Lancaster Field Floating Production Storage and Offloading Vessel FPSO Decommissioning Programme
Lancaster Field Floating Production Storage and Offloading Vessel FPSO Decommissioning Programme
October 2022
HUR-GLA-ASM-REP-0001-1
Amendment Record
Revision Date Description Author Checked Approved
A0 26 August 2021 Internal Review OJ FS SH
Holds
INST P/L
Contents
Tables and Figures ........................................................................................................................ 4 ✓
Terms and Abbreviations .............................................................................................................. 5 ✓
Appendices ................................................................................................................................... 6 ✓
1. Executive Summary ............................................................................................................... 7 ✓
1.1. Decommissioning Programme ................................................................................................. 7 ✓
1.2. Requirement for Decommissioning Programme ..................................................................... 7 ✓
1.3. Introduction ............................................................................................................................. 7 ✓
1.4. Overview of Installation being Decommissioned .................................................................... 8 ✓
1.5. Summary of Proposed Decommissioning Programme ............................................................ 9 ✓
1.6. Field Location including Field Layout and Adjacent Facilities ................................................ 10 ✓
1.7. Industrial Implications ........................................................................................................... 11 ✓
2. Description of Items to be Decommissioned......................................................................... 12 ✓
2.1. Installation – Surface Facility ................................................................................................. 12 ✓
2.2. Wells ...................................................................................................................................... 12
2.3. Inventory Estimates ............................................................................................................... 12 ✓
3. Removal and Disposal Methods ........................................................................................... 14 ✓
3.1. Surface Facility (FPSO) ........................................................................................................... 14 ✓
3.2. Waste Streams ....................................................................................................................... 17 ✓
4. Environmental Appraisal Overview ...................................................................................... 18 ✓
4.1. Environmental Sensitivities.................................................................................................... 18 ✓
4.2. Potential Environmental Impacts and their Management .................................................... 20 ✓
5. Interested Party Consultations ............................................................................................. 21
6. Programme Management .................................................................................................... 23 ✓
6.1. Project Management and Verification................................................................................... 23 ✓
6.2. Post Decommissioning Debris Clearance and Verification .................................................... 23 ✓
6.3. Schedule ................................................................................................................................. 23 ✓
6.4. Costs ....................................................................................................................................... 24
6.5. Close Out ................................................................................................................................ 24
6.6. Post Decommissioning Monitoring and Evaluation ............................................................... 24 ✓
7. Supporting Documents ........................................................................................................ 25
Appendix 1 Partner Letter(s) of Support ...................................................................................... 26
Appendix 2 Public Notices ........................................................................................................... 28
Appendix 3 Statutory Consultee Correspondence ........................................................................ 29
Appendix 4 TMS Buoy Post FPSO Departure Risk Assessment....................................................... 32
Appendices
Appendix Description Page
1 Partner Letters of Support 26
1. Executive Summary
1.1. Decommissioning Programme
This document is the decommissioning programme for the Lancaster Field production host the Aoka Mizu Floating
Production Storage and Offloading (FPSO).
The remaining Lancaster Field infrastructure which is listed on the Section 29 Notices will be subject to a separate
Wells, Subsea, Pipelines and Mooring System Decommissioning Programme (HUR-GLA-ASM-REP-0002), which will
be submitted separately to OPRED.
The Aoka Mizu will be utilised for the initial decommissioning activities, namely the flushing/de-oiling of the subsea
infrastructure i.e. manifolds, risers, subsea flowlines and umbilical, and to support with the implementation of
positive isolations. The FPSO is then not required to perform any further decommissioning related activities on the
subsea infrastructure after completion of the decommissioning activities above, and it is proposed that the vessel
is removed thereafter from its current location. Activities associated with subsequent decommissioning stages of
the subsea flowlines, umbilical, risers and other subsea infrastructure will require the services provided by other
specialist vessels.
The early removal of this Installation will not prejudice any further decommissioning work in the Lancaster Field.
Installation
In accordance with the Petroleum Act 1998, the Section 29 notice holders of the Lancaster Field’s FPSO installation
(Table 1-1) are applying to the Offshore Petroleum Regulator for Environment and Decommissioning (OPRED) to
obtain approval for decommissioning the installation detailed in Section 2.1 of this programme. (See also Appendix
1- Partner Letter(s) of Support).
