Tender Drainage
Tender Drainage
Tender Drainage
1) Materials Cost
* Rate take from PJ VSQ Normal Mix Pump Mix Tremie 2 Tremie 3
Normal Mix Wastage Total Cost Pump Mix Wastage Total Cost Tremie 2 Wastage Total Cost Tremie 3 Wastage Total Cost
Item Type
(RM/m3) 5% (RM/m3) (RM/m3) 5% (RM/m3) (RM/m3) 5% (RM/m3) (RM/m3) 5% (RM/m3)
Lean Concrete
1 Grade 15 230.00 11.50 241.50 N/A - - N/A - - N/A - -
Concrete
1 Grade 25 235.00 11.75 246.75 165.00 8.25 173.25 177.00 8.85 185.85 183.00 9.15 192.15
2 Grade 30 169.00 8.45 177.45 175.00 8.75 183.75 187.00 9.35 196.35 193.00 9.65 202.65
3 Grade 35 180.00 9.00 189.00 186.00 9.30 195.30 196.00 9.80 205.80 201.00 10.05 211.05
4 Grade 40 192.00 9.60 201.60 198.00 9.90 207.90 208.00 10.40 218.40 213.00 10.65 223.65
5 Grade 45 205.00 10.25 215.25 211.00 10.55 221.55 221.00 11.05 232.05 226.00 11.30 237.30
6A Grade 50 N/A - - N/A - - N/A - - 240.00 12.00 252.00
6B Grade 50 N/A - - N/A - - N/A - - 270.00 13.50 283.50
7 Grade 55 N/A - - N/A - - N/A - - 255.00 12.75 267.75
8 Grade 60 N/A - - N/A - - N/A - - 261.00 13.05 274.05
2) Labour Cost
Workload - Fixing & Install
Workload Per ManDay (10 hrs) 6.51 m2/MD (10 hrs)
Workload Per ManDay (8 hrs) 5.21 m2/MD (8hrs)
Rate Per Day 75 Rate/day
Rate / m2 RM 14.40 /m2
By Nos By Nos By Nos By Nos By Nos By Nos Extra Order By Set By Set
Machine Type
Barbending Bar Cutting Link Cutting Total Amt Barbending Bar Cutting Link Cutting Total Amt Link Cutting Barbending & Bar Cutting Machine Different
Diameter 32mm 32mm 16mm 42mm 42mm 16mm 16mm 32mm + 16mm 42mm + 16mm 32mm 42mm
* Per Pcs *1 Set + Link Cutting
Rate RM 500.00 RM 500.00 RM 450.00 RM 1,450.00 RM 1,000.00 RM 1,000.00 RM 450.00 RM 2,450.00 RM 450.00 RM 1,350.00 RM 2,250.00 RM 100.00 RM 200.00
Cost Per Pcs (Bar Bending + Bar Cutting + Link Cutting) 2) Materials Cost
32mm Item Rebar Unit Rate Remark
Total Rental Cost Per Mth (32mm) + Link Cut (16mm) RM 1,450.00 Mild Steel
Rental Cost Per Day (30 Days) RM 48.33 1 R10 - R12 RM/kg RM 2.15
Rental Cost Per Hrs (24 hrs) RM 2.01
High Yield * Rate take from
42mm
PJ VSQ Project
Total Rental Cost Per Mth (42mm) + Link Cut (16mm) RM 2,450.00 2 Y10 - Y12, Y40 RM/kg RM 2.15
Rental Cost Per Day (30 Days) RM 81.67 3 Y16 - Y32 RM/kg RM 2.00
Rental Cost Per Hrs (24 hrs) RM 3.40
