RESEARCH METHODOLGY
(BQS514)
ASSIGNMENT 3
RESEARCH PROPOSAL
GROUP: AP2243C
1
TABLE OF CONTENTS
2
1.0 TITLE OF RESEARCH AND KEYWORDS
2.0 ABSTRACT
According to Yusof et al. (2021), the construction industry is one of the key contributors to
employment and economic growth in Malaysia. However, the rising number of abandoned
structures is a significant issue for the construction sector. Construction work that has been
consistently put off for six months or more, either within the project's completion term or after the
projected completion date, is defined as an abandoned building, as stated by Doraisamy et al.
(2021). Abandoned projects have a negative impact on a number of stakeholders, including the
client, contractor, and consultant. Previous studies have shown that leaving a facility unattended
can result in major issues, which call for a mitigating strategy. This research will investigate the
factors that causes the abandonment of a building in Malaysia as well as its effect towards the
economy and the surrounding environment in Malaysia. The data for this research was collected
from respondents who are contractors in Malaysia who has experience in the construction
industry as well as documents related to abandoned buildings in Malaysia that were collected
from the internet. According to the perspective of the respondents, it is clear that the developers’
financial issues are the major cause of the building's abandonment. So, one of the solutions that
the respondents could agree was to enforce the law in construction industry regarding to building
abandonments by developers.
3
3.0 INTRODUCTION
According to Ariffin (2018), any country's economy would not function without the construction
industry. When the economy is doing well, construction activity often increases, but when the
economy is struggling, project abandonment is more frequent. As mentioned by Ariffin (2018),
construction work that has been consistently put off for six months or more, either within the
project's completion term or after the projected completion date, is defined as an abandoned
building. Abandoned projects have a negative impact on many stakeholders, including the client,
contractor, and consultant. Mainly due to its detrimental effects on the nation, the topic of
abandoned buildings is now one that comes up regularly. Construction abandonments have taken
place in both public and private housing projects as well as commercial buildings.
As stated by Sabri (2019), the issue of abandoned building constructions first surfaced when there
were increasing numbers of project delivery delays, development was regularly halted for at least
six months, vacant homes were placed on the market without a buyer, and in the worst-case
scenario, the project was abandoned for unknown reasons after the contract had expired. Before
a project is deemed abandoned, there are a number of phases that must occur, under the
ministry's definition. It is labelled "late" if it is 10% past the scheduled delivery date; "sick" if it is
10% or more past the planned delivery date; and "abandoned" if no work is being done on the
project site or no staff is present for up to six months, as mentioned by Sabri (2019).
As stated before, when a building is abandoned, it may have a bad impact on organizations as
well as the parties involved and the surrounding area. The parties involved run the risk of losing
money as well as the public's trust, particularly in the case of a government-funded initiative. They
should be aware of the project's goals as a development business so that the projects may be
completed. In addition, a portion of the structure was demolished because of structural and
architectural issues. The expense of the project will rise the longer the structure is abandoned.
From the viewpoint of society, abandoned buildings might potentially turn into places where
crimes can be committed, according to Salam et al. (2020).
In light of this, this research was carried out to determine the causes of abandoned construction
projects in Malaysia and the steps that may be taken to mitigate the situation in the near future.
4
4.0 PROBLEM STATEMENT
The problem statement for this research may be divided into three namely delay in delivery of
project, financial problems and mismanagement.
5
4.3 Mismanagement of the project
According to Salam et al. (2020), the basic goal of construction management is to closely
regulate and track a project's development in terms of quality, cost, and time. The
inexperience of developers may lead to management errors. Some of the examples of
mismanagement that may lead to abandoned housing projects include absence of sufficient
feasibility studies, notably incorrect market research. The project's ability to function smoothly
will be reduced, and the extra time and money required to do a complete feasibility study
during the project's commencement stage will result in the project being abandoned (Adil et
al., 2019).
Another example of mismanagement is fraud. Non-payments or unreasonably decreased
payments of progress billings are a type of fraud. These actions can cause cash flow issues
for suppliers, contractors, and subcontractors, which may ultimately lead to project delays or
project abandonment. As mentioned by Salam et al. (2020), fraud may also be the result of
exorbitant buyer funds being spent, which causes housing projects to be abandoned.
Developer participation in false claims is another instance of fraud. Developers and their
architects work together to have the architects produce progress claim certifications that
fraudulently show greater levels of building progress so that the developers may withdraw
funds from the project.
6
6.0 RESEARCH QUESTIONS
Three research questions are posed to the researcher to aid in reaching the study objectives in
order to support the researcher. The following are the research questions.
a) What are the issues of that makes a construction building being abandoned in
Malaysia?
b) What are the effects of abandoned buildings on the economic and surrounding
environment?
c) What are the solutions to overcome the problems involved in abandoned building
construction in Malaysia?
The aim of this research focusing on the issues of abandoned building construction in Malaysia.
The scope of study is limited to the parties that are involve in the construction of a building in
Malaysia, which are namely consultants, contractors, developers, architects, engineers, clients,
private sectors and also the government.
