Kosovo - Grid Code - Connections Code
Kosovo - Grid Code - Connections Code
CONNECTIONS CODE
ver. 2.4 page 1 from 32
October 2018
GRID CODE PO-KO-005
CONNECTIONS CODE
ver. 2.4 page 2 from 32
CONTENTS
1 Introduction...................................................................................................................................... 6
2 Objective .......................................................................................................................................... 6
10 Derogations .....................................................................................................................................73
10.1 General Provisions ...................................................................................................................... 74
10.2 Request for a derogation by a power-generating facility owner, demand facility owner or
distribution system operator ...................................................................................................... 74
10.3 Request for a derogation by a TSO or by a DSO .......................................................................... 76
10.4 Monitoring of derogations .......................................................................................................... 77
GRID CODE PO-KO-005
CONNECTIONS CODE
ver.2.4 pages 6 from 32
1 Introduction
1.1 The terms and conditions on which connection to the transmission system is granted will be set
out in a commercial agreement, entered into by the user and the transmission system operator (TSO).
This is called the Connection Agreement (CA) and is contractual agreement between the TSO and the
user for each individual connection point of the transmission system. Where a user has multiple
connections on a single site then only a single CA is required.
1.2 The TSO by entering into a CA with a particular user must ensure that the quantity and quality of
service to be in accordance with the criteria set out within this connections code, except if specifically
varied by the relevant CA.
1.3 Users by entering into a CA with the TSO must ensure that they abide by the rules, procedures,
technical specifications and equipment requirements as outlined in this code.
2 Objective
a) There are appropriate procedures for connection of, new or refurbished, user’s plant and
apparatus and that the basic rules for connection treat all users in a non-discriminatory fashion
and in accordance with all statutory and licence obligations;
b) The minimum technical, design and operational criteria specified in this connections code are
designed so that a new or modified connection to the transmission system shall:
- Not deteriorate the system operating conditions compared to the conditions defined in
this connections code;
- Nor impose the same conditions on the transmission system or on the system of any
other user:
3 Scope of application
3.1 This connections code shall apply to all parties that apply and those connected to the
transmission system. This covers all those whose current or prospective activities which includes the
following categories:
3.2 This Code, therefore, helps to ensure fair conditions of competition in the internal electricity
market, to ensure system security and the integration of renewable electricity sources, and to facilitate
Union-wide trade in electricity
3.3 This Code also lays down the obligations for ensuring that TSO makes appropriate use of the
demand facilities' and distribution system' capabilities in a transparent and non-discriminatory manner
to provide a level playing field.
3.4 The TSO shall refuse to allow the connection of a new transmission user’s, which does not comply
with the requirements set out in this Code and which is not covered by a derogation granted by the
regulatory authority. The TSO shall communicate such refusal, by means of a reasoned statement in
writing, to the transmission users and, unless specified otherwise by the regulatory authority, to the
regulatory authority.
3.5 In case of demand facilities with more than one demand unit, these demand units shall together
be considered as one demand unit if they cannot be operated independently from each other or can
reasonably be considered in a combined manner
a) power-generating modules that were installed to provide back-up power and operate in
parallel with the system for less than five minutes per calendar month while the system is in
normal system state. Parallel operation during maintenance or commissioning tests of that
power-generating modul shall not count towards the five-minute limit;
b) power-generating modules that do not have a permanent connection point and are used by
the system operators to temporarily provide power when normal system capacity is partly or
completely unavailable;
c) storage devices except for pump-storage power-generating modules (which shall fulfil all the
relevant requirements in both generating and pumping operation mode);
It is acknowledged that some existing plant and/or apparatus will, in part or in whole, be unable to
comply with some of the minimum standards specified in this connections code, either because the
plant was designed to different standards or because of deterioration against design specification. In
order to continue to operate, the derogation must be sought and granted. For any equipment that met
the prevailing standards at the time of installation and still meets these standards the granting of the
derogation should be automatic. All other cases will be considered on a case by case basis.
4.1 If the existing power-generating facility owners have modified their power-generating facility to
such an extent that its connection agreement must be substantially revised in accordance with the
following procedure:
a) power-generating facility owners who intend to undertake the modernisation of a plant or
replacement of equipment impacting the technical capabilities of the power-generating
module shall notify their plans to the TSO in advance;
b) if the TSO considers that the extent of the modernisation or replacement of equipment is such
that a new connection agreement is required, the system operator shall notify the regulatory
authority and
GRID CODE PO-KO-005
CONNECTIONS CODE
ver.2.4 pages 8 from 32
c) the regulatory authority shall decide if the existing connection agreement needs to be revised
or a new connection agreement is required and which requirements of this Code shall apply;
4.2 If an existing transmission-connected demand facility, an existing distribution system, or an
existing transmission connected demand unit within a demand facility at a voltage level above 1kV, has
been modified to such an extent that its connection agreement must be substantially revised in
accordance with the following procedure:
a) demand facility owners, DSO, who intend to undertake the modernisation of a plant or
replacement of equipment impacting the technical capabilities of the transmission-connected
demand facility, the distribution system, or the demand unit shall notify their plans to the
TSO in advance;
b) if the TSO considers that the extent of the modernisation or replacement of equipment is such
that a new connection agreement is required, the system operator shall notify the regulatory
authority and
c) the regulatory authority shall decide if the existing connection agreement needs to be revised
or a new connection agreement is required and which requirements of this Code shall apply.
4.3 Regulatory authority decides to make an existing transmission-connected demand facility, an
existing transmission-connected distribution facility, existing distribution system, or an existing
demand unit subject to all or some of the requirements of this code following a proposal from the TSO
in accordance with paragraphs 4.5, 4.6 and 4.7
4.4 For the purposes of this Code, a transmission-connected demand facility, a transmission-
connected distribution facility, a distribution system, or a demand unit that is, or can be, used by a
demand facility to provide demand response services to DSO or to TSO, shall be considered as existing
if:
a) is already connected to the network until the date of entry into force of this Connection
Code amended in 2018; or
b) the demand facility owner, DSO has concluded a final and binding contract for the purchase
of the main demand equipment or the demand unit by two years after the expiry of the
transposition deadline. The demand facility owner, DSO must notify TSO of the conclusion
of the contract within 30 months after the date of entry into force of this Connection Code
amended in 2018;
c) The notification submitted by the demand facility owner or DSO, to the TSO shall at least
indicate the contract title, its date of signature and date of entry into force, and the
specifications of the main demand equipment or the demand unit to be constructed,
assembled or purchased;
d) The regulatory authority may determine whether the transmission-connected demand
facility, the transmission-connected distribution facility, the DSO, or the demand unit is to
be considered existing or new.
4.5 Following a public consultation and in order to address significant factual changes in
circumstances, such as the evolution of system requirements including penetration of renewable energy
sources, smart grids, distributed generation or demand response, the TSO may propose to the
regulatory authority to extend the application of this Code to existing transmission-connected demand
facilities, existing transmission-connected distribution facilities, existing distribution system, or existing
demand units used by a demand facility to provide demand response services to DSO or to TSO.
4.6 The regulatory authority shall decide on the extension of the applicability of this Code to existing
transmission-connected demand facilities, existing transmission-connected distribution facilities,
GRID CODE PO-KO-005
CONNECTIONS CODE
ver.2.4 pages 9 from 32
existing distribution system, or existing demand units, within six months of receipt of the report and the
recommendation of the TSO. The decision of the regulatory authority shall be published
4.7 The TSO shall take account of the legitimate expectations of demand facility owners or DSO as
part of the assessment of the application of this Code to existing transmission-connected demand
facilities, existing transmission-connected distribution facilities, existing distribution system, or existing
demand units
4.8 The TSO may assess the application of some or all of the provisions of this Code to existing
transmission-connected demand facilities, existing transmission-connected distribution facilities,
existing distribution system, or existing demand units, every three years in accordance with the
requirements and process set out in paragraphs 4.5 to 4.6
5 Connection Procedure
The TSO must offer to enter into a CA with various categories of Users with reference to the following:
a) new connection points;
b) existing connection points;
c) modifications at a connection points;
5.1.1.1 All users are subject to the same requirements for connection and by entering into a CA with
the TSO they must ensure that they abide by the rules, procedures, technical specifications and
equipment requirements as outlined in this connections code except if specifically varied by the relevant
CA.
5.1.2 CA Specific Conditions
5.1.2.1 The CA must contain the specific conditions that have been agreed to for connection and access
to the transmission network. Data and records exchanged must be part of the CA and, if applicable,
must include but are not limited to some or all of the following:
a) Details of the connection point (ownership, configuration, list of associated assets, associated
plant identification and nomenclature, fault levels, short circuit infeed’s, impedances,
switchgear ratings, nominal voltages, protection equipment type/fault clearance time/settings
of relays, inter-tripping schemes, special automatic features etc.);
b) Bus-bar protection schemes and settings;
c) System splitting or islanding schemes that impact on a power-generating facilities;
d) Frequency and voltage sensitive power-generating module protection settings;
e) Registered capacity and the power transfer capability of associated power-generating units;
f) The agreed authorised demand that may be supplied to the User;
g) Details of the metering groups, metering arrangements and adjustments for losses where the
actual metering equipment is not set in the Connection Point;
h) Details on requirements for CMTs, VMTs, contacts for protection, metering, interlocking etc;
i) Testing intervals for protection relay systems;
GRID CODE PO-KO-005
CONNECTIONS CODE
ver.2.4 pages 10 from 32
5.1.3.1 The design of connections between the transmission system and users shall be in accordance
with the principles set out in this connections code, subject to any modification agreed by the TSO.
5.1.3.2 During the ‘application for connection’ process the TSO will specify the voltage level to which a
user will be connected in accordance with its normal practice for the type of load to be supplied. The
TSO may specify a different connection voltage from normal in order to avoid potential disturbance
caused by the user's apparatus to other users of the transmission system or for other technical reasons
or may agree alternative methods for minimising the effects of disturbing loads.
5.1.3.3 If in the reasonable opinion of the TSO a connection would be more appropriately made to the
distribution system then the TSO shall refer the application with the reasons for their decision to the
DSO.
5.2.1 Timescales
Timescales set for review of Connection Application, are to be implemented as defined in Transmission
Connection Charging Methodology.
including the power transmission capability that the system interconnection facilities should provide. It
applies to both applicants for connection that need to be supplied with electric energy (demand facility
owners) or to applicants who wish to export the generated electric energy for sale (generation facility
owners). A DSO who requires a connection to the transmission system is a user.
5.2.2.2 During the initial phase the user will submit the standard planning data and the preliminary
project planning data as specified in the planning code. Although this data will be treated by the TSO as
confidential data it may be shared with other system operators if this is necessary to progress the
application.
5.2.2.3 Where the design or technical details submitted in the application to connect do not satisfy the
requirements specified by the TSO and are not in accordance with the provisions of this connections
code then the user must inform the TSO when submitting the application.
5.2.2.4 Prior to the formal application being submitted the user may have undertaken a feasibility study
with the TSO as outlined in the planning code. This is an optional exercise and the initial meeting will be
provided as a free service by the TSO. However if the user requests the TSO to carry out more detailed
or additional work then the TSO may make a reasonable charge in order to cover the costs of the work.
5.2.2.5 Data’s and information included in the connection application, TSO will treat as confidential
data’s and information, which should not be disclosed and not be given to a third party, except if TSO
may give details to another TSO, that according to its reasonable judgment is needed to do so for
purposes of performing studies for system planning. These data’s and information, can also be used to
allow TSO to assess the effects of proposed equipment on transmission system performance to assess
the level of any ancillary service that should be ensure for that connection point.
5.2.3.8 The connection offer may contain more than one option for connection to the transmission
system and/or at different levels of service and with different terms and conditions.
5.2.3.9 Both the TSO and the user are entitled to negotiate in respect of the provision of the connection
and any other matters relevant to the provision of the connection and if negotiations occur then such
negotiations must be conducted in good faith.
5.2.3.10 For complex connections due to the size, nature, location or timing of the proposal, the TSO
may decide that additional more extensive system studies are required in order to evaluate more fully
the impact of the proposed user development on the transmission system. Where the TSO judges that
such studies are necessary, the connection offer may indicate the areas that require more detailed
analysis. Before such additional studies are carried out, the user shall indicate whether it wishes the
TSO to undertake the work necessary to proceed to make a revised connection offer. In such case TSO
may recover the reasonable cost of these studies from the user.
6.1.1 The division of ownership between plant and apparatus of TSO and users shall be under the
technical boundary as specified in section 6.2, 6.3 and 6.4 of this code. The commercial boundary in all
cases will be the measuring point. The commercial boundaries between transmission system operator
and distribution system operators is assigned on the basis of Energy Regulatory Office Decision no.
V_403_2012.
6.1.2 The user’ will prepare a program that shows who is responsible for operation and maintenance
of plant and apparatus circuit breakers in the connection point. The TSO will prepare operational
schedule showing the boundaries of the property agreed. Both documents must be agreed by each
party. The TSO and the user will retain copies of these documents. Changes in the boundary
arrangements proposed by either party must be agreed in advance and will be recorded on the
appropriate operational diagrams after agreement by the regulator.
