Contents
1 Scope............................................................. 2
2 Conflicts and Deviations................................. 2
3 Applicable Documents…................................ 2
4 Definitions and Acronyms…........................... 2
5 Roles and Responsibilities............................. 4
6 Guidelines……............................................... 5
7 Governance….............................................. 10
Appendix A……..…….…………………………… 12
9COM Creation Flow Chart.……..………....... 12
9COM For New Technology…………………. 13
Appendix B.….….……………………………..….. 15
9COM Description Maintenance Flow Chart.. 15
9COM QM Maintenance Flow Chart………... 16
Appendix C.….….……………………………..….. 17
9COM Deactivation Flow Chart...……..…...... 17
1 Scope
1.2 This Saudi Aramco Engineering Procedure shall facilitate and streamlines the
creation, maintenance, and deactivation of Commodity Material (9COMs).
2.1 Any conflicts between this procedure and other applicable Saudi Aramco
Standards, Procedures and Procurement Manual shall be resolved in writing
through the Projects Procurement Department (PPD) Manager.
2.2 Direct all requests to deviate from this procedure in writing to PPD’s Manager.
3 Applicable Documents
9CAT: Cataloged materials that are intended to be stocked either in Materials Supply
Inventory or by the stocking vendor.
Inspectable 9COM: Materials that require QM Control, Inspection and plant approval.
IR: Inspection Requirement. Saudi Aramco Form SA-175 titled Inspection and
Testing Requirements that contains minimum guideline for inspection and testing found
in the relevant Saudi Aramco Materials System Specification (SAMSS) and industry
codes and standards.
MDM: Master Data Management tool used to catalogue, maintain, and search for
material master in SAP.
Non-inspectable 9COM: Material that neither require inspection nor plant approval.
SCC Organization: Management authority which includes the next level of approval
for SCC.
5.1 The process owner of creation, maintenance, and deletion of 9COMs is technical
entity (Engineering Services) and procurement organization (P&SCM).
5.2 The relevant unit heads from all departments who owned MSG in coordination
with M&SSD is responsible for overall development and maintenance of all
inspectable 9COM.
5.4 Inquiries related to the creation and maintenance of 9COM shall be addressed to
M&SSD.
5.5 SCC and relevant Unit Heads, VID, M&SSD, and SBDD shall process
workflows for creation and maintenance to the 9COMs in accordance to this
procedure.
5.6 Any pending requests more than the mentioned timeframe in Appendices A, B
and C shall be escalated to higher chain of command up to the Chief Engineer
(CE).
5.7 The relevant SCCs shall be responsible for the final determination of the 9COM
inspectability level and RVL management in accordance with established
criteria. If the material determined to be inspectable, SCC shall be responsible
to maintain the description and correspondence specification. In case SCC
rejects the request, his respective Division Head’s approval is required.
5.9 SBDD is responsible to maintain sources linkage for inspectable 9COM and for
non-inspectable 9COM of Downhole and Chemical (process and drilling)
commodities only.
6 Guidelines
6.2.2.4 VID shall review QM data, and link inspection plan form
(SA-175) to a 9COM with category IDCAT-A/B/S.
6.2.2.7 All users shall be notified of the created 9COM. For created
Technology 9COM (refer to paragraph 6.3.2.5), Technology
Management Division (TMD) shall be notified.
6.4.2 Change in the description for the 9COM shall be reviewed / approved by
the SCC. SCC decisions to approve or rejects 9COM’s maintenance
requests as per this procedure shall be approved by his respective
Division Head.
6.4.3 M&SSD shall review and process description change request approved
by the SCC.
6.4.5 All users shall be notified of the description update for the 9COM.
6.4.6 SCC is responsible to conduct 9COM’s mass review every 2-3 years to
be in consistent with the latest Saudi Aramco Engineering Standards’
Revisions.
Note: Any revisions to 9COM description must consider the impact and necessary
actions for those manufacturers that are already approved for the 9COM being
revised.
6.5.1 Request to change the QM data for the 9COM’s can be initiated only by
responsible Technical Department or Inspection Department through SAP
workflow among Company responsible entities. Change in the QM data
for the 9COM shall be reviewed/approved by the SCC and his respective
Division Head. If no inspection plan (SA-175) is available for a certain
commodity, new form should be developed by SCC. In case SCC rejects
the request, his respective Division Head’s approval is required.
6.5.2 VID shall review the proposed QM data change request approved by
SCC. In case the material is changed from IDCAT-C to IDCAT’s
A/B/S, SA-175 form to be developed by SCC and uploaded by VID in
SAP if applicable.
6.6.1 Criteria
The criteria for 9COM deactivation are limited to one of the following:
6.6.1.5 No usage
User is accountable to use MDM search tool and find his required 9COM.
M&SSD engineer can be approached for clarification only. MDM Materials
Search tool is now available through myhome Corporate Portal.
Notes: The use of searching tool requires SAP Role: MMIM:MPSD:GEN_DISPLAY:0000.
E-Training can be taken to learn how to use this new and improved search tool
thru: MDM Search Course.
7 Governance
Revision Summary
4 July 2016 New Saudi Aramco Engineering Procedure that facilitates and streamlines the creation,
maintenance, and deactivation of Commodity Material (9COMs).
28 July 2020 Editorial revision to extend the next plan update.
Appendix A
9COM CREATION
REQUEST BY USER
TOTAL TIME FRAME:
M&SSD 3 BUSINESS
DAYS
SCC ORGANIZATIONAL
REVIEW
M&SSD
CREATE 9COM DESCRIPTION/
SCC 5-10 BUSINESS SPECIFICATION REVIEW
DAYS
IDCAT LEVEL
NO
SYSTEM
NOTIFICATION
TO ALL USERS IDCAT-A/B
YES
SYSTEM NOTIFICATION TO
SYSTEM NOTIFICATION
ALL USERS
TO ALL USERS TO USE
9COM REPLACEMENT
END
TECHNOLOGY DEPLOYMENT
9COM REQUEST BY USER
8-13 BUSINESS DAYS TOTAL
TIME FRAME
M&SSD 2-3
BUSINESS DAYS
M&SSD
REVIEW
NOT APPROVED
END
END
Appendix B
9COM MAINTENANCE
REQUEST BY USER 10 BUSINESS DAYS TOTAL TIME
FRAME
M&SSD
M&SSD 3 BUSINESS DAYS REVIEWS
SCC ORGANIZATIONAL
SCC 5 BUSINESS DAYS
REVIEW AND APPROVAL
NOT APPROVED
UPDATE IR/QM FOR INSPECTABLE
9COMS AS APPLICABLE
VID 3 BUSINESS DAYS SA-175 TO BE UPDATED BY SCC &
UPLOADED BY BID, IF APPLICABLE
SYSTEM NOTIFICATION TO
ALL USERS
END
NOT APPROVED
END
Appendix C
9COM DEACTIVATION
REQUEST BY USER
M&SSD REVIEWS
MANAGEMENT 3 BUSINESS DAYS DEACTIVATION
CRITIERIA
SCC ORGANIZATIONAL
SCC 5 BUSINESS DAYS REVIEW AND APPROVAL
AUTO DELETION TO
SOURCE AND QM FOR NOT APPROVED
INSPECTABLE 9COMS
SYSTEM NOTIFICATION
TO ALL USERS
END