DDDDDDDDD

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

PROJECT LIMIT PROJECT LIMIT

E 278116.387 E 278316.485

N
N 2704079.420 N 2704072.742

PROJECT EXTENSION

PROJECT EXTENSION
SERVICE
CHILLERS
CHILLERS
TES-P5-01 TES-P6-01
THERMAL ENERGY
STORAGE TANK Truck Truck THERMAL ENERGY
Ø5.5 m &7m HIGH STORAGE TANK

BLOCK
Ø5.5 m & 7m HIGH

GENERATORS
GENERATORS

E=278114.002
N=2704007.909
PHASE-3 E=278314.098
N=2704001.220

ELECTRICAL ELECTRICAL SHADED

HUAWEI DATA CENTER - ABU DHABI


DATA SHADED
WALK WAY
BLOCK CENTER BLOCK WALK WAY

-1 -2
SHADED
WALK WAY

DX COOLING UNITS SCHEDULE PCHWP-P4-04

PCHWP-P4-03

ROOM HAP OUTPUT SELECTION


PCHWP-P4-02

PHASE 2
DATA CENTER PD1

EXISTING STRUCTURE PD1

Unit Unit Unit Air CU CoP Indoor unit


On Coil Temp Off Coil
PD1

PD1

Total Sensible On Coil Temp Off Coil Temp Air Flow DUTY STAND ESP DX Input Indoor Outdoor DUTY STAND Outdoor CU Total Indoor Unit VRV Outdoor Outdoor Unit
Sl. Area Total Sensible Temp Flow Input (Rated */ Remark Model VRV Modules
Room Name Load Load (DB/WB) (DB/WB) (L/s) Indoor Unit Tag QTY BY QTY (DB/WB) (DB) range Power Unit Type Unit Tag QTY BY QTY Temp (DB) Capacity Dimensions System Model Dimensions
No. Load Load (L/s) Power Tested**)
m2 (KW) (KW) °C °C (L/s) (N) (N) (KW) (KW) °C °C (L/s) Pa (kW) (N) (N) °C (kW) (kW) W X H X D mm W X H X D mm PHASE 1
DATA CENTER
EXISTING STRUCTURE

POD5 - Load Summary


SHADED
SHADED WALK WAY
WALK WAY

SHADED
SHADED PARKING
WALK WAY

PROJECT LIMIT

Wall
PLOT LIMIT E 278307.7590
E 278107.6630
N 2703811.5890

4 NOS 150MM
PVC SLEEVE
N 2703818.2776 FIXED

2 Packing / Unpacking 83 7.4 6.6 24.7 / 17.2 13.0 / 12.3 474 DX-P5-01 to 02 2 0 4.9 3.9 24.7 / 17.2 11.9 250 0.033 Mounted FXAQ50PVER 1,050 x 290 x 238

Ceiling KEY PLAN:


5 Corridor POD5 201 11.7 11.4 24.6 / 16.9 13.2 / 12.5 829 DX-P5-03 to 06 4 0 6.1 4.7 24.6 / 16.9 13.0 333 0.111 8.64 3.52 / 3.88 FXHQ63A 1,270 x 235 x 690 RXYTQ12UYF 1,240 x 1,685 x 765
Suspended CU-P5-01A
1 0 48.8 37.7 VRF System RXYTQ22UYF
CU-P5-01B
4 NOC Room 38.7 4.4 3.7 24.9 / 17.7 13.3 / 12.6 265 DX-P5-07 1 0 6.5 4.8 24.9 / 17.7 13.7 350 30-150 0.095 Ducted 8.29 3.90 / 4.11 FXSQ63A 1,000 x 245 x 800 RXYTQ10UYF 1,240 x 1,685 x 765

3 DCIM Server Room 19.6 9.5 9.4 27.9 / 18.7 15.0 / 14.1 605.0 DX-P5-08 1 0 11 8.9 27.9 / 18.7 14.4 533 40-150 0.157 Ducted FXSQ100A 1,400 x 245 x 800
Wall DC Pro Comments:
6 BMS Room 8.5 4.2 3.8 27.9 / 19.2 14.9 / 14.1 244 DX-P5-10 to 11 1 1 5.7 4.4 27.9 / 19.2 13.6 250 0.033 FXAQ50PVER 1,050 x 290 x 238
Mounted 1- All the equipment schedules shall be updated as
CU-P5-03A per approved material submittals when any change
7 Electrical Room 10.7 6.6 6.1 27.9 / 19.0 15.0 / 14.1 393 DX-P5-12 to 13 1 1 9 6.9 27.9 / 19.0 13.4 383 40-150 0.121 Ducted 8.64 3.52 / 3.88 FXSQ80A 1,000 x 245 x 800 RXYTQ12UYF 1,240 x 1,685 x 765
CU-P5-03B
1
occurs.
1 48.8 43.4 VRF System RXYTQ24UYF
CU-P5-04A
8 Telecom Room 10.2 8.8 8.3 21.5 / 15.6 12.5 / 11.9 771 DX-P5-14 to 15 1 1 12.5 9.3 21.5 / 15.6 9.8 650 50-150 0.243 Ducted CU-P5-04B 8.64 3.52 / 3.88 FXSQ140A 1,550 x 245 x 800 RXYTQ12UYF 1,240 x 1,685 x 765

