Esd Module 3 - Notes
Esd Module 3 - Notes
1
For large multi stored building where there are several floors, the
main switch board controls the circuit to each floor. Sun DBs are placed
on different floors and all sub circuits are taken from them.Such a
system of wiring is known as ‘tree system of wiring’. In a tree system,
conductors are taken from the point of supply to the various load
points.The conductors constituting the main branch are known as rising
mains or risers.
Rising mains virtually forming a vertical bus-bar chamber. Such a
unit which is continued through out the height of a five storey building is
fitted into a GI chamber in the building is shown in figure.
2
Design considerations of electrical installation in commercial buildings
1. Deciding the number of sub circuits: The total load in the
commercial building is calculated taking into consideration of general
lighting load, motor load and other power loads. The load on each light-
fan sub circuits shall be restricted to 800W or 10 outlets and load on
3
each power sub-circuit is restricted to 3000W or 2 outlets. To
accommodate future growth, spare circuits are also provided.
2. Deciding the size and rating of switch board and distribution
boards: Sub circuits are fed from sub DBs, which in turn are fed from
main DBs. The sub DBs, main DBs are designed stage by stage
considering the load at different levels.The DBs, Isolators should be
accessible to maintenance personal and located such that faulty circuits
can be identified easily
3. Deciding the size of cables: The size of cables can be found by
calculating the actula current value at each stage. PVC /XLPE (armoured
or un armoured) cable can be used.
4. Deciding the size of conduits: Size of conduits determined from
the size of cables and the number of cables to be drawn through it.
The number of 1/1.80 Al or (1.5mm2 Cu) cable that can run through a
19mm (20mm) conduit are 6 or 5.
5. Bus-bar and Bus-bar Chamber: Bus-bar chamber consists of Bus
-bars which are strips of Cu or Al. The incoming lines are connected to
these distribution bus-bars through the main switch fuse and the load
circuits are supplied from the bus-bars through the switch fuse units. In
a bus-bar chamber there are fixed for bus-bars of which 3 are for the
three phase and the fourth for the neutral. Considering the current
carrying capacity the size of Al or Cu bus bars can be calculated.
4
The size of Chamber depend on
1. The size and number of strips used
2. The number and rating of switches to be mounted on it.
It is usually made up of 16 SWG MS sheet.The bus bar strips are
mounted on bakelite or other supports having their width in their vertical
plane. Each SFU is connected to the Bus-bar Strips by means of strips or
wires of the same material as the bus-bar.
6. Mounting arrangements of switch boards and DBs: switch
boards and DBs can be mounted on the wall or on the floor. Any type of
mounting frame can be made with suitable angle iron
7. Earthing of the Electrical Installation: All the non-current carrying
metal parts shall be earthed properly. All metal conduits, trunking, cable
sheaths, switch gear, DBs, starters, motors, lighting circuits shall be
connected by means of two separate and distinct earth continuity
conductors to an efficient earth electrode.
8. Selection of earth electrode and earth conductors: For earthing
of installations in building, residential premises, small industries, only GI
5
pipe (Cu) or rod earth electrodes are used. GI plate electrodes can be
used for industrial loads upto 30HP. For above 30HP and for power
house and substations, Cu plate earth electrodes are used.
Classification of Industrial Buildings
1. Based on fire hazard
2. Based on Power Consumption
3. Based on Pollution hazard
1. Classification based on fire hazard
(i)Group G1-Building used for low fire hazard industries
Operation/process conducted in those buildings,there
are no possibilities of self propagation of fire to occur.Only effect of
fire from external sources.
E:g; Cement factories,Glass factory,Rice mill,Soap and detergent
factory etc.