6.1.3 The electric power supply between the parties shall be, in principle, a three-phase voltage of a
value detailed in the CA of the connection point at a nominal frequency of 50Hz.
Technical boundary between TSO and Power generating facilities is connection point:
a) Between high voltage bus bar system and transformer bay of step up transformer;
GRID CODE PO-KO-005
CONNECTIONS CODE
ver.2.4 pages 13 from 32
b) In case where power generating facilities owner uses the transmission line for own expenses,
the technical boundary between the TSO and the power generating facility will be treated as
an transmission connected demand facilities (industrial customer) as set forth in the
Transmission Connection Charging Methodology.
The technical boundary between TSO and DSO is connection point of:
a) Transformer bay of power transformers 220/35/10(20) kV and 110/35/10(20) kV to bus bar 35
kV, 10(20) kV.
b) Self-consumption bay (35 kV, 10(20) kV) in bus bars of medium voltage 35 kV, 10(20) kV.
While bus bars, and MV feeders including measurement bays belong to DSO.
Is the end of the insulator chain linked to the end portal of transmission lines. In cases where the
industrial customer wants that except assets with defined boundary to transfer ownership of TSO's and
other assets then it will be defined in the Connection Agreement through a separate chapter within.
Above general rules should be followed, but for every case will depend on special conditions of the site,
disposal of facilities, type of user installation etc. However, in every case the connection point and the
commercial boundary will be described in the CA, and when needed, will be fully supported with
respective diagrams.
6.6.1 The user owns all the electrical equipment, plant and apparatus on the user side of the
connection point and is responsible for the safe operation and maintenance of those assets according to
Kosovan Laws, this grid code and CA.
6.6.2 The user’s assets at the connection point, the system interconnection facilities and the metering
and communication facilities and all associated plant and apparatus to which these rules relate, will be
listed in detail in the CA.
The TSO owns all the electrical equipment – plant and apparatus – on the transmission network side of
the connection point. The TSO will own, operate and maintain the HV substation at the connection point
and all other connection assets which may be required for connection to the transmission network,
according to the ‘Rule on General Condition of Energy Supply’, this grid code and the provisions of the
CA.
7 Connection Conditions
7.1.1 The connection conditions specify the minimum technical, design and operational criteria which
must be complied with by all users, connected to the transmission network and also the criteria with
which the TSO must comply in relation to the part of the transmission network at each connection
point.
7.1.2 All equipment at the ownership boundary shall meet the design principles contained within this
grid code. Connections for entry to and exit from the transmission network shall incorporate a means of
disconnection of the user's installation from the transmission network by the TSO.
GRID CODE PO-KO-005
CONNECTIONS CODE
ver.2.4 pages 14 from 32
7.1.3 The regulator can issue directions relieving the TSO or the users from compliance to the above
provisions. This will be specifically detailed in the relevant CA, under the schedule “specific connection
point derogations”. Any other special terms or conditions that apply to a specific connection point will
be also included in this appendix.
7.2.1.1 The TSO shall own and maintain the transmission network and shall operate it in accordance
with Operating security standards, their operating procedures and ENTSO-E requirements. This shall be
carried out in accordance with the Electrical Standards Code for the Kosovan power system, any other
relevant documents in use at the time for the planning, operation and security of the transmission
system, the grid code, all internal procedures of the TSO and the terms of all applicable Kosovan Laws.
7.2.1.2 The TSO shall ensure that the function of system operation is performed and that the
transmission system complies with the following technical, design and operational criteria at all
connection points.
7.2.4.2 If any of the above values are violated, then the TSO will investigate the cause of quality
deviations and identify appropriate measures to eliminate the deviations.
7.3.1.1 Each user shall operate and maintain the plant and apparatus in its site and design new
connected equipment or proposed modifications, in accordance with its statutory obligations under
licence, the technical parameters of the connection point set forth in the CA, the prevailing Kosovan
standards and procedures as referenced in the standard documents, good electricity industry practice
and the terms of all applicable Kosovan Laws.
7.3.1.2 The user shall comply with all the provisions of this grid code and the prevailing standards,
procedures and specifications for the security, planning, operation and maintenance of its site and the
system interconnection facilities. Power-Generating facility owners must operate and maintain each of
their power–generating facilities to ensure their sound technical operation in order to, as far as possible,
guarantee the safety of the working staff and comply with the environmental laws and quotas.
7.3.1.3 Each power generating facilities must have the performance requirements as detailed in
chapter 8 of this Code.
7.3.4.5 The principle applied is that all power lines shall be protected by at least one protection
designed for all types of faults. The normal arrangements at the different voltage levels are as follows:
a) for power lines of 400 kV two high speed main protections and one backup protection are
provided:
b) for power lines of 110 kV and 220 kV main and backup protections are provided. Backup
protection may be provided remotely;
7.3.4.6 The combination, type and functions of the relay protections shall be agreed between the user
and the TSO.
7.3.4.7 The fault clearance times for faults on a user’s equipment directly connected to the transmission
network, from fault inception to the circuit arc extinction shall not be greater than the following:
a) 90 ms at 400 kV;
b) 100 ms at 220 kV;
c) 140 ms at 110 kV;
7.3.4.8 In the event that the above fault clearance times are not met as a result of failure of the main
protection systems to operate, the users shall provide back-up protection. The TSO will also provide
back-up protection and these back-up protections will be co-ordinated so as to provide discrimination -
selectivity. Back-up protection shall operate to give a fault clearance time of no greater than 500 ms at
voltages of 110 kV and above. Back-up protection may include protection against outage of breaker.
7.3.4.9 In case of any fault in connection equipment that connects the user facilities to the TSO system,
the TSO and the user will ensure to each other the electrical signals that can be used for triggering of
disconnection of the adequate circuit breaker to insulate the fault.
7.3.4.10 Users should also be aware that the protection arrangements on some networks may cause
disconnection of one phase or two phases only of a three phase supply for certain types of fault.
7.3.4.11 No busbar protection, circuit-breaker fail protection relays, AC or DC wiring (other than power
supplies or dc tripping associated with the user's plant and apparatus) shall be worked upon or altered,
by or on behalf of, a user in the absence of a representative of, or written authority from the TSO.
a) External and internal short circuit (the fault levels and fault infeeds assumed at the time the
protection settings were specified);
b) Protection equipment type, fault clearance time, relay settings;
c) Differential protection setting for the generating modul/step up transformer unit/short
distance lines;
d) Power-generating unit protection setting
- Asymmetric load (negative phase sequence),
- Over-/undervoltage at the alternator terminals,
- Inter-area oscillations,
- Inrush current,
- Protection against inadmissible shaft torsions
- Overfluxing (U/f),
- Invers power
- Rate of change of frequency, and
- voltage displacement.
e) Frequency and voltage sensitive power-generating modul protection settings;
f) Unit Transformer protection
g) Busbar protection;
h) Demand circuit protection
i) Back-up against protection and switchgear malfunction.
j) Any site-specific special automatic facilities;
k) Operation and safety diagrams;
l) Site drawings
7.3.6.2 The power-generating facility owner shall organise its protection and control devices in
accordance with the following priority ranking (from highest to lowest):
a) network and power-generating modul protection
b) frequency control (active power adjustment);
c) power restriction; and
d) power gradient constraint;
7.3.6.3 With regard to priority ranking of protection and control, the transmission-connected demand
facility owner or the transmission-connected distribution system operator shall set the protection and
control devices of its transmission-connected demand facility or its transmission-connected
distribution system respectively, in compliance with the following priority ranking, organised in
decreasing order of importance:
a) transmission network protection;
b) transmission-connected demand facility or transmission-connected distribution system
protection;
GRID CODE PO-KO-005
CONNECTIONS CODE
ver.2.4 pages 18 from 32
1
PLC – Power Line Currier
GRID CODE PO-KO-005
CONNECTIONS CODE
ver.2.4 pages 19 from 32
7.3.11 Earthing
All transformers with star connection at the connection point (MV side) to be earthed through
resistance in accordance with specific standards IEC otherwise specified in CA.
7.3.14 Communications
7.3.14.1 Where required by the TSO in order to ensure the monitoring and control of the transmission
system communications between users and the TSO shall be established in accordance with the
relevant CA. These communications shall include some or all of the provisions detailed in the following:
a) Primary speech facility for transfer of communication (voice);
b) Backup or emergency speech facility using communication channels and power supplies
completely independent from the primary facility;
c) Facsimile machine;
d) RTU2 telemetry for system monitoring as per paragraph 7.3.13;
e) Transmission of data in electronic form;
f) Email;
g) Transfer of data from main and backup meter as required by the metering code;
7.3.14.2 The actual requirements in each particular case will be detailed in the CA.
2
RTU – Remote Terminal Unit
GRID CODE PO-KO-005
CONNECTIONS CODE
ver.2.4 pages 20 from 32
7.3.18 Access
A user shall grant to the TSO all necessary permanent rights of way within his own site that are required
for the construction, equipping, replacement, decommissioning, operation, testing, inspection and
maintenance of the system, interconnection facilities, in accordance with the prevailing current Kosovan
standards and procedures for HV system operation and maintenance.
Power-generating facility owners shall operate and maintain their power-generating modules voltage
control facilities, their power-generating modules frequency control facilities and the reactive power
control of the network interconnection facilities, in strict adherence to this code and instructions
received from the TSO for the operation and security of the transmission network.
a) a power generating module shall be capable of remaining connected to the network and
operate within the frequency ranges and time periods specified in Table 1;
b) the TSO and the power generating facility owner may agree on wider frequency ranges,
longer minimum times for operation or specific requirements for combined frequency and
GRID CODE PO-KO-005
CONNECTIONS CODE
ver.2.4 pages 21 from 32
voltage deviations to ensure the best use of the technical capabilities of a power generating
module, if it is required to preserve or to restore system security;
c) the power- generating facility owner shall not unreasonably withhold consent to apply wider
frequency ranges or longer minimum times for operation, taking account of their economic
and technical feasibility.
Table 1: This table shows the minimum time periods a power-generating modul has to be able to
operate for different frequencies deviating from a nominal value without disconnecting from the
network.
8.1.2.1 With regard to the rate of change of frequency withstand capability, a power- generating
module shall be capable of staying connected to the network and operate at rates of change of
frequency up to a value of -1.0 Hz/sec and +1.0 Hz/sec, other than triggered by rate-of-change-of-
frequency-type of loss of mains protection.
8.1.2.2 Power-generating modules shall fulfil the following requirements relating to frequency stability:
a) with regard to active power controllability and control range, the power-generating module
control system shall be capable of adjusting an active power setpoint in line with instructions
given to the power-generating facility owner by the TSO.
b) The TSO shall establish the period within which the adjusted active power setpoint must be
reached. The TSO shall specify a tolerance (subject to the availability of the prime mover
resource) applying to the new setpoint and the time within which it must be reached;
c) manual local measures shall be allowed in cases where the automatic remote control devices
are out of service.
d) The TSO shall notify the regulatory authority of the time required to reach the setpoint
together with the tolerance for the active power;
Figure 1.Active power frequency response capability of power-generating synchronous modules in LFSM-O. ΔΡ
is the change in active power output from the power-generating module. At over-frequencies where Δf is
above Δf1, the power-generating module has to provide a negative active power output change according to
the droop S2.
GRID CODE PO-KO-005
CONNECTIONS CODE
ver.2.4 pages 23 from 32
∆P/Pmax
2%
8.1.3.5 With regard to active power controllability and control range, the power-generating module
control system shall be capable of adjusting an active power set-point in line with instructions given to
the power-generating facility owner by the TSO.
8.1.3.6 The TSO shall establish the period within which the adjusted active power set-point must be
reached. The TSO shall specify a tolerance (subject to the availability of the prime mover resource)
applying to the new set-point and the time within which it must be reached;
8.1.3.7 Manual local measures shall be allowed in cases where the automatic remote control devices
are out of service. The TSO shall notify the regulatory authority of the time required to reach the
setpoint together with the tolerance for the active power;
8.1.3.8 With regard to limited frequency sensitive mode — under-frequency (LFSM-U) the following
requirements shall apply to power-generating modules:
a) the power-generating module shall be capable of activating the provision of active power
frequency response at a frequency threshold and with a droop specified by the TSO in
coordination with the TSOs of the same synchronous area as follows:
- the frequency threshold specified by the TSO shall be between 49,8 Hz and 49,5 Hz
inclusive,
- the droop settings specified by the TSO shall be in the range 2-12 %.
This is represented graphically in figure 3;
b) the actual delivery of active power frequency response in LFSM-U mode shall take into
account:
- ambient conditions when the response is to be triggered,
- the operating conditions of the power-generating module, in particular limitations on
operation near maximum capacity at low frequencies
- the availability of the primary energy sources.
c) the activation of active power frequency response by the power-generating modul shall not be
unduly delayed. In the event of any delay greater than two seconds, the power-generating
facility owner shall justify it to the TSO;
d) in LFSM-U mode the power-generating module shall be capable of providing a power increase
up to its maximum capacity;
e) stable operation of the power-generating module during LFSM-U operation shall be ensured;
GRID CODE PO-KO-005
CONNECTIONS CODE
ver.2.4 pages 24 from 32
Figure 3. Active power frequency response capability of power-generating synchronous units in LFSM-U. ΔΡ is
the change in active power output from the power-generating module. At under frequencies where Δf is
below Δf1, the power-generating module has to provide a positive active power output change according to
the droop s2.