Cost Per Set (Bar Bending & Bar Cutting) + Link Cutting Assumption : 12m of each rebar
32mm Rebar Size Factor Qty Rate/kg Cost Rate/m
Total Rental Cost Per Mth (32mm) + Link Cut (16mm) RM 1,350.00 Mild Steel
Total Rental Cost Per Mth (42mm) + Link Cut (16mm) RM 3,075.00 R10 0.616 7.39 RM 2.15 RM 15.90 RM 1.32
Assume diesel used per mth RM 2,000.00 R12 0.887 10.65 RM 2.15 RM 22.89 RM 1.91
* Diesel record from dengkil maincon backcharges RM 6,425.00
High Yeild
Rental per mth/kg RM 0.03 Y10 0.616 7.39 RM 2.15 RM 15.90 RM 1.32
Assume : RM 0.05 Y12 0.887 10.65 RM 2.15 RM 22.89 RM 1.91
Y16 1.577 18.93 RM 2.00 RM 37.86 RM 3.15
42mm Y20 2.465 29.58 RM 2.00 RM 59.16 RM 4.93
Total Rental Cost Per Mth (42mm) + Link Cut (16mm) RM 2,250.00 Y25 3.851 46.22 RM 2.00 RM 92.43 RM 7.70
RM 3,075.00 Y32 6.310 75.72 RM 2.00 RM 151.44 RM 12.62
RM 5,325.00 Y40 9.859 118.31 RM 2.15 RM 254.37 RM 21.20
High Yeild
Y10 RM 2.15 RM 0.11 RM 0.05 RM 0.36 RM 2.67 RM 0.40 RM 3.07
Y12 RM 2.15 RM 0.11 RM 0.05 RM 0.36 RM 2.67 RM 0.40 RM 3.07
Y16 RM 2.00 RM 0.10 RM 0.05 RM 0.36 RM 2.51 RM 0.38 RM 2.88
Y20 RM 2.00 RM 0.10 RM 0.05 RM 0.36 RM 2.51 RM 0.38 RM 2.88
Y25 RM 2.00 RM 0.10 RM 0.05 RM 0.36 RM 2.51 RM 0.38 RM 2.88
Y32 RM 2.00 RM 0.10 RM 0.05 RM 0.36 RM 2.51 RM 0.38 RM 2.88
Y40 RM 2.15 RM 0.11 RM 0.05 RM 0.36 RM 2.67 RM 0.40 RM 3.07
Project : Dengkil XMU Scaffolding: 900 H, 1700H, 1900H
Subject : Budget of the Scaffolding Size: 1.2m L x 1.8m W (spacing)
Material Cost
Rental of Scaffolding 1.2 x 1.8 (D) x 1.7 (H)
Scaffolding Rate for do the Finishing Works (Apply into the Finishing Works' Rate)
Estimate floor high 3.0m and do an assumption of the scaffolding to use
Assumption : 1.8m Length X 2.6m Height = Area 4.68m2
Area 1 set Main Frame + Short Frame 4.68 m2/1 set scaffolding
407.60
Total Cost RM 407.60
Total Area m2 4.68
Rate/m2 RM 87.10
Total Cost
Material Cost
Rental of Scaffolding 1.2 x 1.8 (D) x 1.7 (H)
Labour Cost
Main Frame Oly
Nov-2020 Workdone 10days 1,832.33 m2
Total Manpower 2 Pax
Workdone/MD 916.17 m2
10 hrs of workdone 91.62 m2/day
8 hrs of workdone 73.29 m2/day
Rate/m2 RM 1.03
Total Cost
Material Cost
Rental of Scaffolding 1.2 x 1.8 (D) x 1.7 (H)
Area of 1 Set Scaffolding side/spacing
Item Dimension Area (m2)
1 set frame
Area 1 set Main frame 1.7m*1.8m 3.06
Area 1 set Sub frame 0.9m*1.8m 1.62
Labour Cost
1.8m
side/spacing
Material Cost