(ii) Group G2 Building of moderate fire hazard
In this type, operation/process are liable to give rise to fire that
will burn with moderate rapidity, produce considerable volume of
smoke or non toxic fumes and will not result in an explosion
E:g; Ship repairing docks, coir industry, chemical manufacturing,
flour mill etc
(iii) Group G3 Buildings with high fire hazard
In this type, operations/ process are liable to give rise to a fire
which will burn with extreme rapidity, generate poisonous fumes,
lead to explosions.
E:g; Alcohol distilleries, explosive manufacturing, fire work industries,
oil
mill, petrochemical.
2. Classification based on power consumption
(i) Light industries(Small)
(ii) Average industries (medium)
6
(iii) Heavy industries
SL Description Average power Examples
No. requirement
1 Light industry Up to 50 kVA Hosiery, garment making,
ornament making etc
2 Average above 50 up to Furniture pottery, glass,
Industry 2000kVA
Tobacco , electrical gadgets,
textiles, engine fitting, light
processing etc.
3 Heavy industry above 2000kVA Heavy electrical equipment ,
steel mills, foundries , ship
building, chemical plants,
fertilizer plants, metal
extraction, petrochemicals,
paper mills etc.
7
Continuous conductivity occurs due to conductive dust, rain
or other wet conditions.
8
Design considerations of electrical installation in small industries
1. Motor current
When the motor is first connected to line, it will draw much
more current than its rated current till the motor comes upto
speed.This is Staring current of the motor.as the motor
reaches full speed delivering its rated horse power at rated
voltage the motor carries the full load current.
The current rating of cables for supply to motor may be
based upon the normal full load current of the motor, but the
rating of fuse should be based upon the starting current.
2. Deciding the size of cable
The cables shall have a current carrying capacity of not less
than 150 percent of the motor full load current rating.
For Eg:
(a) D C motors
Current required by a 400V 15hp DC motor at 80% efficiency
hp 746 15 746
= 33 . 2 A
V 400 0 . 8
The current carrying capacity of the cable should be 1.5 times the
full load current = 33.2 x 1.5 = 49.8A.
The size of the cable that can be used are: 7/1.63mm Cu
conductor cable of capacity 53A or 7/2.24 mm Al conductor cable of
capacity 59A.
(b) Single phase ac motors
The input current of a motor, 5hp single phase A C 240V at
hp 746 5 746
75% efficiency and 0.8pf = 25 . 5 A
V pf 240 0 . 75 0 . 8
The current carrying capacity of the cable should be 1.5 times the
full load current = 25.5 x 1.5 = 38.23A.
The size of the cable that can be used are: 7/1.40mm Cu
9
conductor cable of capacity 43A or 7/1.70 mm Al conductor cable of
capacity 43A.
( c) Three phase AC motors
The input current of a 3 phase motor, 10hp, 415V at 85%
hp 746 10 746
efficiency and 0.8pf = 15 A
3 V pf 3 415 0 . 85 0 . 8
The current carrying capacity of the cable should be 1.5 times the
full load current = 15 x 1.5 = 22.5A.
The size of the cable that can be used are: 7/1.06mm Cu
conductor cable of capacity 28A or 1/2.28 mm Al conductor cable of
capacity 27A.
3. Determination of the size of conduit
The size of conduit depends on:
(a) The number of cables to be installed
(b) The cross sectional area of the cable
(c) The permissible conduit fill
4. Deciding the fuse rating
The criteria for selecting the correct size of fuse for motor
protection is that may carry the starting current safely.
For eg:
The full load current of a 3 phase motor, 10hp, 415V at 75%
hp 746 10 746
efficiency and 0.8pf = 17 A
3 V pf 3 415 0 . 75 0 . 8
10
SL Types of motors Methods of starting
No.