8.1.4 Active Power Control
8.1.4.1 All synchronous gas turbines and hydro generating modules of capacity over 1 MW and thermal
generating modules of over 5 MW must be equipped with turbine speed and active power automatic
control systems.
8.1.4.2 The speed governor of each generating module must be capable of operating within the
generating modules technical limits and in a frequency range defined in paragraph 8.1.1.
8.1.4.3 The speed governor in co-ordination with other control devices must control the generating
module active power output with stability over the entire operating range of the generating module and
must be able to maintain the set active power of the generating module with accuracy as follows:
a) For units of up to 20 MW- not less than 2% of rated power;
b) For units above 20 MW - not less than 1% of rated power.
8.1.4.4 All generating modules with a registered capacity of at least 10 MW must have the capability to
provide secondary control, with the response timing and duration set out in the frequency control code
(within the balancing code).
8.1.4.5 Each generating module with a registered capacity of at least 10 MW must be fitted with
suitable equipment to receive LFC signals from TSO. The TSO will determine the selection and use of this
function to ensure the overall Kosovan power system meets the requirements of the ENTSO-E rules and
standards as set out under the frequency control code (within the balancing code).
8.1.4.6 The LFC system signalling criteria are as follows:
a) Accuracy 0.5 to 1.5% for active power measurement;
b) Accuracy 1.5 mHz for frequency measurement;
c) Regulation update time no more than two seconds;
d) Associated with the above the TSO SCADA/EMS system will continuously display the active
power output, higher and lower operating limits and run up/ run down rates.
GRID CODE PO-KO-005
CONNECTIONS CODE
ver.2.4 pages 25 from 32
8.1.4.7 All generating modules with a registered capacity of 20 MW or more must be capable of
providing primary load-frequency control respectively must operates in Frequency Sensitive Mode-
(FSM) while operating at all times unless relieved of this obligation by the TSO under the terms of a
derogation.
8.1.4.8 The power-generating module shall be capable of providing active power frequency response in
accordance with the parameters specified by the TSO within the ranges shown in table 2 and figure 4. In
specifying those parameters, the TSO shall take account of the following facts:
a) in case of overfrequency, the active power frequency response is limited by the minimum
regulating level,
b) in case of underfrequency, the active power frequency response is limited by maximum
capacity,
c) the actual delivery of active power frequency response depends on the operating and ambient
conditions of the power-generating modul when this response is triggered, in particular
limitations on operation near maximum capacity at low frequencies and available primary
energy sources;
Parameters Ranges
|∆𝑃1 |
Active power range related to maximum capacity 𝑃𝑚𝑎𝑥
1.5 - 10 %
|∆𝑓𝑖 | 10 - 30 mHz
Frequency response insensitivity |∆𝑓𝑖 | 0.02 - 0.06 %
𝑓𝑛
Frequency response deadband 0 - 500 mHz
Droop s1 2-12 %
GRID CODE PO-KO-005
CONNECTIONS CODE
ver.2.4 pages 26 from 32
s1
Figure 4. Active power frequency response capability of power-generating modules in FSM illustrating the case
of zero deadband and insensitivity. Pmax is the reference active power to which ∆𝑃 is related. ∆𝑃 is the change
in active power output from the power- generating modul. fn is the nominal frequency (50 Hz) in the network
and ∆𝑓 is the frequency deviation in the network.
d) The speed governor must be capable of being adjusted, on instruction by the TSO;
e) The frequency response deadband of frequency deviation and droop must be able to be
reselected repeatedly;
f) In the event of a frequency step change, the power- generating modul shall be capable of
activating full active power frequency response, at or above the full line shown in figure 5 in
accordance with the parameters specified by the TSO (which shall aim at avoiding active power
oscillations for the power- generating modul) within the ranges given in Table 3. The
combination of choice of the parameters specified by the TSO shall take possible technology-
dependent limitations into account;
g) The initial activation of active power frequency response required shall not be unduly delayed.
h) If the delay in initial activation of active power frequency response is greater than two
seconds, the power- generating facility owner shall provide technical evidence demonstrating
why a longer time is needed.
i) The power- generating modul shall be capable of providing full active power frequency
response for a period of 15 and 30 minutes as specified by the TSO. In specifying the period,
the TSO shall have regard to active power headroom and primary energy source of the power-
generating modul;
GRID CODE PO-KO-005
CONNECTIONS CODE
ver.2.4 pages 27 from 32
Table 3.Parameters for full activation of active power frequency response resulting from
frequency step change (explanation for Figure 4).
Parameters Values
j) with regard to frequency restoration control, the power-generating modul shall provide
functionalities complying with specifications specified by the TSO, aiming at restoring
frequency to its nominal value or maintaining power exchange flows between control areas at
their scheduled values;
k) with regard to disconnection due to underfrequency, power-generating facilities capable of
acting as a load, including hydro pump-storage power-generating facilities, shall be capable of
disconnecting their load in case of underfrequency. The requirement referred to in this point
does not extend to auxiliary supply;
l) with regard to real-time monitoring of Frequency Sensitive Mode (FSM):
- to monitor the operation of active power frequency response, the communication inter-
face shall be equipped to transfer in real time and in a secured manner from the power-
generating facility to the network control centre of the TSO, at the request of the TSO,
at least the following signals: status signal of FSM (on/off), scheduled active power out-
put, actual value of the active power output, actual parameter settings for active power
frequency response, droop and dead-band;
GRID CODE PO-KO-005
CONNECTIONS CODE
ver.2.4 pages 28 from 32
- the TSO shall specify additional signals to be provided by the power-generating facility
by monitoring and recording devices in order to verify the performance of the active
power frequency response provision of participating power-generating modules.
8.1.5.1 At the request of the TSO, the power-generating facility owner shall provide simulation models
which properly reflect the behaviour of the power-generating module in both steady-state and dynamic
simulations (50 Hz component) or in electromagnetic transient simulations.
8.1.5.2 The power-generating facility owner shall ensure that the models provided have been verified
against the results of compliance tests referred to in paragraph 8.5.7 and 8.5.8 and shall notify the
results of the verification to the TSO;
8.1.5.3 The models provided by the power-generating facility owner shall contain the following sub-
models, depending on the existence of the individual components:
a) alternator and prime mover,
b) speed and power control,
c) voltage control, including, if applicable, power system stabiliser (‘PSS’) function and excitation
control system,
d) power-generating module protection models, as agreed between the TSO and the power-
generating facility owner, and
e) converter models for power park modules;
8.1.5.4 The request by the TSO referred to in point a) shall include:
a) the PSS/E format or similar in which models are to be provided,
b) the provision of documentation on a model's structure and block diagrams,
c) an estimate of the minimum and maximum short circuit capacity at the connection point,
expressed in MVA, as an equivalent of the network;
8.1.5.5 The power-generating facility owner shall provide recordings of the power-generating modules
performance to the TSO if requested. The TSO may make such a request, in order to compare the
response of the models with those recordings;
8.1.6.1 All generating modules connected on 400 kV, 220 kV or 110 kV (through step up transformer)
with regard to voltage ranges shall fulfil the following requirements:
a) power- generating module shall be capable of staying connected to the network and
operating within the ranges of the network voltage at the connection point, expressed by the
voltage at the connection point related to the reference 1 pu voltage, and for the time periods
specified in Tables 4 and 5;
b) the TSO may specify shorter periods of time during which power- generating modules shall be
capable of remaining connected to the network in the event of simultaneous overvoltage and
under-frequency or simultaneous under-voltage and overfrequency;
GRID CODE PO-KO-005
CONNECTIONS CODE
ver.2.4 pages 29 from 32
Table 4.The minimum time periods within each generation module has to operate for voltages deviating
from the nominal value at the connection point without disconnecting from the network for 220 kV and 110
kV voltage level
Table 5.The minimum time periods within each generation module has to operate for voltages deviating
from the nominal value at the connection point without disconnecting from the network for 400 kV voltage
level
8.1.6.2 The supply generated must have balanced phase voltages with harmonic distortion of no greater
than 2%.
8.1.6.3 Each generating module and the power–generating facility in which is located that generating
modules must be capable of continuous uninterrupted operation during the occurrence of the following
factors:
a) Unbalanced load up to 10%;
b) Negative phase sequence current up to 5%.
8.1.6.4 All synchronous generating modules connected on 400 kV, 220 kV or 110 kV (through step up
transformer) with regard to Fault-ride-through capability shall fulfil the following requirements:
a) Power- generating module shall be capable of staying connected to the network and
continuing to operate stably after the power system has been disturbed by secured faults. That
capability shall be in accordance with a voltage-against-time profile at the connection point for
fault conditions specified by the TSO.
b) This voltage-against-time-profile shall be expressed by a lower limit of the course of the one of
the three phase-to-phase voltages on the network voltage level at the Connection Point which
sustains the lowest retained voltage during a symmetrical or asymmetrical fault, irrespective of
the voltage drop of the other two phase-to-phase voltages, as a function of time before, during
and after the fault. This lower limit illustrated by the red line is shown in figure 6 for
asynchronous generation modules and by the green line in figure 7 for power park modules.
c) TSO shall specify and make publicly available the pre-fault and post-fault conditions for the
fault-ride-through capability in terms of:
GRID CODE PO-KO-005
CONNECTIONS CODE
ver.2.4 pages 30 from 32
- the calculation of the pre-fault minimum short circuit capacity at the connection point;
- pre-fault active and reactive power operating point of the power- generating module at
the connection point and voltage at the connection point; and
- calculation of the post-fault minimum short circuit capacity at the connection point.
d) At the request of a power- generating facility owner, the TSO or DSO or (as the case may be)
shall provide the pre-fault and post-fault conditions to be considered for fault-ride-through
capability as an outcome of the calculations at the connection point as specified in point h)
regarding:
- pre-fault minimum short circuit capacity at each connection point expressed in MVA;
- pre-fault operating point of the power- generating module expressed in active power
output and reactive power output at the connection point and voltage at the
connection point; and
- post-fault minimum short circuit capacity at each connection point expressed in MVA
U/pu.
1.1
1.0
Urec2 = 0.9
0.8
Urec1 = 0.7
0.6
0.5
0.4
0.3
0.2
Uclear =0.25
0.1
Uret =0 tclear =0.15s trec1 =trec2 =0.45s trec3 =1.5s
0 0.15 0.3 0.45 0.6 0.75 0.9 1.05 1.2 1.35 1.5 1.65 1.8 1.9 2.0 2.1 t/s
The diagram represents the limit of a voltage-against-time profile of the voltage at the connection point,
expressed as the ratio of its actual value and its reference 1 pu value before, during and after a fault. Uret
is the retained voltage at the connection point during a fault, tclear is the instant when the fault has been
cleared. Urec1, Urec2, trec1, trec2 and trec3 specify certain points of lower limits of voltage recovery and
relevant times after fault clearance.
GRID CODE PO-KO-005
CONNECTIONS CODE
ver.2.4 pages 31 from 32
U/pu.
1.1
1.0
0.9
Urec1 =Urec2 =0.85
0.8
Urec1 = 0.7
0.6
0.5
0.4
0.3
0.2
0.1 tclear =0.15s
Uclear =Uret = 0 trec1 =trec2 =tclear =0.45s trec3 =1.5s
0 0.15 0.3 0.45 0.6 0.75 0.9 1.05 1.2 1.35 1.5 1.65 1.8 1.9 2.0 2.1 t/s
Power-generating facilities are responsible for protection of their generating modules against
asynchronous operation if generating modules become disconnected from the transmission system.
All power-generation modules eligible for central dispatch must be fitted with LFC (equipment for
secondary regulation). Specification for these will be as determined by the TSO.
8.1.9.1 For each power-generating module in CA will specified if required a black start capability. All
power-generating modules with a black start capability will be made available under the terms of an
ancillary services agreement, and meet the operational requirements set out in the contingency
planning code.
8.1.9.2 Power-generating module shall fulfil the following requirements relating to black start
capability:
a) power-generating facility owners shall, at the request of the TSO, provide a quotation for
providing black start capability. The TSO may make such a request if it considers system
security to be at risk due to a lack of black start capability in its control area;
b) a power-generating modul with black start capability shall be capable of starting from
shutdown without any external electrical energy supply within a time frame specified by the
TSO under the terms of an ancillary services agreement;
c) a power-generating modul with black start capability shall be able to synchronise within the
frequency limits laid down in table 1 (paragraph 8.1.1) and, where applicable, voltage limits
specified by the TSO or in tables 4 and 5 of paragraph 8.1.6.1;
GRID CODE PO-KO-005
CONNECTIONS CODE
ver.2.4 pages 32 from 32
8.2.1.1 With regard to reactive power capability, the TSO may specify supplementary reactive power to
be provided if the connection point of a synchronous power- generating module is neither located at the
high-voltage terminals of the step-up transformer to the voltage level of the connection point nor at the
alternator terminals, if no step-up transformer exists. This supplementary reactive power shall
compensate the reactive power demand of the high-voltage line or cable between the high-voltage
terminals of the step-up transformer of the synchronous power- generating module or its alternator
terminals, if no step-up transformer exists, and the connection point and shall be provided by the
responsible owner of that line or cable.