DOCUMENT REVIEW STATUS


9 Pump Room 120 15.7 15.2 27.8 / 18.7 14.9 / 14.1 985 DX-P5-16 to 19 2 2 11 8.8 27.8 / 18.7 14.3 533 40-150 0.157 Ducted FXSQ100A 1,400 x 245 x 800
CODE A - ACCEPTED
POD6 - Load Summary X CODE B - ACCEPTED WITH COMMENTS
CODE C - REVISE AND RESUBMIT
Wall
1 Storage Room 46 2.9 2.2 24.7 / 18.2 13.1 / 12.5 156 DX-P6-01 1 0 4.3 3.1 24.7 / 18.2 12.2 200 0.02 FXAQ40PVER 1,050 x 290 x 238 CODE D - REJECTED
mounted
CODE E - ISSUED FOR INFORMATION
3 Reception 63.2 14.3 14 24.6 / 16.6 12.7 / 12.0 984 DX-P6-02 to 03 2 0 9.5 7.8 24.6 / 16.6 12.6 533 40-150 0.157 Ducted 8.64 3.52 / 3.88 FXSQ100A 1,400 x 245 x 800 RXYTQ12UYF 1,240 x 1,685 x 765
PERMISSION TO PROCEED SHALL NOT RELIEVE THE
CU-P6-01A SUPPLIER OF ALL RESPONSIBILITY CONCERNING
4 Security Room 16 1.8 1.5 24.9 / 17.8 13.4 / 12.7 111 DX-P6-04 1 0 2.6 1.9 24.9 / 17.8 14.7 150 30-150 0.041 Ducted 1 0 48.8 37.7 8.29 3.90 / 4.11 VRF System FXSQ25A 550 x 245 x 800 RXYTQ22UYF RXYTQ10UYF 1,240 x 1,685 x 765 SUBMITTED DESIGN DETAILS, SHOP DRAWINGS,
CU-P6-01B CALCULATIONS, METHOD STATEMENTS, PROJECT
Wall ANALYSIS, TEST METHODS OR MATERIALS AND FROM
7 Cylinder Room 40 1.9 1.8 24.7 / 17.1 13.2 / 12.5 128 DX-P6-05 1 0 2.5 2.1 24.7 / 17.1 13.2 / 12.5 133 0.028 mounted FXAQ25PVE 795 x 290 x 238 FULL COMPLIANCE WITH THE PROJECT AND END USER
REQUIREMENTS.
Ceiling
8 Corridor POD6 113 7.8 7.5 24.7 / 17.1 13.4 / 12.7 555 DX-P6-06 to 08 3 0 6.2 4.7 24.7 / 17.1 13.1 333 0.111 Suspended FXHQ63A 1,270 x 235 x 690
Patrick BC 06-Jan-2021
CLIENT / CLIENT CONSULTANT
SUDLOWS COMMENT REV.-01- STATUS B REPRESENTATIVE. DATE

1. Electrical loads for equipments shall be


HUAWEI DATA CENTER - ABU DHABI
DX COOLING UNITS SCHEDULE verified as per approved material
ROOM HAP OUTPUT SELECTION submittal and to be coordinated with
Total Sensible
On Coil Off Coil
Air Flow DUTY STAND
Unit Unit On Coil Off Coil
Unit Air DX Input DUTY STAND
Outdoor
CU Total CU Input Indoor Selection
Indoor Unit
Dimensions from
Outdoor Selection Outdoor Unit Electrical discipline.
Area Temp Temp Total Sensible Temp Temp Indoor Unit Outdoor Unit Temp CoP * Remark
SL. No Room Name Load Load (L/s) Indoor Unit Tag QTY BY QTY Flow (L/s) Power QTY BY QTY Capacity Power from Daikin from Daikin Dimensions
m2 (DB/WB) (DB/WB) Load Load (DB/WB) (DB) Type Tag (DB) Daikin