Specifically, this research will only reach out to the parties that are involved a construction project
that is being abandoned in Malaysia, asking about their experience and involvement. This scope
of research will be conducted for around 2-4 months through questionnaires and documentation,
which the data will be analyzed by using content analysis as well as Statistical Package for the
Social Sciences (SPSS). Lastly, the geographical location that is being covered in this research
will be only in Malaysia.
7
8.0 RESEARCH METHODOLOGY
In order to create trustworthy and acceptable findings in accordance with the scientific method,
research techniques are the dissertation procedure. According to Patel (2019), a research
problem is the first step in every research process. To conduct well-defined research, it is critical
to have a well stated research problem. The research design stage is the next step in the study
procedure. Therefore, the design is influenced by the study approach that was used. The actual
data collecting and analysis is the next step in the procedure. The study approach employed will
determine how the data are collected and interpreted. The reporting of the findings and
suggestions for further investigation is the process's last stage.
The research strategy that has been applied in this case study is the mixed method research
which are namely qualitative research as well as quantitative research. This is due to the fact that
the researcher used documents and distributed questionnaires to conduct the research, which
can be classified under documentation, which is a qualitative research method as stated by
Malhotra (2017). Meanwhile, the questionnaires will be conducted using Likert’s Scale, which is
a quantitative method Malhotra (2017). The figures below will show the topic, aim, questions and
objectives of this research as well as the outline of research.
TOPIC RESEARCH
Factors of Abandoned Building in Malaysia's Construction
Industry
AIM OF RESEARCH
To examine the factors of
abandoned building in
Malaysia’s construction
industry.
QUESTION 2 QUESTION 3
QUESTION 1
What are the effects of What are the solutions to
What are the issues of abandoned buildings on the overcome the problems
that makes a construction economic and surrounding involved in abandoned
building being abandoned environment? building construction in
in Malaysia? Malaysia?
OBJECTIVE 1 OBJECTIVE 2
To identify the factors that To identify the effects of OBJECTIVE 3
abandoned building To analyse the possible solutions to
contributes to the construction towards the
abandoned building overcome the issue of abandoned
economy and the surrounding building construction in Malaysia.
construction in Malaysia. environment in Malaysia.
Figure 8.1.1 shows the Topic, Aim, Questions and Objectives of this research
8
STAGE 1
Problem
identification and
brainstorming ideas
STAGE 1 (Cont'd)
STAGE 4 Establishments on
objectives, scope of
Conclusion and work and problem
recommendation statement, research
question
STAGE 2
Data collection
through
Documentation and
Questionnaire
The reason why the researcher used quota sampling method is due to the fact that to investigate
the contractor’s knowledge and perspectives about the research. As an illustration, the population
of contractors in Sarawak is 500 contractors. The researcher will just require a sample of the
population in order to comprehend and get comments from it, as mentioned by Jan (2020).
9
Additionally, the researcher is particularly interested in certain population strata. According to Jan
(2020), quota sampling can aid in this situation by classifying the population into groups or strata.
In this research, the researcher aims towards the population of contractors in Malaysia. The
researcher will only take around 100 samples out of 81,301 samples of registered contractors
under Construction Industry Development Board (CIDB), which means the percentage of samples
will be 0.12%. The statistic below shows the amounts of registered contractors from January 2004
to June 2017.
10
Figure 8.4 shows Likert’s Scale
11
9.0 REFERENCES
12
11. Salam, S. A., Ariffin, N. F., Mohamad Noor, N. F. N., Ali, M. I., & Ramli, N. I. (2020). Effect
of mismanagement towards abandoned project in Malaysia. IOP Conference Series: Materials
Science and Engineering, 849(1). https://doi.org/10.1088/1757-899X/849/1/012004
12. Showkat, N., Parveen, H., & Parveen NayeemShowkat, H. (2017). Non-Probability and
Probability Sampling Review View project Mass Communication Theory View project M16-Non-
Probability and Probability Sampling P2-Communications Research Quadrant-I (e-Text)Title Non-
Probability and Probability Sampling Module ID P2M16 Pre-requisites Objectives Keywords Non-
Probability and Probability Sampling M16-Non-Probability and Probability Sampling P2-
Communications Research Quadrant-I (e-Text).
https://www.researchgate.net/publication/319066480
13. STUDY ON FACTORS THAT LEAD TO THE ABANDONED BUILDING PROJECT IN
BORNEO (SABAH & SARAWAK) IZYANA JANNATI BINTI SABRI B. ENG (HONS.) CIVIL
ENGINEERING UNIVERSITI MALAYSIA PAHANG. (n.d.).
14. Yusof, A. M., Khoso, A. R., Sohu, S., Khahro, S. H., & Chai, C. S. (2021). Improving
performance in construction projects: A case study of malaysian public projects. Pertanika Journal
of Science and Technology, 29(4), 2579–2604. https://doi.org/10.47836/PJST.29.4.19
15. Doraisamy, S. v, Akasah, Z., & Yunus, R. (n.d.). A REVIEW ON ABANDONED
CONSTRUCTION PROJECTS : CAUSES & EFFECTS.