1 Induction motors of very low DOL starter
rating
2 Induction motors of medium Star - delta starter
rating (upto 15 hp)
3 Induction motors of high rating Auto-transformer starting
4 Slip ring induction motors of Rotor Resistance starters
high rating
5 D C series motor Two point starter
6 DC shunt/compound motor Three point starter
11
Sol:
The schematic or single line diagram for the motor installation is shown
below
(a) Size of wire: Assume the motor efficiency to be 85% and power
factor 0.8, the full load current of the motor,
hp 746 15 746
IL 23 . 1 A
3 V pf 3 415 0 . 85 0 . 8
The current carrying capacity of the cable should be 1.5 times the
full load current = 1.5 x 23.1 = 34.6 A
The size of the cable that may be used is a single core PVC
insulated 7/1.70mm Al conductor cable.
(b) Size of conduit : From the main board to motor switch and from the
motor switch to motor starter, only 3 wires to be run. Hence 32mm
heavy gauge conduit is required. From the motor starter to motor
terminals 6 phase and one neutral wires are to be run and 38mm
heavy gauge conduit is used.
12
(c) Rating of switch fuse: Starting current of the motor = 1.5 x 24 = 34.6A
So the main switch and motor switch to be used can be 40A
500Vgrade TPIC switches.
The complete wiring diagram for the installation is shown in fig.
(d) Length of the conduit required: the following assumptions are made:
the main switch, motor switch and the starter are installed at a height
of 1.5m above the floor level
Height of conduit run above floor level = 3m
(1) Length of 32 mm conduit
From main switch to motor switch =
Allowing 20 % wastage =
Total =
13
(2) Length of 38mm conduit:
(a) From motor starter to ground and 0.30m below it (1.5+0.3)
=1.8m
(b) From ground to motor foundation 0.5m above the ground level
(2.5+0.3+0.5) = 3.3m
Total = (a) +(b)
(3) Length of 32mm flexible conduit required = 0.6m
(4) Length of 38mm flexible conduit required = 1m
(e) Length of wire required:
(1) From meter to main switch (3 run) = 3 x 0.3 = 0.9m
(2) From main switch to motor switch = 3 x 27 + 2x 3 x 1.5 = 90m
(3) From motor switch to motor starter = 3 x 0.3 = 0.9m
(4) Form motor starter to motor terminals (7 runs) = 7x1 = 7m
Wastage 20%
Total =
(f) Length of earth wire required :
Two separate earth electrodes have to be provided. According to
IE rules, motor frames, starters, motor and main switches, all metal
parts are to be earthed by two separate and distinct earth
conductors to the earth electrode.
No.8 SWG GI wire can be used as earth wire .
Length of earth wire = 2 x 40 m = 80m
(g) Labour cost : As the distance between motor and main switch is 30m,
one electrician with a helper will take 3 days to complete the work
(h) Schedule of material
14
15
Q2) A small workshop has to be equipped with the following machinery:
(1) One 5hp, 400V, 3phase motor
(2) One 3hp, 400V, 3phase motor
(3) One 1/2 hp, 230V, 1 phase motor
(4) One 1hp, 400V, 3phase motor
The positions of the machines are shown below. Draw the wiring
diagram, estimate the quantity of materials required.
Sol:
(a) Main supply: Assume the motor efficiency to be 85% and pf to be 0.8
for the machines.
hp 746 5 746
(1) Motor 1, I L1 7 .5 A
3 V pf 3 415 0 . 85 0 . 8
hp 746 3 746
(2) Motor 2, I L2 4 .5 A
3 V pf 3 415 0 . 85 0 . 8
hp 746 0 . 5 746
(3) Motor 3, I L3 2 . 25 A
V pf 240 0 . 85 0 . 8
hp 746 1 746
(4) Motor 4, I L4 1 .5 A
3 V pf 3 415 0 . 85 0 . 8
16
Total full load current for these motors = 15.75A
The current rating of the main switch is the starting current of the
large motor plus the load current of the remaining motor.
So, 25A, 500V grade TPIC SFU shall be used as main switch.