1) Skim Coat White (2mm thk) 2) Skim Coat Grey (2mm thk) 3) Skim Coat Grey (5mm thk)
Base (381) 40kg - 1 bag RM 17.00 Base (781) 40kg - 1 bag RM 14.50 Base (781) 40kg - 1 bag RM 14.50
Coverage Area for 1 bag = 30.77 m2/mm thk Coverage Area for 1 bag = 30.77 m2/mm thk Coverage Area for 1 bag = 30.77 m2/mm thk
1kg = RM 0.43 1kg = RM 0.36 1kg = RM 0.36
Coverage = 1.3kg/m2/mm thk Coverage = 1.3kg/m2/mm thk Coverage = 1.3kg/m2/mm thk
Cost = RM 0.55 /m2/1 mm thk Cost = RM 0.47 /m2/1 mm thk Cost = RM 0.47 /m2/1 mm thk
Cost = RM 1.11 /m2/2 mm thk Cost = RM 0.94 /m2/2 mm thk Cost = RM 1.41 /m2/3 mm thk
Finish (281) 25kg - 1 bag RM 16.00 Finish (681) 25kg - 1 bag RM 13.50 Finish (681) 25kg - 1 bag RM 13.50
Coverage Area for 1 bag = 20.83 m2/mm thk Coverage Area for 1 bag = 20.83 m2/mm thk Coverage Area for 1 bag = 20.83 m2/mm thk
1kg = RM 0.64 1kg = RM 0.54 1kg = RM 0.54
Coverage = 1.2kg/m2/mm thk Coverage = 1.2kg/m2/mm thk Coverage = 1.2kg/m2/mm thk
Cost = RM 0.77 /m2/1 mm thk Cost = RM 0.65 /m2/1 mm thk Cost = RM 0.65 /m2/1 mm thk
Cost = RM 1.54 /m2/2 mm thk Cost = RM 1.30 /m2/2 mm thk Cost = RM 1.30 /m2/2 mm thk
* Spec is minimum 3mm thk) * Spec is minimum 3mm thk)
Specification = Max. 2 mm thk of Skim Coat White Specification = Max. 2 mm thk of Skim Coat Grey Specification = Max. 5 mm thk of Skim Coat Grey
* Total mm thk = 2 mm thk (Base 1mm thk & Finish 1mm thk) * Total mm thk = 1 mm thk (Base 1 mm thk & Finish 1 mm thk) * Total mm thk = 5 mm thk (Base 3 mm thk & Finish 2 mm thk)
Rate = 1.32 /m2/2 mm thk Rate = 1.12 /m2/2 mm thk Rate = 2.71 /m2/5 mm thk
Estimate Labour Rate/day (8 Hrs) 70.00 Estimate Labour Rate/day (8 Hrs) 70.00
Rate/m2/2mm thk/Day RM 1.59 /m2 Rate/m2/5mm thk/Day RM 1.70 /m2
Rate/m2/1mm thk/Day RM 0.79 Rate/m2/1mm thk/Day RM 0.34
Oct-2020 Workdone - (White) 9,891.95 m2 / 8 pax Oct-2020 Workdone - (Grey) 5,467.61 m2 / 3 pax
Workdone for 1 Man 1,236.49 m2 Workdone for 1 Man 1,822.54 m2
10 hrs of workdone 47.56 m2 10 hrs of workdone 70.10 m2
8 hrs of workdone 38.05 m2 8 hrs of workdone 56.08 m2
Estimate Labour Rate/day (8 Hrs) 70.00 Estimate Labour Rate/day (8 Hrs) 70.00
Rate/m2/2mm thk/Day RM 1.84 /m2 Rate/m2/5mm thk/Day RM 1.25 /m2
Rate/m2/1mm thk/Day RM 0.92 Rate/m2/1mm thk/Day RM 0.25
Rate/M2
Total Area (m2) 57,048.00 m2
Rate/M2 -
Total Material Cost #REF!