8.2.1.2 The U-Q/Pmax-profile, within the boundary of which Synchronous Power Generating modul shall
be capable of providing Reactive Power at its Maximum Capacity is shown in Figure 8.
8.2.1.3 The synchronous power- generating module shall be capable of moving to any operating point
within its U-Q/Pmax profile in appropriate timescales to target values requested by the TSO in a range
between 10 seconds and 1 minute.
8.2.1.4 With regard to reactive power capability below maximum capacity, when operating at an active
power output below the maximum capacity (P<Pmax), the synchronous power- generating modules shall
be capable of operating at every possible operating point in the P-Q-capability diagram of the alternator
of that synchronous power- generating module, at least down to minimum stable operating level. Even
at reduced active power output, reactive power supply at the connection point shall correspond fully to
the P-Q-capability diagram of the alternator of that synchronous power- generating module, taking the
auxiliary supply power and the active and reactive power losses of the step-up transformer, if
applicable, into account.
V/pu
1.10
1.05
1.00
0.95
0.90
Consumption Production
(lead) (lag) Q/Pmax
0.00
-0.33
0.33
0.41
Figure 8: U-Q/Pmax-profile of a synchronous power- generating module. The diagram represents boundaries of
a U-Q/Pmax-profile by the voltage at the connection point, expressed by the ratio of its actual value and it’s the
reference 1 pu value, against the ratio of the reactive power (Q) and the maximum capacity (Pmax).
GRID CODE PO-KO-005
CONNECTIONS CODE
ver.2.4 pages 34 from 32
8.2.2.1 Each generating module must be capable of contributing to voltage control by continuous
modulation of reactive power supplied to the transmission network.
8.2.2.2 All generating modules connected in transmission network, must be fitted with a continuously
acting automatic voltage regulator (AVR) that may include stabilisers, to provide constant terminal
voltage of the generating module, without instability over the entire operating range of the generating
module. If required by the CA, will incorporate PSS (power stabilizer system) to attenuate power
oscillations. Automatic Voltage Regulator (AVR) should compensate for any voltage decreases across a
step up transformer of the generating module and also to provide a stable reactive power distribution
between the synchronous generating module and network.
8.2.2.3 Automatic Voltage Regulator shall be capable of maintaining the voltage at the generating
module terminals with an accuracy as follows:
a) for generating modules of up to 25 MVA – not less than 1% of rated voltage;
b) for generating modules above 25 MVA - not less than 0.5% of rated voltage
8.2.2.4 The excitation system must provide for increase (forcing) in the excitation current and voltage of
a synchronous generating module as a factor at nominal load as follows:
a) hydro generating modules up to 25 MVA - min factor (ratio) 1.5 - min time 10 s;
b) hydro generating modules above 25 MVA - min factor 1.8 - min time 10 s;
c) thermal generating modules of up to 25 MVA - min factor 1.8 - min time 10 s;
d) thermal generating modules above 25 MVA - min factor 2.0 - min time 10 s.
8.2.2.5 The forcing parameters must be achieved at a generating module terminal voltage within the
range of 90% to 110% of the nominal voltage and at a frequency range of 47.5 Hz to 51.5 Hz.
8.2.2.6 The speed of change in the voltage of the synchronous generating module shall not be lower
than 2 relative units/sec using as reference the exciting voltage under nominal load of the synchronous
generating module.
a) bandwidth limitation of the output signal to ensure that the highest frequency of response
cannot excite torsional oscillations on other power-generating modules connected to the
network;
b) an under-excitation limiter to prevent the AVR from reducing the alternator excitation to a
level which would endanger synchronous stability;
c) an over-excitation limiter to ensure that the alternator excitation is not limited to less than the
maximum value that can be achieved whilst ensuring that the synchronous power-generating
module is operating within its design limits;
d) a stator current limiter; and
e) a PSS function to attenuate power oscillations, if the synchronous power-generating module
size is above a value of maximum capacity specified by the TSO.
GRID CODE PO-KO-005
CONNECTIONS CODE
ver.2.4 pages 35 from 32
8.2.2.8 The excitation systems of generating modules involved in the restoration of the transmission
network after severe system incidents, shall be able to regulate the excitation of the generating module
in the absence of an external ac supply.
8.2.2.9 The TSO and the power-generating facility owner shall enter into an agreement regarding
technical capabilities of the power-generating module to aid angular stability under fault conditions.
8.3.1 Power park modules with capacity ≥5 MW shall fulfil the requirements listed in paragraph 8.1.
8.3.1.1 For power park modules with capacity ≥5 MW the TSO or the DSO (as the case may be) in
coordination with the TSO shall have the right to specify that a power park module be capable of
providing fast fault current at the connection point in case of symmetrical (3-phase) faults, under the
following conditions:
a) The power park module shall be capable of activating the supply of fast fault current either by:
- ensuring the supply of the fast fault current at the connection point, or
- measuring voltage deviations at the terminals of the individual units of the power park
module and providing a fast fault current at the terminals of these units;
b) the TSO or the DSO (as the case may be) in coordination with the TSO shall specify:
- how and when a voltage deviation is to be determined as well as the end of the voltage
deviation,
- the characteristics of the fast fault current, including the time domain for measuring the
voltage deviation and fast fault current,
- the timing and accuracy of the fast fault current, which may include several stages
during a fault and after its clearance;
8.3.1.2 With regard to the supply of fast fault current in case of asymmetrical (1-phase or 2-phase)
faults, the TSO or the DSO (as the case may be) in coordination with the TSO shall have the right to
specify a requirement for asymmetrical current injection.
8.3.1.3 Power park modules with capacity ≥5 MW shall fulfil the following additional requirements in
relation to robustness:
a) the TSO shall specify the post-fault active power recovery that the power park module is
capable of providing and shall specify:
- when the post-fault active power recovery begins, based on a voltage criterion;
- a maximum allowed time for active power recovery; and
- a magnitude and accuracy for active power recovery;
b) the specifications shall be in accordance with the following principles:
- interdependency between fast fault current requirements according to paragraph
8.3.1.1 and paragraph 8.3.1.2 and active power recovery;
- dependence between active power recovery times and duration of voltage deviations;
- a specified limit of the maximum allowed time for active power recovery;
GRID CODE PO-KO-005
CONNECTIONS CODE
ver.2.4 pages 36 from 32
- (adequacy between the level of voltage recovery and the minimum magnitude for active
power recovery; and
- adequate damping of active power oscillations.
8.3.1.4 Power park modules with capacity ≥5 MW shall fulfil the following additional requirements in
relation to frequency stability:
a) the TSO shall have the right to specify that power park modules be capable of providing
synthetic inertia during very fast frequency deviations;
b) the operating principle of control systems installed to provide synthetic inertia and the
associated performance parameters shall be specified by the TSO.
8.3.1.5 Power park modules with capacity ≥5 MW shall fulfil the following additional requirements in
relation to voltage stability:
a) with regard to reactive power capability, the TSO or the DSO (as the case may be) may specify
supplementary reactive power to be provided if the connection point of a power park module
is neither located at the high-voltage terminals of the step-up transformer to the voltage level
of the connection point nor at the convertor terminals, if no step-up transformer exists. This
supplementary reactive power shall compensate the reactive power demand of the high-
voltage line or cable between the high-voltage terminals of the step-up transformer of the
power park module or its convertor terminals, if no step-up transformer exists, and the
connection point and shall be provided by the responsible owner of that line or cable.
b) with regard to reactive power capability at maximum capacity:
- the TSO or the DSO (as the case may be) in coordination with the TSO shall specify the
reactive power provision capability requirements in the context of varying voltage. To
that end, it shall specify a U-Q/Pmax-profile that may take any shape within the
boundaries of which the power park module shall be capable of providing reactive
power at its maximum capacity;
c) with regard to reactive power capability, the TSO or the DSO (as the case may be) in
coordination with the TSO shall have the right to specify the capability of a power park module
with capacity ≥5MW to provide reactive power. The U-Q/Pmax-profile within the boundary of
which the Power Park Modules shall be capable of providing Reactive Power at its Maximum
Capacity is shown in Figure 9:
GRID CODE PO-KO-005
CONNECTIONS CODE
ver.2.4 pages 37 from 32
V/pu
1.05
1.10
1.00
0.90
0.85
-0.33 Q/Pmax
0.00
0.33
0.41
Consumption (lead) Production (lag)
Figure 9: U-Q/Pmax-profile of a Power Park module with capacity ≥5MW. The diagram represents
boundaries of a U-Q/Pmax-profile by the voltage at the connection point, expressed by the ratio of its
actual value and it’s the reference 1 pu value, against the ratio of the reactive power (Q) and the
maximum capacity (Pmax).
- The reactive power provision capability requirement applies at the connection point.
d) With regard to reactive power capability below maximum capacity:
- With regard to reactive power capability below maximum capacity (P<Pmax), the P-
Q/Pmax-profile at the connection point, within the boundary of which Power Park
Modules shall be capable of providing reactive power to a ratio of P/Pmax of 0.1 pu.
- Below a ratio of P/Pmax of 0.1 pu, reactive power capability is not required. when
operating at an active power output below maximum capacity (P<Pmax), the power park
module shall be capable of providing reactive power at any operating point inside its P-
Q/Pmax-profile illustrated in Figure 10, if all units of that power park module which
generate power are technically available that is to say they are not out of service due to
maintenance or failure, otherwise there may be less reactive power capability, taking
into consideration the technical availabilities;
- the power park module shall be capable of moving to any operating point within its P-
Q/Pmax profile in appropriate timescales to target values requested by the TSO or the
DSO (as the case may be) in a range of 10 seconds to 1 minute.
GRID CODE PO-KO-005
CONNECTIONS CODE
ver.2.4 pages 38 from 32
P/pu
1.00
0.90
0.80
0.70
0.60
0.50
0.40
0.30
0.20
0.10
Q/Pmax
-0.33
0.00
0.33
0.41
Figure 10: P-Q/Pmax-profile of a power park module with capacity ≥5MW. The diagram represents
boundaries of a P-Q/Pmax-profile at the connection point by the active power, expressed by the ratio of its
actual value and the maximum capacity pu, against the ratio of the reactive power (Q) and the maximum
capacity (Pmax).
no greater than 5 % of the maximum reactive power. The TSO or the DSO (as the case
may be) shall specify the time specifications;
- for the purpose of reactive power control mode, the power park module shall be
capable of setting the reactive power setpoint anywhere in the reactive power range,
specified by points (a) and (b) of paragraph 8.3.1.5, with setting steps no greater than 5
MVAr or 5 % (whichever is smaller) of full reactive power, controlling the reactive power
at the connection point to an accuracy within plus or minus 5 MVAr or plus or minus 5 %
(whichever is smaller) of the full reactive power;
- for the purpose of power factor control mode, the power park module shall be capable
of controlling the power factor at the connection point within the required reactive
power range, specified by the TSO or the DSO (as the case may be) according to points
(a) and (b) of paragraph 8.3.1.5, with a target power factor in steps no greater than
0.01. The TSO or the DSO (as the case may be) shall specify the target power factor
value, its tolerance and the period of time to achieve the target power factor following a
sudden change of active power output. The tolerance of the target power factor shall be
expressed through the tolerance of its corresponding reactive power. This reactive
power tolerance shall be expressed by either an absolute value or by a percentage of
the maximum reactive power of the power park module;
- the TSO or the DSO (as the case may be), in coordination with the TSO and with the
power park module owner, shall specify which of the above three reactive power
control mode options and associated setpoints is to apply, and what further equipment
is needed to make the adjustment of the relevant setpoint operable remotely;
f) with regard to prioritising active or reactive power contribution, the TSO shall specify whether
active power contribution or reactive power contribution has priority during faults for which
fault-ride-through capability is required. If priority is given to active power contribution, this
provision has to be established no later than 150 ms from the fault inception;
g) with regard to power oscillations damping control, if specified by the TSO a power park
module shall be capable of contributing to damping power oscillations. The voltage and
reactive power control characteristics of power park modules must not adversely affect the
damping of power oscillations.
8.4.1.1 The power-generating facility owner connected in transmission network shall demonstrate to
the TSO that it has complied with the requirements set out in this Code by completing successfully the
operational notification procedure for connection of each power-generating module described in
paragraphs 8.4.2 to 8.4.6.
8.4.1.2 The TSO be shall clarify and make publicly available the details of the operational notification
procedure.
8.4.2 Procedure for power-generating modules connected in transmission network
8.4.2.1 The operational notification procedure for connection of each new power-generating module in
the transmission network shall comprise:
a) energisation operational notification (‘EON’);
GRID CODE PO-KO-005
CONNECTIONS CODE
ver.2.4 pages 40 from 32
8.4.3.1 An EON shall entitle the power-generating facility owner to energise its internal network and
auxiliaries for the power-generating modules by using the grid connection that is specified for the
connection point.
