as recommended by Supervisor/engineer.
 
9.0 SUPPORTING DOCUMENTS 
 
9.1.1 Electrical equipment Layouts. 
9.1.2 Electrical Panel Fixing Details. 
9.1.3 Vendor Drawings for Installation of the Panels. 
9.1.4 Risk Assesment 
9.1.5 PTW 
 
Planned Schedule of Activities 

As per approved 3‐week Schedule 

Site Engineer  QC ENGINEER  SAFETY ENGINEER  AG Site Manager  NG Consultant 


Azhar Imam  Asjad Zafar  Shahid Ansari  Naukhez A. Kashif  Engr. Yehya Hemdan 
 

           
 