In conjunction with public, stakeholder and regulatory consultation, the Decommissioning Programme is submitted
in compliance with national and international regulations and OPRED guidelines. The schedule outlined in this
document is for a 23-30 day decommissioning project plan due to begin in 2023, however the timing of the
decommissioning programme will depend on reservoir performance, oil price and other factors.
The Lancaster Field Operator (Hurricane Energy PLC), on behalf of the P1368 Central Licensee (Hurricane GLA
Limited), has submitted to the Oil and Gas Authority (OGA) a Cessation of Production document which
demonstrates, against a backdrop of the Licensee’s financial position, that all economic development opportunities
have been pursued for the Lancaster Field and associated infrastructure including access to current third-party
infrastructure. On 14 December 2021 the OGA confirmed no objection to the CoP document as proposed.
1.3. Introduction
The Lancaster Field is located West of Shetland, approximately 70 kilometres southwest of the Clair Field and
approximately 15 kilometres to the southeast of the Foinaven and Schiehallion Fields within Blocks 205/21a,
205/22a and 205/26b in Frontier Licence P1368 Central. The licence is owned by Hurricane GLA Limited with 100%
interest. Hurricane GLA Limited is a 100% wholly owned subsidiary of Hurricane Energy PLC. Hurricane Energy PLC
operates Frontier Licence P1368 Central and the Lancaster Field on behalf of Hurricane GLA Limited. Hereafter
“Hurricane” or “Company” shall be used to reference either one or more of Hurricane Energy PLC and Hurricane
GLA Limited, as the context requires.
Field Description
The reservoir at the Lancaster Field is comprised of fractured basement consisting of both igneous and
metamorphic rocks of Precambrian age at a depth of approximately 1000 metres below sea level at its shallowest
point. This basement reservoir is overlain by a sequence of Mesozoic sediments which onlap onto the flanks of the
basement high which are overlain by a thick sequence of late Cretaceous marine shales which act as a regional seal.
The Lancaster Field is a 4-way dip structure with hydrocarbon fill controlled by dip spill to the east. The oil present
within the reservoir is 38° API with a gas oil ratio (GOR) in the range of 390 - 420 scf/stb based on a single stage
flash to stock tank conditions.
1.4.1. Installation
Figure 1:3 - Disconnectable Turret Buoy (DTB) position post FPSO removal
Bluewater Lancaster Production (UK) Ltd. will carry out the demobilisation of the Aoka Mizu FPSO under the existing
Production, Operation and Services contract with Hurricane GLA Limited.
2.2. Wells
Decommissioning the Aoka Mizu FPSO will generate a quantity of waste which Hurricane and Bluewater will manage
using environmentally acceptable methods for managing wastes in line with the Waste Framework Directive and
principles of the waste hierarchy.
Surface Facility Description: The Aoka Mizu is a Bluewater designed, owned and operated FPSO. The FPSO was
built in 2008, integrating a turret moonpool, a foundation grillage to support process topsides and hull upgrades
for higher ultimate strength and fatigue capacity.
The FPSO operated on the Ettrick and Blackbird Fields, UKCS, from 2009 until 2016. Following a period of lay-up in
Gdansk (Poland), the FPSO was refurbished and upgraded for redeployment to the Lancaster Field at the Drydock
World Dubai shipyard in 2017-2018.
The FPSO is equipped with a DTB, located aft of the accommodation enabling passive weathervaning. The mooring
legs are connected to the DTB and are arranged in a 3x4 configuration, optimised with respect to prevailing wind
conditions. The Aoka Mizu commenced production from the Lancaster Field in 2019.
The main dimensions of the FPSO are set out in Table 3-1 while a picture of the Aoka Mizu if provided in Figure
3:2.
Dimension Metres
Length 248.1
Breadth 42.0
Depth 21.2
Table 3-1 - FPSO Dimensions
Section 2 of this decommissioning programme describes all items and substances relating to the Lancaster FPSO to
be removed from the Lancaster Field. No items or substances in the Lancaster Field, other than detailed in Section
2 will be removed at this time and will be the subject of a further decommissioning programme. The
decommissioned waste and FPSO vessel (if not reused) will be recycled or disposed of in compliance with the
standards comparable with those set under the applicable laws of the United Kingdom.