POD5 ‐ Load Summary


(KW) (KW) °C °C (L/s) (N) (N) (KW) (KW) °C °C (L/s) (kW) (N) (N) °C (kW) (kW) W X H X D mm
2. All models shall be as per approved SHOP DRAWING FOR APPROVAL Thangaraj
01 19-12-2020
material submittal. 00 05-09-2020 SHOP DRAWING FOR APPROVAL Thangaraj
27.0 / Standard
1 DCIM Server Room 19.6 9.5 9.4 27.9 / 18.7 15.0 / 14.1 605.0 0 1 12.36 11.21 13.5 686 0.34 Ducted DX 1 0 48.8 _ 4.96 3.41 FDMRN50AV1K9 1569 x 378 x 541 RR50AY1K9 1030 x 852 x 400
19.0 DX
Rev. No. Date Description Revised by

27.0 / Wall Mounted


3. Any Equipment selection deviations
2 MV Room 47 8.4 8.1 1 5.09 4.38
19.0
14.6 295 0.085
DX
1 48.8 _ 2.29 3.72 DX FTKM24PVM 1,050 x 340 x 259 RKM24PVM 930 x 695 x 350
from Employer Requirements and the Project :

APOLLO-03 DATA CENTER


POD6 ‐ Load Summary approved specifications will not be
accepted unless prior approval is sought
1 MV Room 47 8.4 8.1 1 5.09 4.38
27.0 /
19.0
14.6 295 0.085
Wall Mounted
DX
1 48.8 _ 2.29 3.72 DX FTKM24PVM 1,050 x 340 x 259 RKM24PVM 930 x 695 x 350
from the Engineer and Client team,
Client :
PIVOT
PIVOT ASSET HOLDING RSC LTD
contractor to confirm any Deviation and Abudhabi -UAE
Client Consultant :
shall obtain client team approval prior to
proceed.
HUAWEI DATA CENTER - ABU DHABI
DX COOLING UNITS SCHEDULE Client Consultant :

ROOM HAP OUTPUT SELECTION

Unit Unit Unit Air CU


Total Sensible On Coil Temp Off Coil Temp Air Flow DUTY STAND On Coil Temp Off Coil DX Input DUTY STAND Outdoor CU Total UNIT DIMENSIONS Design & Build Contractor
Area Total Sensible Flow Input CoP * Remark MODEL NO
Load Load (DB/WB) (DB/WB) (L/s) QTY BY QTY (DB/WB) Temp (DB) Power QTY BY QTY Temp (DB) Capacity WXHXD mm
Sl. Load Load (L/s) Power
Room Name Indoor Unit Tag Indoor Unit Type Outdoor Unit Tag
No.
m2 (KW) (KW) (L/s) (N) (N) (KW) (KW) (L/s) (kW) (N) (N) (kW) (kW)
SUDLOWS DMCC
DRAWINGS REVIEW STAMP
Project : A100 HUAWEI INTERNATIONAL CO., LTD
POD5 - Load Summary ☐ A - Accepted Lead Design Consultant :
☐ B – Accepted with Comments

11 LV Room 171 46.6 46.2 27.8 / 18.6 14.9 / 14.0 2977 DX-P5-22 to 23 1 1 70.83 51.95 27.0 / 19.0 16.9 4248 3.0 Packaged Unit 1 1 48.8 _ 31.44 3.49 PACKAGE UNIT UATQ300CGXY1 2410 x 1950 x 2030 ☐ C – Revise & Resubmit
☐ D – Rejected

P.O. BOX 22851 SHARJAH, TEL. : 971 6 5566880 FAX. : 971 6 5566881
Reviewed By: NPM/OL Date:10-01-2021
POD6 - Load Summary The comments and / or approval in no way relieve the contractor from his
P.O. BOX 99352 DUBAI, TEL. : 971 4 3432110 FAX. : 971 4 3432113
P.O. BOX 110512 ABU DHABI, TEL. : 971 2 6316782 FAX. : 971 2 6316783
obligation under the contract to ensure conformance to the specification and
employer requirement. Any deviations from the specification and employer P.O. BOX 18927 RIYADH, TEL. : 966 1 460 3301 FAX. : 966 1 4603302
requirement found subsequent to approval shall be corrected by the contractor
to the satisfaction of the engineer and client team
10 LV Room 171 45.5 45.2 27.8 / 18.6 14.9 / 14.0 2909 DX-P6-11 to 12 1 1 70.83 51.95 27.0 / 19.0 16.9 4248 3.0 Packaged Unit 1 1 48.8 _ 31.44 3.49 PACKAGE UNIT UATQ300CGXY1 2410 x 1950 x 2030 Any changes on site are to be captured accordingly in another revision of the Civil consultant & Architect of Record :
contractors Shop Drawing
The co-ordination between the different disciplines is contractor responsibility