8.4.3.2 An EON shall be issued by the TSO, subject to completion of preparations including agreement
on the protection and control settings relevant to the connection point between the TSO and the
power-generating facility owner.
8.4.4 Interim operational notification
8.4.4.1 An ION shall entitle the power-generating facility owner to operate the power-generating
module and generate power by using the grid connection for a limited period of time.
8.4.4.2 An ION shall be issued by the TSO, subject to completion of the data and study review process
as required by paragraph 8.4.4.3
8.4.4.3 With regard to the data and study review, the TSO shall have the right to request that the
power-generating facility owner provide the following:
a) itemised statement of compliance;
b) detailed technical data on the power-generating module of relevance to the network
connection as specified by the TSO;
c) equipment certificates issued by an authorised certifier in respect of power-generating
modules, where they are relied upon as part of the evidence of compliance;
d) simulation models, as specified by paragraph 8.1.5 and required by the TSO;
e) studies demonstrating the expected steady-state and dynamic performance as required by
paragraph 8.5.7 and 8.5.8;
f) details of intended compliance tests in accordance with paragraph 8.5.5 and 8.5.6.
8.4.4.4 The maximum period during which the power-generating facility owner may maintain ION
status shall be 24 months. The TSO is entitled to specify a shorter ION validity period. An extension of
the ION shall be granted only if the power-generating facility owner has made substantial progress
towards full compliance. Outstanding issues shall be clearly identified at the time of requesting
extension.
8.4.4.5 An extension of the period during which the power-generating facility owner may maintain
ION status, beyond the period established in paragraph 8.4.4.4, may be granted if a request for a
derogation is made to the TSO before the expiry of that period in accordance with the derogation
procedure laid down in chapter 10 of this code.
8.4.5.1 A FON shall entitle the power-generating facility owner to operate a power-generating modul
by using the grid connection.
GRID CODE PO-KO-005
CONNECTIONS CODE
ver.2.4 pages 41 from 32
8.4.5.2 A FON shall be issued by the TSO, upon prior removal of all incompatibilities identified for the
purpose of ION status and subject to completion of the data and study review process as required by
paragraph 8.4.5.3
8.4.5.3 For the purposes of the data and study review, the power-generating facility owner must submit
the following to the TSO:
a) an itemised statement of compliance; and
b) an update of applicable technical data, simulation models and studies as referred to in
points (b), (d) and (e) of paragraph 8.4.4.3, including the use of actual measured values
during testing.
8.4.5.4 If incompatibility is identified in connection with the issuing of the FON, a derogation may be
granted upon a request made to the TSO, in accordance with the derogation procedure described in
chapter 10 of this code. A FON shall be issued by the TSO if the power-generating module complies
with the provisions of the derogation.
8.4.5.5 Where a request for a derogation is rejected, the TSO shall have the right to refuse to allow the
operation of the power-generating module until the power-generating facility owner and the TSO
resolve the incompatibility and the TSO considers that the power-generating module complies with the
provisions of this Code.
8.4.5.6 If the TSO and the power-generating facility owner do not resolve the incompatibility within a
reasonable time frame, but in any case not later than six months after the notification of the rejection of
the request for a derogation, each party may refer the issue for decision to the regulatory authority.
8.4.6.1 Power-generating facility owners to whom a FON has been granted shall inform the TSO
immediately in the following circumstances:
a) the facility is temporarily subject to either significant modification or loss of capability affecting
its performance; or
b) Equipment failure leading to non-compliance with some relevant requirements.
8.4.6.2 The power-generating facility owner shall apply to the TSO for a LON, if the power-generating
facility owner reasonably expects the circumstances described in paragraph 8.4.6.1 to persist for more
than three months.
8.4.6.3 A LON shall be issued by the TSO and shall contain the following information which shall be
clearly identifiable:
a) the unresolved issues justifying the granting of the LON;
b) the responsibilities and timescales for the expected solution; and
c) a maximum period of validity which shall not exceed 12 months. The initial period granted may
be shorter with the possibility of an extension if evidence is submitted to the satisfaction of
the TSO demonstrating that substantial progress has been made towards achieving full
compliance.
8.4.6.4 The FON shall be suspended during the period of validity of the LON with regard to the items for
which the LON has been issued.
8.4.6.5 A further extension of the period of validity of the LON may be granted upon a request for a
derogation made to the TSO before the expiry of that period, in accordance with the derogation
procedure described in chapter 10 of this code.
GRID CODE PO-KO-005
CONNECTIONS CODE
ver.2.4 pages 42 from 32
8.4.6.6 The TSO shall have the right to refuse to allow the operation of the power-generating module,
once the LON is no longer valid. In such cases, the FON shall automatically become invalid.
8.4.6.7 If the TSO does not grant an extension of the period of validity of the LON in accordance with
paragraph 8.4.6.5 or if it refuses to allow the operation of the power-generating module once the LON is
no longer valid in accordance with paragraph 8.4.6.6 the power-generating facility owner may refer the
issue for decision to the regulatory authority within six months after the notification of the decision of
the TSO.
8.5.1.1 The power-generating facility owner shall ensure that each power-generating module complies
with the requirements applicable under this Code throughout the lifetime of the facility
8.5.1.2 The power-generating facility owner shall notify to the TSO any planned modification of the
technical capabilities of a power-generating module which may affect its compliance with the
requirements applicable under this Code, before initiating that modification.
8.5.1.3 The power-generating facility owner shall notify the system operator of any operational
incidents or failures of a power-generating module that affect its compliance with the requirements of
this Code, without undue delay, after the occurrence of those incidents.
8.5.1.4 The power-generating facility owner shall notify the TSO of the planned test schedules and
procedures to be followed for verifying the compliance of a power-generating module with the
requirements of this Code, in due time and prior to their launch. The TSO shall approve in advance the
planned test schedules and procedures. Such approval by the TSO shall be provided in a timely manner
and shall not be unreasonably withheld.
8.5.1.5 The TSO may participate in such tests and record the performance of the power-generating
module.
8.5.2.1 The TSO shall assess the compliance of a power-generating module with the requirements
applicable under this Code, throughout the lifetime of the power-generating facility. The power-
generating facility owner shall be informed of the outcome of this assessment.
8.5.2.2 The TSO shall have the right to request that the power-generating facility owner carry out
compliance tests and simulations according to a repeat plan or general scheme or after any failure,
modification or replacement of any equipment that may have an impact on the power-generating
modules compliance with the requirements of this Code.
8.5.2.3 The power-generating facility owner shall be informed of the outcome of those compliance
tests and simulations.
8.5.2.4 The TSO shall make publicly available a list of information and documents to be provided as well
as the requirements to be fulfilled by the power-generating facility owner within the framework of the
compliance process. The list shall cover at least the following information, documents and
requirements:
a) all the documentation and certificates to be provided by the power-generating facility owner;
b) details of the technical data on the power-generating module of relevance to the grid connec-
tion;
GRID CODE PO-KO-005
CONNECTIONS CODE
ver.2.4 pages 43 from 32
c) require the power-generating facility owner to carry out appropriate tests in order to demon-
strate a power-generating module's performance when operating on alternative fuels or fuel
mixes. The TSO and the power-generating facility owner shall agree on which types of fuel are
to be tested.
8.5.3.3 The power-generating facility owner is responsible for carrying out the tests in accordance with
the conditions laid down in paragraph 8.5.5. and 8.5.6. The TSO shall cooperate and not unduly delay
the performance of the tests.
8.5.3.4 The TSO may participate in the compliance testing either on site or remotely from the system
operator's control centre. For that purpose, the power-generating facility owner shall provide the
monitoring equipment necessary to record all relevant test signals and measurements as well as ensure
that the necessary representatives of the power-generating facility owner are available on site for the
entire testing period. Signals specified by the TSO shall be provided if, for selected tests, the system
operator wishes to use its own equipment to record performance. The TSO has sole discretion to decide
about its participation.
8.5.3.5 The TSO may attach test equipment or monitoring equipment to plant of the power-generating
facility owner or request the latter to attach such test equipment. In carrying out monitoring the TSO
must not cause the performance of the monitored plant to be constrained in any way.
8.5.3.6 Each power-generating facility owner must co-operate with the TSO in testing the operation of
equipment forming part of the protection system relating to a connection point at which that power-
generating facility is connected to the transmission system and the TSO must conduct these tests as
follows:
a) Prior to the plant at the relevant connection point being placed in service;
b) At intervals specified in the connection agreement;
c) If the TSO assumes that the defense system is not in compliance with the requirements of the
Grid Code or CA.
8.5.4.4 The TSO shall have the right to check that a power-generating module complies with the
requirements of this Code by carrying out its own compliance simulations based on the provided
simulation reports, simulation models and compliance test measurements.
8.5.4.5 The TSO shall provide the power-generating facility owner with technical data and a simulation
model of the network, to the extent necessary to carry out the requested simulations in accordance
with paragraph 8.1.5.
8.5.5.1 Power-generating facility owners shall undertake the compliance tests set out in paragraphs
8.5.5.2, 8.5.5.3, 8.5.5.4 and 8.5.5.6 in relation to synchronous power-generating modules. Where a
power-generating module provides black start capability, power-generating facility owners shall also
undertake the tests referred to in 8.5.5.5. Instead of the relevant test, the power-generating facility
owner may use equipment certificates issued by an authorised certifier to demonstrate compliance with
the relevant requirement. In that case, the equipment certificates shall be provided to the TSO.
8.5.5.2 The following requirements with regard to the LFSM-U response test shall apply:
a) it shall demonstrate that the power-generating module is technically capable of continuously
modulating active power at operating points below maximum capacity to contribute to fre-
quency control in case of a large frequency drop in the system;
b) the test shall be carried out by simulating appropriate active power load points, with low fre-
quency steps and ramps big enough to trigger active power change of at least 10 % of maxi-
mum capacity, taking into account the droop settings and the deadband. If required, simulated
frequency deviation signals shall be injected simultaneously into both the speed governor and
the load controller references;
c) the test shall be deemed successful if the following conditions are fulfilled:
- the test results, for both dynamic and static parameters, comply with a paragraph
8.1.3.8; and
- un-damped oscillations do not occur after the step change response.
8.5.5.3 The following requirements with regard to the FSM response test shall apply:
a) it shall demonstrate that the power-generating module is technically capable of continuously
modulating active power over the full operating range between maximum capacity and mini-
mum regulating level to contribute to frequency control. The steady-state parameters of regu-
lations, such as droop and deadband and dynamic parameters, including robustness through
frequency step change response and large, fast frequency deviations shall be verified;
b) the test shall be carried out by simulating frequency steps and ramps big enough to trigger the
whole active power frequency response range, taking into account the settings of droop and
deadband, as well as the capability to actually increase or decrease active power output from
the respective operating point. If required, simulated frequency deviation signals shall be in-
jected simultaneously into the references of both the speed governor and the load controller
of the unit or plant control system;
c) the test shall be deemed successful if the following conditions are fulfilled:
- the activation time of full active power frequency response range as a result of a fre-
quency step change is no longer than required by paragraph 8.1.4.7;
- undamped oscillations do not occur after the step change response;
- the initial delay time complies with paragraph 8.1.4.7;
- the droop settings are available within the range specified in paragraph 8.1.4.7 and the
GRID CODE PO-KO-005
CONNECTIONS CODE
ver.2.4 pages 46 from 32
deadband (threshold) is not higher than the value specified in that paragraph; and
- the insensitivity of active power frequency response at any relevant operating point
does not exceed the requirements set out in paragraph 8.1.4.7.
8.5.5.4 With regard to the frequency restoration control test the following requirements shall apply:
a) the power-generating modules technical capability to participate in frequency restoration
control shall be demonstrated and the cooperation of FSM and frequency restoration control
shall be checked;
b) the test shall be deemed successful if the results, for both dynamic and static parameters,
comply with the requirements of paragraph 8.1.4.8 point (k).
8.5.5.5 With regard to the black start capability test the following requirements shall apply:
a) for power-generating module with black start capability, this technical capability to start from
shut down without any external electrical energy supply shall be demonstrated;
b) the test shall be deemed successful if the start-up time is kept within the time frame set out in
point b) of paragraph 8.1.9.2.
8.5.5.6 With regard to the tripping to houseload test the following requirements shall apply:
a) the power-generating modules technical capability to trip to and stably operate on house load
shall be demonstrated;
b) the test shall be carried out at the maximum capacity and nominal reactive power of the pow-
er-generating module before load shedding;
c) the TSO shall have the right to set additional conditions, taking into account paragraph 8.1.9.4
d) the test shall be deemed successful if tripping to house load is successful, stable houseload op-
eration has been demonstrated in the time period set out in paragraph 8.1.9.4; and re-
synchronisation to the network has been performed successfully.