17
(3) Motor 3, IL3= 2.25A, Is3= 3.37A, 1/1.80mm AL cable (10A)
(c) Rating of switch fuse : The 3 nos. 3 phase motor of rating 5,3,1hp can
be controlled by 16A, 500V TPIC switches and the 1/2 hp single phase
motor can be controlled by a 16A, 250V DPIC SFU.
18
(1) Number of sub-circuits:
Grading of Fuses
The feeder to a DB will be fed from SDB or MDB. It is necessary
that the major protective fuse shall not blow off before or along with
motor protective fuse in the DB. There shall be grading or discrimination
between these fuses. The fuses in two systems are termed as minor and
major fuses. For achieving grading, the minor fuse should be lower than
19
half of the major fuse.
Substations
Types of substations:
20
1. Transformer substations
4. Converter substations
21
Transformers above 400kVA are installed on a foundation or plinth with
a fence or wall surrounding it.
11kV LA (3 nos) are erected at the top of the H - pole structure for
the protection of the transformer against lightning. Earth terminals of
all 3 LA are joined together and connected to earth provided specially
for LA.
11kV horn gap fuses installed below the G.O switch and 11kV
transformer bushings to protect the transformer on the 11kV side.
22
23
24
25
Earthing arrangement of substations
26
Bus-bar Arrangements
1. Single bus scheme.
27
3. Ring bus system.
28
Indoor Substation -Floor mounted Type
Indoor substations of 11kV/415V are quite frequently installed in
industrial areas and big cities where load requirements is heavy and
continuity of supply is very important.
Industrial units, continuous processing plants, important commercial
complexes, railway stations, telephone exchange, cinema houses all
employ indoor substations.
General requirements:
The substation building should be constructed providing the
necessary accommodation for the transformer, HT and LT switch
gear and cable trenches for incoming and outgoing cables.
The building for housing the transformer should be spacious and
should be sufficiently high.
Adequate clearance between the walls and equipment and between
different equipment should be provided to ensure safety of the
personal
Adequate provision for ventilation must be ensured, so that there is
free circulation of air on all sides of the transformer and with in the
building.
29
11kV OH line terminates on a pole structure outside the indoor
substation
11kV GO(Gang operating) switch and LA (Lightning arrestors) are
installed in it for isolation and protection.
The supply from the OH line is brought inside the substation through
an UG cable using an out door cable box.
11kV CB (Oil/Air/Vacuum) is placed at the incomer enters the
substation
Transformer shall have cable boxes at the HT and LT ends
LT circuit breaker is connected at LT side using a four core cable.
The size of the cable depends on the rating of transformer
30
Up to 300A SFU is used. Above that OCB is used at LT side
The LT OCB. LT bus-bars, and the SFU feeding local circuits,
capacitor banks are all installed on a LT panel board.
11kV metering by KSEB is provided at the 11kV side of the
transformer.
PT & CT are installed at HT lines with the 11kV OCB. The output of
CT and PT are brought to metering devices.
For LV metering, supply is run directly to the meters.
Fire fighting equipment should also be provided at the room
Portable CO2 dry chemical fire extinguishers shall be installed in the
substation at suitable place.
Fire buckets shall be installed with a suitable stand for storage of
water and sand.
First aid charts displaying methods of giving artificial respiration to a
recipient of electrical shock shall be provided at appropriate places
Standard first aid boxes containing materials should be provided in
front of switch boards and other control equipment.
Danger sign plates shall be provided on HV and MV equipment.
Earthing:
LA should be earthed separately
Two separate and distinct earth electrodes shall be provided for
neutral earthing.
Body of the transformer,HV and MV panels etc, the earth conductor
is to be connected to a common earth bus run between another two
separate and distinct earth electrodes.
For a single transformer substation total number of earth electrodes
shall be 5.(1 for LA, 2 for neutral, 2 for body parts).
31
32
Q1) An outdoor pole mounted 11kV/415V substation has to be
installed for supply to a residential area having a load of 63kVA.
Estimate the quantity of materials required.