Preparation:
Other hazardous NORM, LSA scale, any radioactive Transported onshore for disposal by appropriate
materials material, instruments containing means, only minimal quantities expected.
heavy metals, batteries
Table 3-2 - Preparation of Surface Facility for Removal
Removal Methods:
Method Description
Disconnection and complete removal Following the flushing, cleaning and disconnection of all risers
and umbilical’s and putting in place appropriate barriers for
retention of hydrocarbons the FPSO using its own systems shall
disconnect and lower the DTB from its moonpool.
The FPSO will then transit outside the Lancaster Field’s FPSO
500m Safety Zone, at which point the FPSO is considered to be
redelivered to the owner.
The DTB with connected mooring system, risers and umbilical
will be at a depth of approximately 20m below mean sea level
following disconnection and will remain in this condition
pending subsea and mooring system decommissioning.
Marine growth Marine growth is expected, however will not impact the demobilisation operations.
NORM/LSA Scale NORM contaminated items will be decontaminated at an approved facility prior to disposal.
All NORM materials will be disposed of at a suitably permitted facility.
Seabed The Lancaster Field is situated at the edge of the continental shelf to the west of Shetland.
Water depths over the whole of the Lancaster Field range from 134 m to around 180 m, the
water depth at the Aoka Mizu FPSO location is approximately 150 m. Lancaster is situated at
the upper edge of an area on the continental shelf known as the ‘iceberg ploughmark zone’.
This area is characterised by the presence of furrows in the seabed caused by the grounding
of icebergs in previous glacial periods. The seabed generally comprises of coarse sandy
sediments interspersed with more gravelly areas supporting patches of cobbles and
boulders.
Fish The Lancaster Field lies within spawning areas for Norway pout, a species that spawns during
the winter and early spring (January to April), and sand eels which spawn from November to
February. The Lancaster field is also located within year round nursery grounds for spurdog
(high intensity), herring, whiting, blue whiting, ling, hake, monkfish (high intensity), sandeels,
mackerel (high intensity) and Norway pout (Coull et al, 1998; Ellis et al, 2012).
Fisheries The Lancaster Field lies in ICES rectangle 49E6, fishing effort is moderate compared to other
ICES rectangles in Scottish waters. Effort is spread throughout the year but tends to be
focused from November to May and in September.
Marine The Lancaster Field is situated near the edge of the Faroe-Shetland Channel. The waters of
Mammals the channel support important and diverse populations of whales, dolphins and porpoises.
The area is understood to provide feeding grounds, breeding and nursery areas and
migration routes for a range of cetacean species. Certain species are resident in the shallower
waters of the shelf where they feed all year round such as minke whales, smallest of the
larger filter feeding whales, white beaked dolphins and harbour porpoises. White sided
dolphins and larger species such as killer whales and long finned pilot whales preferentially
inhabit the deeper waters beyond the continental shelf and are rarer in the shallow waters
around the Aoka Mizu FPSO. The Lancaster field is located in the relatively shallow waters of
the continental shelf, where minke whales, white-beaked dolphins, and harbour porpoises
feed year round.
Birds Seabirds present within the immediate vicinity of the Aoka Mizu FPSO include Fulmar
(Fulmarus glacialis), Gannet (Sula bassana), Shag (Phalacrocorax aristotelis), Arctic Skua
(Stercorarius parasiticus), Great Skua (Stercorarius skua), Great Black-Backed Gull (Larus
marinus), Kittiwake (Rissa tridactyla), Common Tern (Sterna hirundo), Arctic Tern (Sterna
paradisea), Guillemot (Uria aalge), Razorbill (Alca torda), Black Guillemot (Cepphus grylle)
and Puffin (Fratercula arctica). All these species have breeding populations within the SEA 4
area, which exceed one percent of their European population, with most of these species
having major breeding colonies, in terms of their biogeographic population, located on
Shetland, Orkney and the north coast of Scotland.
The Seabird Oil Sensitivity Index (SOSI) identifies areas at sea where seabirds are likely to be
most sensitive to surface pollution; the SOSI values in Block 205/21a is low throughout the
year except for periods of high sensitivity in January and November with no data available
for this block in December.
Onshore All onshore facilities used during the decommissioning of the Lancaster EPS FPSO, including
Communities offload ports and recycling facilities, will comply with all permitting and legislative
requirements.