Material Cost
1) Skim Coat White (2mm thk) 2) Skim Coat Grey (3mm thk) 3) Skim Coat Grey (3mm base + 2mm finish = 5mm thk)
Base Mortar 381 40 kg/bag RM 17.00 Starken Base 40 kg/bag RM 18.30 Starken Base 40 kg/bag RM 18.30
Coverage = 1.3 kg/m2/mm thk Coverage = 1.4 kg/m2/mm thk Coverage = 1.4 kg/m2/mm thk
m2/1mm m2/2mm m2/3mm m2/2mm m2/3mm m2/4mm m2/2mm m2/3mm m2/4mm
Thickness for 2-3mm/coat = 30.77 15.38 10.26 Thickness for 2-4mm/coat = 14.29 9.52 7.14 Thickness for 2-4mm/coat = 14.29 9.52 7.14
Cost = RM 0.55 /m2/1 mm thk Cost = RM 1.28 /m2/2 mm thk Cost = RM 1.28 /m2/2 mm thk
RM 1.11 /m2/2 mm thk RM 1.92 /m2/3 mm thk RM 1.92 /m2/3 mm thk
RM 1.66 /m2/3 mm thk
* Base 2-3mm/coat * Base 2-4mm/coat * Base 2-4mm/coat
Finish Mortar 281 25 kg/bag RM 16.00 Starken Finish 25 kg/bag RM 18.00 Starken Finish 25 kg/bag RM 18.00
Coverage = 1.2 kg/m2/mm thk Coverage = 1.2 kg/m2/mm thk Coverage = 1.2 kg/m2/mm thk
m2/mm m2/2mm m2/mm m2/2mm m2/mm m2/2mm m2/3mm
Thickness for 1-2mm/coat = 20.83 10.41 Thickness for 1-2mm/coat = 20.83 10.41 Thickness for 1-2mm/coat = 20.83 10.41 6.94
Cost/thickness = RM 0.77 /m2/1mm Cost/thickness = RM 0.86 /m2/1mm Cost/thickness = RM 0.86 /m2/1mm
RM 1.54 /m2/2mm RM 1.73 /m2/2mm RM 1.73 /m2/2mm
RM 2.59 /m2/3mm
* Finish 1-2mm/coat * Finish 1-2mm/coat * Finish 1-2mm/coat
* Total coats = 2 mm thk (Specification requirement, Min. thickness * Total coats = 3 mm thk * Total coats = 5 mm thk
are base 2mm + finish 1mm)
RM RM RM
Base Mortar 381 0.55 (Base 1mm thk ) Starken Base 1.28 (Base 2mm) Starken Base 1.92 (Base 3mm thk)
Finish Mortar 281 0.77 (Finish 1mm thk) Starken Finish 0.86 (Finish 1mm thk) Starken Finish 1.73 (Finish 2mm thk)
RM 1.32 /m2/2 mm thk RM 1.66 RM 2.15 /m2/3 mm thk RM 3.65 /m2/5 mm thk
Estimate Labour Rate/day (8 Hrs) 70.00 Estimate Labour Rate/day (8 Hrs) 70.00
Rate/m2/Day RM 1.59 /m2/2mm RM 1.65 /m2/3mm Rate/m2/Day RM 1.70 /m2/5mm
Oct-2020 Workdone - (White) 9,891.95 m2 /pax 8 Oct-2020 Workdone - (Grey) 5,467.61 m2 /pax
Workdone for 1 Man 1,236.49 m2/days 26 Workdone for 1 Man 1,822.54 m2
10 hrs of workdone 47.56 m2 10 hrs of workdone 70.10 m2
8 hrs of workdone 38.05 m2/2mm 8 hrs of workdone 56.08 m2/5mm
Estimate Labour Rate/day (8 Hrs) 70.00 Estimate Labour Rate/day (8 Hrs) 70.00
Rate/m2/Day RM 1.84 /m2/2mm RM 1.54 /m2/3mm Rate/m2/Day RM 1.25 m2/5mm
Average of Labour Cost per 2mm coat Average of Labour Cost per 5mm coat