8.5.5.7 With regard to the reactive power capability test the following requirements shall apply:
a) the power-generating module's technical capability to provide leading and lagging reactive
power capability in accordance with paragraphs 8.2.1.2 and 8.2.1.4 shall be demonstrated;
b) the test shall be deemed successful if the following conditions are fulfilled:
- the power-generating module operates at maximum reactive power for at least one
hour, both leading and lagging, at minimum stable operating level, at maximum capacity
and an active power operating point between those maximum and minimum levels;
- the power-generating modules capability to change to any reactive power target value
within the agreed or decided reactive power range shall be demonstrated.
8.5.5.8 Instead of the relevant test, the power-generating facility owner may use equipment certificates
issued by an authorised certifier to demonstrate compliance with the relevant requirement. In such a
case, the equipment certificates shall be provided to the TSO.
8.5.6 Compliance testing for power park modules connected in transmission network
8.5.6.1 Power-generating facility owners shall undertake LFSM-O response compliance tests in relation
to power park modules. Instead of the relevant test, the power-generating facility owner may use
equipment certificates issued by an authorised certifier to demonstrate compliance with the relevant
requirement. In that case, the equipment certificates shall be provided to the TSO.
GRID CODE PO-KO-005
CONNECTIONS CODE
ver.2.4 pages 47 from 32
8.5.6.2 The LFSM-O response tests shall reflect the choice of control scheme selected by the TSO.
8.5.6.3 With regard to the LFSM-O response tests the following requirements shall apply:
a) the power park module's technical capability to continuously modulate active power to
contribute to frequency control in case of increase of frequency in the system shall be
demonstrated. The steady-state parameters of regulations, such as droop and deadband, and
dynamic parameters shall be verified;
b) the test shall be carried out by simulating frequency steps and ramps big enough to trigger at
least 10 % of maximum capacity change in active power, taking into account the droop settings
and the deadband. To perform this test simulated frequency deviation signals shall be injected
simultaneously into the control system references;
c) the test shall be deemed successful in the event that the test results, for both dynamic and
static parameters, comply with the requirements set out in paragraph 8.1.3.1.
8.5.6.4 With regard to the active power controllability and control range test the following
requirements shall apply:
a) the power park module's technical capability to operate at a load level below the setpoint set
by the by the TSO shall be demonstrated;
b) the test shall be deemed successful if the following conditions are fulfilled:
- the load level of the power park module is kept below the setpoint;
- the setpoint is implemented according to the requirements laid down in paragraph
8.1.2.2 point (a); and
- the accuracy of the regulation complies with the value that will specified according
paragraph 8.1.2.2 point (b).
8.5.6.5 With regard to the LFSM-U response test the following requirements shall apply:
a) the power park module's technical capability to continuously modulate active power to
contribute to frequency control in case of a large frequency drop in the system shall be
demonstrated;
b) the test shall be carried out by simulating the frequency steps and ramps big enough to
trigger at least 10 % of maximum capacity active power change with a starting point of no
more than 80 % of maximum capacity, taking into account the droop settings and the
deadband;
c) the test shall be deemed successful if the following conditions are fulfilled:
d) the test results, for both dynamic and static parameters, comply with the requirements laid
down in paragraph 8.1.2.2 point (c); and
e) undamped oscillations do not occur after the step change response.
8.5.6.6 With regard to the FSM response test the following requirements shall apply:
a) the power park module's technical capability to continuously modulate active power over the
full operating range between maximum capacity and minimum regulating level to contribute
to frequency control shall be demonstrated. The steady-state parameters of regulations, such
as insensitivity, droop, deadband and range of regulation, as well as dynamic parameters,
including frequency step change response shall be verified;
GRID CODE PO-KO-005
CONNECTIONS CODE
ver.2.4 pages 48 from 32
b) the test shall be carried out by simulating frequency steps and ramps big enough to trigger the
whole active power frequency response range, taking into account the droop settings and the
deadband. Simulated frequency deviation signals shall be injected to perform the test;
c) the test shall be deemed successful if the following conditions are fulfilled:
- the activation time of the full active power frequency response range as a result of a
frequency step change is no longer than that required by paragraph 8.1.4.7;
- undamped oscillations do not occur after the step change response;
- the initial delay is in line with paragraph 8.1.4.7;
- the droop settings are available within the ranges specified in paragraph 8.1.4.7 and the
deadband (threshold) is not higher than the value chosen by the TSO; and
- the insensitivity of active power frequency response does not exceed the requirement
set out in paragraph 8.1.4.7.
d) With regard to the frequency restoration control test the following requirements shall apply:
- the power park module's technical capability to participate in frequency restoration
control shall be demonstrated. The cooperation of both FSM and frequency restoration
control shall be checked;
- the test shall be deemed successful if the results for both dynamic and static parameters
comply with the requirements of point (k) of paragraph 8.1.4.8.
8.5.6.7 With regard to the reactive power capability test the following requirements shall apply:
a) the power park module's technical capability to provide leading and lagging reactive power
capability in accordance with points (b) and (d) of paragraph 8.3.1.5 shall be demonstrated;
b) it shall be carried out at maximum reactive power, both leading and lagging, and shall verify
the following parameters:
- operation in excess of 60 % of maximum capacity for 30 min;
- operation within the range of 30-50 % of maximum capacity for 30 min; and
- operation within the range of 10-20 % of maximum capacity for 60 min;
c) the test shall be deemed successful if the following criteria are fulfilled:
d) the power park module operates for a duration no shorter than the requested duration at
maximum reactive power, both leading and lagging, in each parameter specified in paragraph
8.5.6.7 point (b);
e) the power park module's capability to change to any reactive power target value within the
agreed or decided reactive power range is demonstrated; and
f) no protection action takes place within the operation limits specified by the reactive power
capacity diagram.
8.5.6.8 With regard to the voltage control mode test the following requirements shall apply:
a) the power park module's capability to operate in voltage control mode referred to in the
conditions set out in points (d) of paragraph 8.3.1.5 shall be demonstrated;
b) The voltage control mode test shall verify the following parameters:
- the implemented slope and deadband according to points (e) of paragraph 8.3.1.5;
GRID CODE PO-KO-005
CONNECTIONS CODE
ver.2.4 pages 49 from 32
8.5.6.11 With regard to the tests referred to in paragraphs 8.5.6.8, 8.5.6.9 and 8.5.6.10, the TSO may
select only one of the three control options for testing.
8.5.7.1 Synchronous power-generating modules shall be subject to the compliance simulations detailed
in paragraphs 8.5.7.2 to 8.5.7.5. Instead of all or part of those simulations, the power-generating facility
owner may use equipment certificates issued by an authorised certifier, which must be provided to the
TSO.
8.5.7.2 With regard to the LFSM-U response simulation the following requirements shall apply:
a) the power-generating modules capability to modulate active power at low frequencies in
accordance with paragraph 8.1.4.7 shall be demonstrated;
b) the simulation shall be carried out by means of low frequency steps and ramps reaching
maximum capacity, taking into account the droop settings and the deadband;
c) the simulation shall be deemed successful in the event that:
- the simulation model of the power-generating modul is validated against the
compliance test for LFSM-U response described in of paragraph 8.5.5.2; and
- compliance with the requirement of paragraph 8.1.3.8 is demonstrated.
8.5.7.3 With regard to the FSM response simulation the following requirements shall apply:
a) the power-generating modules capability to modulate active power over the full frequency
range in accordance with paragraph 8.1.4.7 shall be demonstrated;
b) the simulation shall be carried out by simulating frequency steps and ramps big enough to
trigger the whole active power frequency response range, taking into account the droop
settings and the deadband;
c) the simulation shall be deemed successful in the event that:
8.5.8 Compliance simulation for power park modules connected in transmission network
8.5.8.1 Power park modules are subject to the compliance simulations in paragraphs 8.5.8.2 to 8.5.8.5.
Instead of all or part of those simulations, the power-generating facility owner may use equipment
certificates issued by an authorised certifier, which must be provided to the TSO.
8.5.8.2 With regard to the LFSM-O response simulation the following requirements shall apply:
a) the power park module's capability to modulate active power at high frequency in accordance
with paragraph 8.1.3.1 shall be demonstrated;
b) the simulation shall be carried out by means of high frequency steps and ramps reaching
minimum regulating level, taking into account the droop settings and the deadband;
c) the simulation shall be deemed successful in the event that:
- the simulation model of the power park module is validated against the compliance test
for LFSM-O response set out in paragraph 8.5.6.3; and
- compliance with the requirement laid down in paragraph 8.1.3.1 is demonstrated.
8.5.8.3 With regard to the fast fault current injection simulation the following requirements shall apply:
GRID CODE PO-KO-005
CONNECTIONS CODE
ver.2.4 pages 52 from 32
a) the power park module's capability to provide fast fault current injection in accordance with
the conditions set out in paragraph 8.3.1.1 shall be demonstrated;
b) the simulation shall be deemed successful if compliance with the requirement laid down in
paragraph 8.3.1.1 is demonstrated.
8.5.8.4 With regard to the fault-ride-through simulation capability power park modules, the following
requirements shall apply:
a) the power park module's capability to ride through faults in accordance with the conditions set
out in paragraph 8.1.6.4 shall be demonstrated by simulation;
b) the simulation shall be deemed successful if compliance with the requirement laid down in
paragraph 8.1.6.4 is demonstrated.
8.5.8.5 The following requirements with regard to the post fault active power recovery simulation shall
apply:
a) the power park module's capability to provide post fault active power recovery in accordance
with the conditions set out in paragraph 8.3.1.3 shall be demonstrated;
b) the simulation shall be deemed successful if compliance with the requirement laid down in
paragraph 8.3.1.3 is demonstrated.
8.5.8.6 With regard to the LFSM-U response simulation the following requirements shall apply:
a) the power park module's capability to modulate active power at low frequencies in
accordance with paragraph 8.1.3.8 shall be demonstrated;
b) the simulation shall be carried out by simulating low frequency steps and ramps reaching
maximum capacity, taking into account the droop settings and the deadband;
c) the simulation shall be deemed successful in the event that:
- the simulation model of the power park module is validated against the compliance test
for LFSM-U response set out in paragraph 8.5.6.5; and
- compliance with the requirement laid down in paragraph 8.1.3.8 is demonstrated.
8.5.8.7 With regard to the FSM response simulation the following requirements shall apply:
a) the power park module's capability to modulate active power over the full frequency range as
referred to in paragraph 8.1.4.7 shall be demonstrated;
b) the simulation shall be carried out by simulating frequency steps and ramps big enough to
trigger the whole active power frequency response range, taking into account the droop
settings and the deadband;
c) the simulation shall be deemed successful in the event that:
- the simulation model of the power park module is validated against the compliance test
for FSM response set out in paragraph 8.5.6.6; and
- compliance with the requirement laid down in paragraph 8.1.4.7 is demonstrated.
8.5.8.8 With regard to the island operation simulation, the following requirements shall apply:
GRID CODE PO-KO-005
CONNECTIONS CODE
ver.2.4 pages 53 from 32
a) the power park module's performance during island operation in accordance with the
conditions set out in paragraph 8.1.9.3 shall be demonstrated;
b) the simulation shall be deemed successful in the event that the power park module reduces
or increases the active power output from its previous operating point to any new operating
point, within the P-Q-capability diagram and within the limits set out in paragraph 8.1.9.3,
without disconnection of the power park module from the island due to over or
underfrequency.
8.5.8.9 With regard to the simulation of the capability of providing synthetic inertia, the following
requirements shall apply:
a) the model of the power park module's capability of providing synthetic inertia to a low
frequency event as set out in paragraph 8.3.1.4 shall be demonstrated;
b) the simulation shall be deemed successful if the model demonstrates that it complies with
the conditions set out in paragraph 8.3.1.4.
8.5.8.10 With regard to the reactive power capability simulation, the following requirements shall
apply:
a) the power park module shall demonstrate that it can provide leading and lagging reactive
power capability as set out in points (b) and (d) of paragraph 8.3.1.5;
b) the simulation shall be deemed successful if the following conditions are cumulatively
fulfilled:
- the simulation model of the power park module is validated against the compliance
tests for reactive power capability set out in paragraph 8.5.6.7; and
8.5.8.11 With regard to the power oscillations damping control simulation, the following requirements
shall apply:
a) the model of the power park module shall demonstrate that it can provide active power
oscillations damping capability accordance with point (g) of paragraph 8.3.1.5;
b) the simulation shall be deemed successful in the event that the model demonstrates
compliance with the conditions described in point (g) of paragraph 8.3.1.5.
8.5.8.12 In addition to the compliance simulations for power park modules with capacity ≥5MW
connected in distribution network set out in paragraph 8.5.8, power park modules connected in
transmission network are subject to the fault-ride-through capability of power park modules
compliance simulation.
8.5.8.13 Instead of all or part of the simulations mentioned in paragraph 8.5.8.12, the power-
generating facility owner may use equipment certificates issued by an authorised certifier, which must
be provided to the TSO.
8.5.8.14 The model of the power park module connected in transmission network shall demonstrate
that it is suitable for simulating the fault-ride-through capability in accordance with paragraph 8.1.6.4.
8.5.8.15 The simulation shall be deemed successful if the model demonstrates compliance with the
conditions set out in paragraph 8.1.6.4.