Sol:
For erection of the transformer and allied accessories, PCC poles of
11m length can be used. On a double pole structure, LA, HG fuse units,
GO switch, and disc insulators are installed along with the distribution
transformer. 2 sets of stays and 3 sets of earthing arrangements are to
be made.
To find the size of cable to be run from the secondary side of the
transformer, the current rating should be found out.
63 10
3
3-1/2 core 95sq.mm cable should be run from the transformer to the
distribution box and from the distribution box the different feeder cables
are to be selected by taking into consideration of the load of each circuit.
2 11kV LA 3 nos.
33
8 3-1/2 core 95sq.mm PVC insulated LT cable 8m
Sol:
34
3-1/2 core 185 sq.mm cable should be run from the transformer to
the distribution box and from the distribution box the different feeder
cables are to be selected by taking into consideration of the load of each
circuit.
2 11kV LA 3 nos.
35
18 Aluminium paint 2lts
Sol:
(3) 2 nos. 63A SFU along with LT bus bars and cable boxes.
LT cables:
36
(1) 3-1/2 core 185 sq.mm PVC insulated LT cable to rum from
200A SFU
(2) 3-1/2 core 95 sq.mm PVC insulated LT cable to rum from 100A
SFU
(3) 3-1/2 core 50 sq.mm PVC insulated LT cable to rum from 63A
SFU
37
11 3-1/2 core 95sq.mm PVC insulated LT cable 50m
38
insulated LT cable can be used.
Line diagram:
Estimation of materials:
2 11kV LA 3 nos.
39
17 Stay wire7/8SWG 30kg
3-1/2 core 95sq.mm cable should be run from the transformer to the
distribution box and from the distribution box the different feeder cables
are to be selected by taking into consideration of the load of each circuit.
The distribution box consists of one 100A incoming main switch and
4 nos. Of outgoing switches.
1 no. 63A for 25hp agricultural load, 2 no.s of 30A for 10kW
residential load and 15hp water works, 1 no. 30A spare for future
40
expansion.
2 11kV LA 3 nos.
41
17 Earthing sets 3 sets
Sol:
Dead end poles and every 10th structure is to be double pole and
the rest are single pole structures. The no.of poles required = 57
Insulators
11kV pin insulators on all intermediate pole structures = 45 x 3
=135
42
Cross arms
GI cross arms 1.5m x 12.5 cm x12.5 cm = 45
Angle iron pieces 38mm x 38mm x 6mm for supporting earth wire
on double pole structure = 12
Angle iron pieces 38mm x 38mm x 6mm for supporting earth wire
on intermediate structure = 45
Conductor
Length of ACSR conductor 6/1x2.59mm = 3 x 3000 + 2% for sag
and wastage =9180m
Substation
The supply is taken from 11kV, 3 phase 50Hz OH transmission line
which terminates on a double pole structure. The protective devices
such as GO switch, HG fuses, LA are all erected on the pole structure.the
supply is taken by 11kV 3 core 25 mm2 paper insulated cable.
The capacity of the transformer can be calculated based on the
connected load
400 150 100
Total connected load = 0 . 6 500 kVA
0 .8
( Assume pf 0.8 &
load factor 0.6)
An 11kV/415V 500kVA transformer is to be installed in the indoor
substation. An LT OCB 1000A 415V can be connected to protect the LT
43
panel.
The LT panel consists of:
1. A 600A, 415V LT OCB to feed the production shop load.
2. A 300A SFU to feed the foundry shop load
3. A 200A SFU to feed the light & fan load in the administration
block.
4. One 200A & 300A SFU as spare
Size of cables
50010 3
Line current at the secondary of the transformer, IL 696 A
3 415
44
SL Description of material Quantity
No.
11 11kV LA 3 nos.
45
nos.of 300A, and 2 nos.of 200A SFU along with LT
bus bars and suitable cable end boxes
46
47