For White Color RM 1.71 m2/1mm RM 1.61 m2/1mm For Grey Color RM 1.48 m2/1mm
Material Cost
1) Render Grey (10 - 12mm thk)
Starken AAC Render 40 kg/bag RM 14.80
Coverage = 1.6 kg/m2/mm thk
m2/10mm m2/11mm m2/12mm
Thickness for 10-12mm/coat = 2.50 2.27 2.08
Cost = RM 5.92 /m2/10 mm thk
RM 6.51 /m2/11 mm thk
RM 7.10 /m2/12 mm thk
* Render 10-12mm/coat
Others Materials
Corner Bead (1 nos of 2.5m) RM 1.00
Rate/m RM 0.40
Labour RM 1.50
Material Cost
1) Plastering (20mm thk) price = RM 4.33
Cement Mortar (1:5) 50 kg/bag RM 19.25 800 bag/Palletised
Assume: 1 5 6
Mortar ratio (1:5) 1/6 5/6
Plaster thickness = 20 mm
Constants:
Density of cement= 1440 kg/m3
1m3= 35.3147 ft3
Truck size
L= 5.5 - 6 m
W= 1.7 m
H= 2m
Vol. of Dumper = L x B x H
= 19.55 m3
rken AAC Block, Domain Rate Starken AAC Block, Domain Rate
Int. Wall Ext. Wall
150mm 200mm 250mm 300mm Thick 75mm 100mm 125mm 150mm 200mm 250mm
160 210 260 310 115 115 140 165 215 265
3-5mm 3-5mm 3-5mm 3-5mm 3-5mm 3-5mm 3-5mm 3-5mm 3-5mm 3-5mm
10-12mm 10-12mm 10-12mm 10-12mm 10-12mm 10-12mm
2.50 2.50 2.50 2.50 RM 2.50 2.50 2.50 2.50 2.50 2.50
37.20 37.20 37.20 37.20 RM 37.20 37.20 37.20 37.20 37.20 37.20
29.00 38.00 48.00 58.00 RM 16.00 19.00 24.00 29.00 38.00 48.00
1.13 1.13 1.13 1.13 RM 1.13 1.13 1.13 1.13 1.13 1.13
1.27 1.27 1.27 1.27 RM 1.27 1.27 1.27 1.27 1.27 1.27
45.00 45.00 90.00 90.00 RM 45.00 45.00 45.00 45.00 45.00 90.00
0.79 0.79 0.79 0.79 RM 0.79 0.79 0.79 0.79 0.79 0.79
116.89 125.89 180.89 190.89 RM 103.89 106.89 111.89 116.89 125.89 180.89
5.84 6.29 9.04 9.54 RM 5.19 5.34 5.59 5.84 6.29 9.04
20 21 22 23 RM 17 18 19 20 21 22
11.58 15.10 19.13 23.16 RM 8.05 8.05 9.82 11.58 15.10 19.13
154.31 168.28 231.06 246.59 RM 134.13 138.28 146.30 154.31 168.28 231.06
15.43 16.83 23.11 24.66 RM 13.41 13.83 14.63 15.43 16.83 23.11
170.00 186.00 255.00 272.00 148.00 153.00 161.00 170.00 186.00 255.00
RM
0 0 0 0 RM 15.50 15.50 15.50 15.50 15.50 15.50
170.00 186.00 255.00 272.00 0.00 163.50 168.50 176.50 185.50 201.50 270.50
215 x 102 x 70 mm
How many m2 are in a pallet of bricks? 500 pcs
(L × H × W) of brick = 0.215 m × 0.065 m × 0.1025 m
Area of 1/2 brick = length × height, 10mm mortar
Area of 1/2 brick = 0.225 m × 0.075 m = 0.016875 m2
No. of half brick thk = 1 m2/0.016875 m2 = 60 nos
15.50
287.50 64.36 64.36 128.72 46.77 46.77
1 brick thk = 120 nos
Damp Proof Course, 30m Length