GRID CODE PO-KO-005
CONNECTIONS CODE
ver.2.4 pages 54 from 32
Table 7.The minimum time periods during which a transmission-connected demand facilities and
transmission-connected distribution systems has to operate for voltages deviating from the nominal value
at the connection point without disconnecting from the network for 400 kV voltage level
the maximum import capacity or maximum export capacity (0,9 power factor import or export
of active power), except in situations where either technical or financial system benefits are
demonstrated, for transmission-connected demand facilities, by the transmission-connected
demand facility owner and accepted by the TSO;
b) For transmission-connected distribution systems, the actual reactive power range specified by
the TSO for importing and exporting reactive power shall not be wider than:
- 48 % (i.e. 0,9 power factor) of the larger of the maximum import capability or maximum
export capability during reactive power import (consumption); and
- 48 % (i.e. 0,9 power factor) of the larger of the maximum import capability or maximum
export capability during reactive power export (production); Except in situations where
either technical or financial system benefits are proved by the TSO and the transmission-
connected distribution system operator through joint analysis;
c) The TSO and the transmission-connected distribution system operator shall agree on the
scope of the analysis, which shall address the possible solutions, and determine the optimal
solution for reactive power exchange between their systems, taking adequately into
consideration the specific system characteristics, variable structure of power exchange,
bidirectional flows and the reactive power capabilities in the distribution system;
d) The TSO may establish the use of metrics other than power factor in order to set out
equivalent reactive power capability ranges;
e) The reactive power range requirement values shall be met at the connection point;
f) By way of derogation from point (e), where a connection point is shared between a power-
generating modul and a demand facility, equivalent requirements shall be met at the point
defined in connection agreements or national law.
9.4.2 Without prejudice to point (b) of paragraph 9.4.1, the TSO may require the transmission-
connected distribution system to actively control the exchange of reactive power at the connection
point for the benefit of the entire system. The TSO and the transmission-connected distribution system
operator shall agree on a method to carry out this control, to ensure the justified level of security of
supply for both parties. The justification shall include a roadmap in which the steps and the timeline for
fulfilling the requirement are specified.
9.4.3 In accordance with paragraph 9.4.2 the transmission-connected distribution system operator may
require the TSO to consider its transmission-connected distribution system for reactive power
management.
e) converter models.
9.6.5 TSO shall specify the requirements of the performance of the recordings of transmission-
connected demand facilities or transmission-connected distribution facilities, or both, in order to
compare the response of the model with these recordings.
any case not later than six months after the notification of the rejection of the request for a derogation,
each party may refer the issue for decision to the regulatory authority.
9.8 Connection of demand units used by a demand facility to provide demand response services to
TSO
9.8.1 General provisions
9.8.1.1 Demand response services provided to system operators shall be distinguished based on the
following categories:
a) remotely controlled:
- demand response active power control;
- demand response reactive power control;
- demand response transmission constraint management.
b) autonomously controlled:
- demand response system frequency control;
- demand response very fast active power control.
9.8.1.2 Demand facilities may provide demand response services to the TSOs. Demand response
services can include, jointly or separately, upward or downward modification of demand.
9.8.1.3 The categories referred to in paragraph 9.8.1.1 are not exclusive and this Code does not prevent
other categories from being developed. This Code does not apply to demand response services provided
to other entities than TSOs.
9.8.2 Specific provisions for demand units with demand response active power control, reactive
power control and transmission constraint management
9.8.2.1 Demand facilities may offer demand response active power control, demand response reactive
power control, or demand response transmission constraint management to TSO.
9.8.2.2 Demand units with demand response active power control, demand response reactive power
control, or demand response transmission constraint management shall comply with the following
requirements, either individually or, where it is not part of a transmission-connected demand facility,
collectively as part of demand aggregation through a third party:
a) be capable of operating across the frequency ranges specified in paragraph 9.1.1 and the ex-
tended range specified in paragraph 9.1.2;
b) be capable of operating across the voltage ranges specified in paragraph 9.2.3 if connected at
a voltage level at or above 110 kV;
c) be capable of operating across the normal operational voltage range of the system at the con-
nection point, specified by the TSO, if connected at a voltage level below 110 kV. This range
shall take into account Distribution Code requirements;
d) be capable of controlling power consumption from the network in a range equal to the range
contracted, directly or indirectly through a third party, by the TSO;
e) be equipped to receive instructions, directly or indirectly through a third party, from the TSO
to modify their demand and to transfer the necessary information. The TSO shall make publicly
available the technical specifications approved to enable this transfer of information. For de-
mand units connected at a voltage level below 110 kV, these specifications shall, prior to ap-
proval by the regulatory authority, be subject to consultation with the relevant stakeholders;
f) be capable of adjusting its power consumption within a time period specified by the TSO. For
demand units connected at a voltage level below 110 kV, these specifications shall, prior to
approval by the regulatory authority;
GRID CODE PO-KO-005
CONNECTIONS CODE
ver.2.4 pages 64 from 32
g) be capable of full execution of an instruction issued by the TSO to modify its power consump-
tion to the limits of the electrical protection safeguards, unless a contractually agreed method
is in place with the TSO for the replacement of their contribution (including aggregated de-
mand facilities' contribution through a third party);
h) once a modification to power consumption has taken place and for the duration of the re-
quested modification, only modify the demand used to provide the service if required by the
TSO to the limits of the electrical protection safeguards, unless a contractually agreed method
is in place with the TSO for the replacement of their contribution (including aggregated de-
mand facilities' contribution through a third party). Instructions to modify power consumption
may have immediate or delayed effects;
i) notify the TSO of the modification of demand response capacity. The TSO shall specify the mo-
dalities of the notification;
j) where the TSO, directly or indirectly through a third party, command the modification of the
power consumption, enable the modification of a part of its demand in response to an instruc-
tion by the TSO, within the limits agreed with the demand facility owner and according to the
demand unit settings;
k) have the withstand capability to not disconnect from the system due to the rate-of-change-of-
frequency up to a value specified by the TSO. With regard to this withstand capability, the val-
ue of rate-of-change-of-frequency shall be calculated over a 500 ms time frame. For demand
units connected at a voltage level below 110 kV, these specifications shall, prior to approval by
the Regulatory Authority, be subject to consultation with the relevant stakeholders.
l) where modification to the power consumption is specified via frequency or voltage control, or
both, and via pre-alert signal sent by the TSO, be equipped to receive, directly or indirectly
through a third party, the instructions from the TSO, to measure the frequency or voltage val-
ue, or both, to command the demand trip and to transfer the information. The TSO shall speci-
fy and publish the technical specifications approved to enable this transfer of information. For
demand units connected at a voltage level below 110 kV, these specifications shall, prior to
approval by the Regulatory Authority, be subject to consultation with the relevant stakehold-
ers.
9.8.2.3 For voltage control with disconnection or reconnection of static compensation facilities, each
transmission-connected demand facility shall be able to connect or disconnect its static compensation
facilities, directly or indirectly, either individually or commonly as part of demand aggregation through a
third party, in response to an instruction transmitted by the TSO, or in the conditions set forth in the
contract between TSO and the demand facility owner.
9.8.3 Specific provisions for demand units with demand response system frequency control
9.8.3.1 Demand facilities may offer demand response system frequency control to TSOs.
9.8.3.2 Demand units with demand response system frequency control shall comply with the following
requirements, either individually or, where it is not part of a transmission-connected demand facility,
collectively as part of demand aggregation through a third party:
a) be capable of operating across the frequency ranges specified in paragraph 9.1.1 and the ex-
tended range specified in paragraph 9.1.2;
b) be capable of operating across the voltage ranges specified in paragraph 9.2.3 if connected at
a voltage level at or above 110 kV;
GRID CODE PO-KO-005
CONNECTIONS CODE
ver.2.4 pages 65 from 32
c) be capable of operating across the normal operational voltage range of the system at the con-
nection point, specified by the TSO, if connected at a voltage level below 110 kV. This range
shall take into account existing standards, and shall, prior to approval by the Regulatory Au-
thority, be subject to consultation with the relevant stakeholders;
d) be equipped with a control system that is insensitive within a dead band around the nominal
system frequency of 50,00 Hz, of a width to be specified by the TSO in consultation with the
TSOs in the synchronous area. For demand units connected at a voltage level below 110 kV,
these specifications shall, prior to approval by the Regulatory Authority, be subject to consulta-
tion with the relevant stakeholders;
e) be capable of, upon return to frequency within the dead band specified in paragraph 2(d), ini-
tiating a random time delay of up to 5 minutes before resuming normal operation. The maxi-
mum frequency deviation from nominal value of 50,00 Hz to respond to shall be specified by
the TSO in coordination with the TSOs in the synchronous area. For demand units connected
at a voltage level below 110 kV, these specifications shall, prior to approval by the Regulatory
Authority, be subject to consultation with the relevant stakeholders. The demand shall be in-
creased or decreased for a system frequency above or below the dead band of nominal (50,00
Hz) respectively;
f) be equipped with a controller that measures the actual system frequency. Measurements shall
be updated at least every 0,2 seconds;
g) be able to detect a change in system frequency of 0,01 Hz, in order to give overall linear pro-
portional system response, with regard to the demand response system frequency control's
sensitivity and accuracy of the frequency measurement and the consequent modification of
the demand. The demand unit shall be capable of a rapid detection and response to changes in
system frequency, to be specified by the TSO in coordination with the TSOs in the synchronous
area. An offset in the steady-state measurement of frequency shall be acceptable up to 0,05
Hz.
9.8.4 Specific provisions for demand units with demand response very fast active power control
9.8.4.1 TSO may agree with a demand facility owner (including, but not restricted to, through a third
party) on a contract for the delivery of demand response very fast active power control.
9.8.4.2 If the agreement referred to in paragraph 9.8.4.1 takes place, the contract referred to in
paragraph 9.8.4.1 shall specify:
a) a change of active power related to a measure such as the rate-of-change-of-frequency for
that portion of its demand;
b) the operating principle of this control system and the associated performance parameters;
c) the response time for very fast active power control, which shall not be longer than 2 seconds.
9.8.5 Operational notification procedure for demand units with demand response
9.8.5.1 The operational notification procedure for demand units used by a demand facility to provide
demand response to TSO shall be distinguished between:
a) demand units within a demand facility connected at a voltage level of or below 1 kV;
b) demand units within a demand facility connected at a voltage level above 1 kV.
GRID CODE PO-KO-005
CONNECTIONS CODE
ver.2.4 pages 66 from 32
9.8.5.2 Each demand facility owner, providing demand response to a TSO, shall confirm to the TSO,
directly or indirectly through a third party, its ability to satisfy the technical design and operational
requirements as referred in paragraph 9.8 of this Code.
9.8.5.3 The demand facility owner shall notify, directly or indirectly, through a third party, the TSO, in
advance of any decision to cease offering demand response services and/or about the permanent
removal of the demand unit with demand response. This information may be aggregated as specified by
the TSO.
9.8.5.4 The TSO shall specify and make publicly available further details concerning the operational
notification procedure.
9.8.5.5 The operational notification procedure for a demand unit within a demand facility connected at
a voltage level of or below 1 kV shall comprise an installation document.
9.8.5.6 The installation document template shall be provided by the TSO, either directly or indirectly
through a third party.
9.8.5.7 Based on an installation document, the demand facility owner shall submit information, directly
or indirectly through a third party, to the TSO. The date of this submission shall be prior to the offer in
the market of the capacity of the demand response by the demand unit. The requirements set in the
installation document shall differentiate between different types of connections and between the
different categories of demand response services.
9.8.5.8 For subsequent demand units with demand response, separate installation documents shall be
provided.
9.8.5.9 The content of the installation document of individual demand units may be aggregated by the
TSO.
9.8.5.10 The installation document shall contain the following items:
a) the location at which the demand unit with demand response is connected to the network;
b) the maximum capacity of the demand response installation in kW;
c) the type of demand response services;
d) the demand unit certificate and the equipment certificate as relevant for the demand response
service, or if not available, equivalent information;
e) the contact details of the demand facility owner, or the third party aggregating the demand
units from the demand facility.
9.8.5.11 The operational notification procedure for a demand unit within a demand facility or a closed
distribution system connected at a voltage level above 1 kV shall comprise a demand response unit
document (DRUD). The TSO, shall specify the content required for the DRUD. The content of the DRUD
shall require a statement of compliance which contains the information in paragraph 9.10 to 9.12 for
demand facilities, but the compliance requirements in paragraph 9.10 to 9.12 for demand facilities can
be simplified to a single operational notification stage as well as be reduced. The demand facility owner
shall provide the information required and submit it to the TSO. Subsequent demand units with demand
response shall provide separate DRUDs.
9.8.5.12 Based on the DRUD, the TSO shall issue a FON to the demand facility owner.
GRID CODE PO-KO-005
CONNECTIONS CODE
ver.2.4 pages 67 from 32
modification or replacement of any equipment that may have an impact on the compliance of the
transmission-connected demand facility, the distribution system, or the demand unit with the
requirements of this Code. The demand facility owner, the DSO shall be informed of the outcome of
those compliance tests and simulations.
