Project Management Pop Quiz (Alicia)
Project Management Pop Quiz (Alicia)
Project Management Pop Quiz (Alicia)
Question 2
The project team can sync their schedule with the team’s calendar. This allows members to
check when each member is available and assign the most ideal meeting time where most
members can attend. They can also attach meeting materials to the event set in the
calendar.
Allocation of resources software can allow the team to identify what resource is required
and allocate them to a particular time and task. It can prevent overworking in team
members.
Instant messaging allows team members to quickly send short text messages between each
other. They can discuss topics in real time.
Question 3
(a) CPM (Critical path method) is a diagram that shows the shortest time to complete a
project while Gantt Chart is a table diagram that shows the tasks to complete in
greater detail. They both show which tasks are dependent on each other, both
indicated by an arrow connecting a task to another depending task. Moreover, they
both provide an estimated time to complete each task.
On the other hand, Gantt Charts are known to display more details about each task
compared to CPM, at the columns next to each task, the project managers are able
to note who is the person responsible for that task, the estimated start and end date
of each task and extra notes.
CPM represents each milestone with a circle that is numbered for reference.
(b) Gantt Chart has a moving line the list of tasks that shows the current time/ progress
the project is expected to be at, it can be used to identify which tasks are behind
schedule. There are columns next to each tasks to show further details (such as who
is the person responsible for the task, the estimated start and end date of each task)
Question 4
(a) PERT allows managers to use an estimated time when a fixed time to complete is not
known. This time is carefully calculated with most optimistic, most likely and most
pessimistic time. This means it also takes account various delay scenarios that the
project might run into, which makes the diagram reliable to run and easier to
estimate completion time. Moreover, PERT is more flexible to adapt to unpredicted
issues that may arise as it can account a sufficient float time. PERT can schedule for
uncertain activities while CPM can only define known activities.
Furthermore, PERT reduces the rate of the project timeline being overlooked as it
holds greater details of each task compared to CPA.
Moreover, PERT allows critical path time to be calculated more precisely as it is a
technique to plan and control activities based on time, CPA controls costs and time
more.
(b) WBS allows project managers to breakdown large complex tasks into smaller
manageable chunks. It can identify what tasks are subtasks of a main task with its
hierarchal layout. Managers can spot which phase has a heavier amount of task and
assign more resources to the particular phase to ensure that each team is not
understaffed or overworked. Each team manager can be assigned to each phase,
while team members carry out the sub-stages in each phase. WBS can show the
relationship between each task.