Other Users of The Lancaster Field is in what is described as an open water location and the level of shipping
the Sea traffic is quite low although there has been an increase in routes since the drilling operations
at Lancaster began in 2009. The majority of this traffic is made up of support vessels for the
offshore industry.
The Lancaster Field does not fall within a Ministry of Defence (MoD) designated Practice and
Exercise Area (PXEA), the nearest practice area is approximately 100km to the south.
However, licensing conditions relevant to the Lancaster field indicate the requirement to
consult with MoD regarding training areas. In addition, an annual multi-disciplinary training
and readiness exercise is known to take place in waters west of Scotland (Exercise Joint
Warrior).
Atmosphere Although offshore winds around the FPSO may blow from any direction, southwesterly winds
are most prevalent. In spring (March to May), winds are recorded from all directions with
those from the southeast slightly more dominant (Met Office, 2009). Gale force winds have
been recorded, but winds of 11 to 27 knots are most common. Conditions are more settled
during the summer (June to August); winds up to 21 knots are most common at this time.
Wind strength increases in autumn (September to November) with gale forces winds from
the southwest encountered regularly. Conditions are roughest in winter (December to
February) with a significant proportion of winds in excess of 33 knots. The wind regime at
this time is dominated by winds from the southwest.
Table 4-1 - Environmental Sensitivities
Floating Facility Removal There will be no impact on the seabed from the removal
of the FPSO as all infrastructure will remain in the water
column attached to the DTB until the subsea and
mooring systems are decommissioned.
Floating Facility Removal It is anticipated that there will be localised effects on air
quality from the project due to increased vessel use but
it is not anticipated that there will be a significant
impact on air quality on a wider scale.
UK HSE None.
Statutory Consultations
National Due to the geographical area of these assets been in Scottish Waters
Federation of the National Federation Fishermen’s Organisation (NFFO) have no
Fishermen’s comments regarding the planned decommissioning program, as the
Organisations Scottish Fishermen’s Federation who we work closely with are best
placed to comment and raise any concerns if required.
6. Programme Management
6.1. Project Management and Verification
Hurricane Asset Management Team will manage and liaise with Bluewater for the removal of the FPSO Aoka
Mizu from the Lancaster Field. Standard procedures for operational control, hazard identification and
management will be used.
Hurricane, together with Bluewater, will monitor and track the process of consents and the consultations
required as part of this process. Any changes in detail to the offshore removal programme will be discussed and
agreed with OPRED.
There is no requirement for post decommissioning debris clearance or verification following FPSO removal, this
will be carried out upon completion of the Wells Subsea, Pipelines and Mooring System Decommissioning
Programme.
A full-scale post decommissioning environmental seabed and pipeline survey of the Lancaster field will be
carried out following full decommissioning of the field. Results of this survey will be available once the work is
complete, with a copy forwarded to OPRED.
6.3. Schedule
A nominal decommissioning schedule is provided in Figure 6:1 based around a nominal cessation of production
(CoP) date of Q2 2023. The actual timing of CoP will depend on many factors including production performance,
oil price.
6.4. Costs
In accordance with the OPRED Guidelines, a close out report will be submitted to OPRED within one year of the
completion of this FPSO Decommissioning Programme.
The report will detail the scope performed and explain any major variances from the programme.
A full field close out report will be submitted to OPRED within one year of the completion of full field
decommissioning.
Following FPSO decommissioning a guard vessel will remain on site to monitor and ensure the safety of the DTB
prior to its decommissioning. The guard vessel will remain on station until the DTB is removed from the field.
The earliest opportunity for the subsea decommissioning programme will be the summer season following
removal of the FPSO. Therefore, the DTB will remain submerged in the water column for a minimum of one year
post removal of the FPSO, refer to Appendix 4 TMS Buoy Post FPSO Departure Risk Assessment for the Risk
Assessment.
The subsea decommissioning programme will be executed in line with OGA Stewardship Expectation 10 Cost
Effective Decommissioning, however it is expected this will be within 3 years of removal of the FPSO.
Post-decommissioning site surveys for the subsea installations and moorings will be covered under the
Decommissioning Programme for the subsea infrastructure and wells.
7. Supporting Documents
Not applicable, the FPSO decommissioning does not require support of an environmental appraisal or
comparative assessment.
Document
Title
Number