9.9.2.4 provided as well as the requirements to be fulfilled by the demand facility owner or the DSO in
the frame of the compliance process. The list shall cover at least the following information, documents
and requirements:
a) all documentation and certificates to be provided by the demand facility owner, the DSO;
b) details of the technical data required from the transmission-connected demand facility, the
distribution system, or the demand unit, with relevance to the grid connection or operation;
c) requirements for models for steady-state and dynamic system studies;
d) timeline for the provision of system data required to perform the studies;
e) studies by the demand facility owner, the DSO for demonstrating expected steady-state and
dynamic performance referring to the requirements set forth in paragraphs 9.11.1, 9.11.2 and
9.11.3;
f) conditions and procedures including scope for registering equipment certificates;
g) conditions and procedures for the use of relevant equipment certificates issued by an author-
ised certifier by the demand facility owner, or by the DSO.
9.9.2.5 The TSO shall make public the allocation of responsibilities to the demand facility owner or the
DSO and to the system operator for compliance testing, simulation and monitoring.
9.9.2.6 The TSO may totally or partially delegate the performance of its compliance monitoring to third
parties. In such cases, the TSO shall continue ensuring compliance with entering into confidentiality
commitments with the assignee.
9.9.2.7 If compliance tests or simulations cannot be carried out as agreed between the TSO and the
demand facility owner, or the DSO due to reasons attributable to the TSO, then the TSO shall not
unreasonably withhold the operational notification referred in paragraphs 9.1 to 9.8.
b) require the demand facility owner or the DSO to carry out additional or alternative sets of
tests in those cases where the information supplied to the TSO in relation to compliance test-
ing under the provisions of paragraphs 9.10.2 to 9.10.6, is not sufficient to demonstrate com-
pliance with the requirements of this Code.
GRID CODE PO-KO-005
CONNECTIONS CODE
ver.2.4 pages 69 from 32
9.10.1.3 The demand facility owner or the DSO is responsible for carrying out the tests in accordance
with the conditions laid down in paragraph 9.10. The TSO shall cooperate and not unduly delay the
performance of the tests.
9.10.1.4 The TSO may participate in the compliance testing either on site or remotely from the system
operator's control room. For that purpose, the demand facility owner or the DSO shall provide the
monitoring equipment necessary to record all relevant test signals and measurements as well as ensure
that the necessary representatives of the demand facility owner or the DSO are available on site for the
entire testing period. Signals specified by the TSO shall be provided if, for selected tests, the system
operator wishes to use its own equipment to record performance. The TSO has sole discretion to decide
about its participation.
9.10.3.2 An equipment certificate may be used instead of part of the tests provided for in paragraph
9.10.3.1, on the condition that it is provided to the TSO.
9.10.6 Compliance testing for demand units with demand response active power control, reactive
power control and transmission constraint management
9.10.6.1 With regard to the demand modification test:
a) the technical capability of the demand unit used by a demand facility to provide demand
response active power control, demand response reactive power control or demand
response transmission constraint management to modify its power consumption, after
receiving an instruction from the DSO or TSO, within the range, duration and time frame
previously agreed and established in accordance with paragraph 9.8.2, shall be
GRID CODE PO-KO-005
CONNECTIONS CODE
ver.2.4 pages 71 from 32
b) require the demand facility owner or the DSO to carry out additional or alternative sets of
simulations in those cases where the information supplied to the TSO in relation to
compliance simulation under the provisions of paragraphs 9.11.2, 9.11.3 and 9.11.4, is not
sufficient to demonstrate compliance with the requirements of this Code.
9.11.1.4 The transmission-connected demand facility owner or the transmission-connected distribution
system operator shall provide a report with the simulation results for each individual transmission-
connected demand facility or transmission-connected distribution facility. The transmission-connected
demand facility owner or the transmission-connected distribution system operator shall produce and
provide a validated simulation model for a given transmission-connected demand facility or
transmission-connected distribution facility. The scope of the simulation models is set out in paragraphs
9.6.1 and 9.6.2
9.11.1.5 The TSO shall have the right to check that a demand facility or a distribution system complies
with the requirements of this Code by carrying out its own compliance simulations based on the
provided simulation reports, simulation models and compliance test measurements.
9.11.1.6 The TSO shall provide the demand facility owner or the DSO with technical data and a
simulation model of the network, to the extent necessary to carry out the requested simulations in
accordance with paragraphs 9.11.2, 9.11.3 and 9.11.4.
c) the simulation shall be deemed passed if the results demonstrate compliance with the
requirements set out in paragraph 9.4.1 and 9.4.2
9.11.3.2 With regard to the reactive power capability simulation of a transmission-connected demand
facility with onsite generation:
a) a load flow simulation model of the transmission-connected demand facility shall be used to
calculate the reactive power exchange under different load conditions and under different
generation conditions;
b) a combination of minimum and maximum load and generation conditions resulting in the
lowest and highest reactive power capability at the connection point shall be part of the
simulations;
c) the simulation shall be deemed passed if the results demonstrate compliance with the
requirements set out in paragraph 9.4.1 and 9.4.2
9.11.4 Compliance simulations for demand units with demand response very fast active power con-
trol
9.11.4.1 The model of the demand unit used by a demand facility owner to provide demand response
very fast active power control shall demonstrate the technical capability of the demand unit to provide
very fast active power control to a low frequency event in the conditions set out in paragraph 9.8.4.
9.11.4.2 The simulation shall be deemed passed provided that the model demonstrates compliance
with the conditions set out in paragraph 9.8.4.
10 Derogations
Regulatory may, at the request of power-generating facility owner, a demand facility owner, DSO or
TSO, grant: power-generating facility owner, demand facility owners, DSO and TSO derogations from
one or more provisions of this Code for new and existing transmission-connected demand facilities,
transmission-connected distribution facilities, distribution system and demand units in accordance
with paragraphs 10.1 to 10.3.
GRID CODE PO-KO-005
CONNECTIONS CODE
ver.2.4 pages 74 from 32
10.1.2 If the regulatory authority deems that it is necessary due to a change in circumstances relating
to the evolution of system requirements, it may review and amend at most once every year the criteria
for granting derogations in accordance with paragraph 10.1.1. Any changes to the criteria shall not apply
to derogations for which a request has already been made
10.1.3 The regulatory authority may decide that: power-generating modules, transmission-connected
demand facilities, transmission-connected distribution facilities, distribution system and demand units
for which a request for a derogation has been filed pursuant to paragraphs 10.2 or 10.3. do not need to
comply with the requirements of this Code from which a derogation has been sought from the day of
filing the request until the regulatory authority's decision is issued.
10.2 Request for a derogation by a power-generating facility owner, demand facility owner or distri-
bution system operator
10.2.1 Power-generating facility owners, demand facility owners and DSO, may request a derogation
to one or several requirements of this Code for power-generating modules within their facilities,
transmission-connected demand facilities, transmission-connected distribution facilities, distribution
system, or demand units used by a demand facility to provide demand response services to DSO and to
TSO.
10.2.2 A request for a derogation shall be filled with the TSO or DSO as the case may be and include:
a) an identification of the power-generating facility owner, demand facility owner, the DSO and
a contact person for any communications;
b) a description of the power-generating module or modules, transmission-connected demand
facility, the transmission-connected distribution facility, the distribution system, or the
demand unit for which a derogation is requested;
c) a reference to the provisions of this Code from which a derogation is requested and a detailed
description of the requested derogation;
d) demonstration that the requested derogation would have no adverse effect on cross-border
trade.
10.2.3 Within two weeks of receipt of a request for a derogation, the TSO or DSO (as the case may be)
shall confirm to the power-generating facility owner, demand facility owner or to the DSO, whether the
request is complete. If the TSO or DSO (as the case may be) considers that the request is incomplete,
power-generating facility owner, the demand facility owner or the DSO shall submit the additional
required information within one month from the receipt of the request for additional information. If the
power-generating facility owner, demand facility owner or if the DSO does not supply the requested
information within that time limit, the request for a derogation shall be deemed withdrawn
GRID CODE PO-KO-005
CONNECTIONS CODE
ver.2.4 pages 75 from 32
10.2.4 If a request for a derogation concerns power-generating module connected to distribution sys-
tem, the DSO assessment must be accompanied by an assessment of the request for a derogation by
the TSO. The TSO shall provide its assessment within two months of being requested to do so by the
DSO.
10.2.5 The DSO shall, in coordination with the TSO, assess the request for a derogation, taking into ac-
count the criteria determined by the regulatory authority pursuant to paragraph 10.1.
10.2.6 Within six months of receipt of a request for a derogation, the TSO or DSO (as the case may be)
shall forward the request to the regulatory authority and submit the assessment(s) prepared in
accordance with paragraphs 10.2.4 and 10.2.5. That period may be extended by one month where the
TSO or DSO (as the case may be) seeks further information from the power-generating facility owner,
demand facility owner or from the DSO and by two months where the DSO requests the TSO to submit
an assessment of the request for a derogation
10.2.7 The regulatory authority shall adopt a decision concerning any request for a derogation within
six months from the day after it receives the request. That time limit may be extended by three months
before its expiry where the regulatory authority requires further information from the power-generating
facility owner, demand facility owner or from the DSO or from any other interested parties. The
additional period shall begin when the complete information has been received
10.2.8 For the power-generating facility owner TSO or DSO (as the case may be), shall submit any
additional information requested by the regulatory authority within two months of such request. If the
TSO or DSO (as the case may be) does not supply the requested information within that time limit, the
request for a derogation shall be deemed withdrawn unless, before its expiry. Demand facility owner or
the DSO shall submit any additional information requested by the regulatory authority within two
months of such request. If the power-generating facility owner, demand facility owner or if the DSO
does not supply the requested information within that time limit, the request for a derogation shall be
deemed withdrawn unless, before its expiry:
a) identification of the TSO or DSO (as the case may be), and a contact person for any
communications;
b) a description of the power-generating modules, transmission-connected demand facility,
the transmission-connected distribution facility, the distribution system, or the demand
unit for which a derogation is requested and the total installed capacity and number of
power-generating modules, transmission-connected demand facilities, transmission-
connected distribution facilities, distribution system, or demand units;
c) the requirement or requirements of this Code for which a derogation is requested, with a
detailed description of the requested derogation;
d) detailed reasoning, with all relevant supporting documents;
e) demonstration that the requested derogation would have no adverse effect on cross-border
trade.
10.3.3 Where the request for a derogation is submitted by DSO, the regulatory authority shall, within
two weeks from the day after receipt of that request, ask the TSO to assess the request for a derogation
in the light of the criteria determined by the regulatory authority. pursuant to paragraph 10.1
10.3.4 Within two weeks from the day after the receipt of such request for assessment, the TSO shall
confirm to the DSO whether the request for a derogation is complete. If the TSO considers that it is
incomplete, the DSO shall submit the required additional information within one month from the
receipt of the request for additional information.
10.3.5 Within six months of receipt of a request for a derogation, the TSO shall submit to the
regulatory authority its assessment, including any relevant documentation. The six-month time limit
may be extended by one month where the TSO seeks further information from the DSO.
10.3.6 The regulatory authority shall adopt a decision concerning a request for a derogation within six
months from the day after it receives the request. Where the request for a derogation is submitted by
the DSO, the six-month time limit runs from the day following receipt of the TSO's assessment pursuant
to paragraph 10.3.5
10.3.7 The six-month time limit referred to in paragraph 10.3.6 may, before its expiry, be extended by
an additional three months where the regulatory authority requests further information from the TSO
requesting the derogation or from any other interested parties. That additional period shall run from the
day following the date of receipt of the complete information.
The TSO shall provide any additional information requested by the regulatory authority within two
months from the date of the request. If the TSO does not provide the requested additional information
within that time limit, the request for a derogation shall be deemed withdrawn unless, before expiry of
the time limit:
a) the regulatory authority decides to provide an extension; or
GRID CODE PO-KO-005
CONNECTIONS CODE
ver.2.4 pages 77 from 32
b) the TSO informs the regulatory authority by means of a reasoned submission that the
request for a derogation is complete.
10.3.8 The regulatory authority shall issue a reasoned decision concerning a request for a derogation.
Where the regulatory authority grants derogation, it shall specify its duration.
10.3.9 The regulatory authority shall notify its decision to the TSO requesting the derogation, and the
Secretariat and the Energy Community Regulatory Board.
10.3.10 Regulatory authority may lay down further requirements concerning the preparation of requests
for a derogation by TSO. In doing so, regulatory authorities shall take into account the delineation
between the transmission system and the distribution system at the national level and shall consult
with DSO, demand facility owners and stakeholders, including manufacturers.
10.3.11 Regulatory authority may revoke a decision granting a derogation if the circumstances and
underlying reasons no longer apply or upon a reasoned recommendation of the Commission or
reasoned recommendation by the the Secretariat and the Energy Community Regulatory Board
pursuant to paragraph 10.4.2.
10.4.2 The Secretariat and the Energy Community Regulatory Board may issue a reasoned
recommendation to regulatory authority to revoke a derogation due to a lack of justification.