Generator Installation - AHA
Generator Installation - AHA
RAC CHART
H = HIGH RISK
This is the overall risk assessment code for this activity.
*Probability is the likelihood that an incident would occur and is identified as: Frequent,
M = MODERATE RISK
Likely, Occasional, Seldom, or Unlikely after controls are put in place.
**Severity is the outcome/degree should an incident occur and is identified as: Catastrophic,
L = LOW RISK
Critical, Marginal, or Negligible after controls are in place.
3. Inspect the crane, rigging and all 3a. A competent person shall inspect all equipment prior to use.
3a. Crane or hoisting equipment failure M
other hoisting equipment Whenever any crane and/or hoisting equipment is found to be
This AHA has been reviewed by M.C. Dean for general compliance with the jobsite safety requirements. M.C. Dean is responsible for reviewing this AHA with all personnel involved with the
Definable Feature of Work (DFOW) on a regular basis and must notify the GC and adjust the AHA as necessary whenever the plan for performing the DFOW is modified or following an
unplanned event.
Page 1 of 9
unsafe, or whenever a deficiency that affects the safe operation of
the crane and/or hoisting equipment is observed, the affected
equipment shall be immediately taken out of service by the
operator, tagged out of service, and its use prohibited until unsafe
conditions have been corrected.
4b. When positioning the trailers into their location for crane
access always use a spotter to back the trucks up. Ensure
4b. Drivers obstructed line of sight deliveries are coordinated with other trades and the barricaded L
staging area is clear prior to delivery trucks arriving.
5. Rigging the generator package and 5a. Rigging equipment shall be inspected as specified by the
items: manufacturer, by a competent person, before use on each shift
and as necessary during its use to ensure that it is safe.
1. Base 5a. Defective rigging L
Defective rigging shall be tagged out and removed from service.
2. Gen Set Note: Only shackles made in the USA will be used.
5b. Rigging failure due to improper use 5b. The use and maintenance of rigging equipment shall be in L
This AHA has been reviewed by M.C. Dean for general compliance with the jobsite safety requirements. M.C. Dean is responsible for reviewing this AHA with all personnel involved with the
Definable Feature of Work (DFOW) on a regular basis and must notify the GC and adjust the AHA as necessary whenever the plan for performing the DFOW is modified or following an
unplanned event.
Page 2 of 9
accordance with recommendations of the rigging manufacturer
and the equipment manufacturer. Identify the weight of the object
to be lifted. Rigging equipment shall not be loaded in excess of its
recommended safe working load.
Page 3 of 9
and barricades with clear signage should be erected until the
equipment is set up and deemed safe.
6a. Crane and hoisting equipment shall be operated only by
designated qualified personnel with a current certification by an
accredited crane operator testing organization per OSHA 29 CFR
7a. Unqualified operators M
1926.1427. Operator shall not leave crane / controls for any
reason during the pick and place operation.
7. Hoisting the generator package in 6c. An operational test shall consist of a demonstration that the
the below sequence: test load and the selected rigging can be safely lifted,
7c. Crane/hoisting equipment failure L
1. Base maneuvered, controlled, stopped, and landed at radius desired to
2. Gen Set set the electrical equipment. Only lift from approved pick points.
6e. Loads shall not be lifted over personnel nor shall personnel
7e. Crushed by falling objects M
position themselves under suspended loads.
7f. Electrocution from contacting overhead 6f. Adequate clearances shall be maintained from electrical
electrical lines sources (10' clearance required for lines up to 50 kV). M
6g. The operator shall respond to signals from the person who is
directing the lift or an appointed signal person. One qualified
7g. Operator's view obstructed signal person shall be designated to communicate understood L
signals with the crane operator - he/she shall be trained in
signaling.
This AHA has been reviewed by M.C. Dean for general compliance with the jobsite safety requirements. M.C. Dean is responsible for reviewing this AHA with all personnel involved with the
Definable Feature of Work (DFOW) on a regular basis and must notify the GC and adjust the AHA as necessary whenever the plan for performing the DFOW is modified or following an
unplanned event.
Page 4 of 9
6h. A standard signal system shall be used on all cranes and
hoisting equipment (by hand, voice, audible, or comparable
7h. Communication failure signals). Manual (hand) signals may be used when the distance L
between the operator and signal person is not more than 100'.
8b. All hand and power tools shall be inspected prior to each use
for proper guards, attachments (secondary handle), electrical
9. Anchor generator to base cords, ground prongs and damaged insulation. Tools shall be
9a. Use of power tools (drill) L
used in accordance with manufacturer’s recommendations and
instructions.
10. Anchor intake penthouse, intake 10a. Access to roof, Falls from elevated 9a. Utilize mechanical means such as boom lift/aerial lift when L
hood, discharge baffle, EPOD heights working at heights to minimize ladder usage. If a ladder must be
(scrubber) and intake rain shields on used it needs to be justified/determined that no other means of
top of generator enclosure access can be used.
Page 5 of 9
out/removed from service. If installing sleeves from a ladder it
must be inspected and defective ladders tagged out of service,
employees must maintain 3 points of contact while
ascending/descending.
11. Installation / anchor enclosure 10d. All material secured to the generator: scrubber and or
intake hood, discharge baffle, EPOD 11d. Loose material (material falling) exhaust system shall be secured in place (bolted down) prior to
releasing any rigging or being unsecured. L
(scrubber) and intake rain shields
10e. If a ladder must be used a Ladder Permit needs to be
completed and signed off by WA. All ladders shall be inspected
prior to each use. The appropriate size ladder shall be selected
11e. Portable ladder use for adequate access to the work. The top step and cap of the
ladder shall not be stepped on for access to work. Step ladders L
shall be used for their designed purpose and not used as
extension ladders.
Page 6 of 9
11a. Perform periodic housekeeping through the day and do not
12a. Slips/Trips/Falls let material/debris accumulate on the jobsite. L
TASK-SPECIFIC PPE:
Safety-Toe
ANSI Z-89.1 ANSI Z-87.1 TYPE: ANSI Class II
Construction-Grade WB
Other:
Equipment Cleaning Permit Excavation/Underground Action Plan Excavation/Utility Permit Fall Protection Plan / Rescue Plan
Near Energized Work Permit Silica Exposure Control Plan Steel & Precast Erection Plan Other:
EQUIPMENT USED TRAINING REQUIREMENTS / COMPETENT OR QUALIFIED PERSONS NAMES INSPECTION REQUIREMENTS
This AHA has been reviewed by M.C. Dean for general compliance with the jobsite safety requirements. M.C. Dean is responsible for reviewing this AHA with all personnel involved with the
Definable Feature of Work (DFOW) on a regular basis and must notify the GC and adjust the AHA as necessary whenever the plan for performing the DFOW is modified or following an
unplanned event.
Page 7 of 9
CREW SIGNATURES / VERIFICATION OF REVIEW
Name (Print) Signature Date Name (Print) Signature Date
This AHA has been reviewed by M.C. Dean for general compliance with the jobsite safety requirements. M.C. Dean is responsible for reviewing this AHA with all personnel involved with the
Definable Feature of Work (DFOW) on a regular basis and must notify the GC and adjust the AHA as necessary whenever the plan for performing the DFOW is modified or following an
unplanned event.
Page 8 of 9
This AHA has been reviewed by M.C. Dean for general compliance with the jobsite safety requirements. M.C. Dean is responsible for reviewing this AHA with all personnel involved with the
Definable Feature of Work (DFOW) on a regular basis and must notify the GC and adjust the AHA as necessary whenever the plan for performing the DFOW is modified or following an
unplanned event.
Page 9 of 9