ACE INTERNATIONAL CONSULTING ENGINEERS


P.O. BOX 47302,
Abu dhabi-U.A.E.
Tel: +971 2 644 7764
Fax: +971 2 644 7746

HUAWEI DATA CENTER ‐ ABU DHABI


HUAWEI DATA CENTER ‐ ABU DHABI FANS SCHEDULE
MEP Contractor :
IN ROW COOLING UNITS SCHEDULE Motor Full Load Electrical Total
Sn. Air Flow (LPS) ESP (Pa) SFP Qty
Ref Location Fan Type Model Rating Current Characteristics Weight LAITH ELECTROMECHANICAL LLC.
NO. P.O.Box : 47391, Abu Dhabhi - UAE
ROOM CALCULATED OUTPUT SELECTION Req'd Actual Req'd Actual kW Amp V/Ph/Hz W/l/s Nos. kg
Tel : 02 5537571, Fax : 02 5537579
Email: [email protected]
Indoor DYNAIR TA-HT: Ducted Axial Fan rated at 400°C/2hrs. w/ Feet support (Long Cased & Hot Dip Galvanized) and External Terminal Box
Web : www.laithllc.com
Net On Coil Off Coil Chilled Unit Unit Chilled Outdoor Unit Outdoor
Total Temp Temp Air DUTY STANDBY Unit Total On Coil Temp Off Coil Temp Unit Air Unit Unit
CLEAN AGENT PURGE FANS SCHEDULE
Sensible Water Sensible Water Flow Input Remark
Area Load (DB/WB) (DB/WB) Input POD-5 Axial Fan rated at
Sl. No. Room Name Load Flow Flow QTY QTY Indoor Unit Tag Load (DB/WB) (DB/WB) Flow (L/s) Power 1 EAF-PUR-P5-01 TA-HT-400-150-6-6-38°T, 1.80kW, 2P, 415V/50Hz 1,607 1,613 300 302 1.8 2.98 415/3/50 0.81 1 40 CIVIL Contractor :
Load Rate Tag Power Data Hall-B 400°C/2hrs
Rate
Packing / Unpacking Axial Fan rated at
2 EAF-PUR-P5-02 TA-HT-400-240-12-12-22°T, 0.55kW, 4P, 415V/50Hz 159 161 250 236 0.55 1.36 415/3/50 1.36 1 36
m2 (KW) (KW) °C °C (L/s) (L/s) (N) (N) (KW) (KW) °C °C (L/s) (L/s) (W) (W) Room 400°C/2hrs
POD5 ‐ Equipment Schedule POD-5 Axial Fan rated at TA-HT-400-240-12-12-33°T, 1.73/0.43kW, 2/4P, 1.73 /
3 EAF-PUR-P5-03 1292 / 646 1,311 / 649 350 360 / 88 3.8 / 1.2 415/3/50 1.14 / 0.35 1 40 P.O.Box : 112524, Abu Dhabhi - UAETel : +971 2 5558688,
LV & UPS Room 400°C/2hrs 415V/50Hz 0.43
35.1 33.3 35 / 20.6 23.72 / 16.94 2,500 NA 15 With Humidifier Fax : +971 2 5558689 Email: [email protected] Web : www.telal.co
1 MMR Room 1 25 24.3 22.2 - - - - 1 1 POD-6 Axial Fan rated at
35.1 33.3 35 / 20.6 23.72 / 16.94 2,500 NA 15 With Humidifier 4 EAF-PUR-P6-01 TA-HT-400-150-6-6-38°T, 1.80kW, 2P, 415V/50Hz 1,607 1,613 300 302 1.8 2.98 415/3/50 0.81 1 40
Data Hall-B 400°C/2hrs
POD6 ‐ Equipment Schedule Drawing Title :
POD-6 Axial Fan rated at TA-HT-400-240-12-12-33°T, 1.73/0.43kW, 2/4P, 1.73 /
35.1 33.3 35 / 20.6 23.72 / 16.94 2,500 NA 15 With Humidifier 5 EAF-PUR-P6-02 1292 / 646 1,311 / 649 350 360 / 88 3.8 / 1.2 415/3/50 1.14 / 0.35 1 40
LV & UPS Room 400°C/2hrs 415V/50Hz 0.43
1 MMR Room 2 25 24.1 22 - - - - 1 1
35.1 33.3 35 / 20.6 23.72 / 16.94 2,500 NA 15 With Humidifier HVAC EQUIPMENT
VENTILATION FANS
2 MMR Room 5 20 33.7 31.6 1 1
35.1 33.3 35 / 20.6 23.72 / 16.94 2,500 NA 15 With Humidifier SCHEDULE
- - - - POD-5 Transformer Axial Fan rated at
35.1 33.3 35 / 20.6 23.72 / 16.94 2,500 NA 15 With Humidifier 6 EF-P5-01 to 02 TA-HT-710-150-6-6-32°T, 9.0kW, 2/4P, 415V/50Hz 5937 6,504 450 466 9 14.39 415/3/50 1.02 2 125
Room 400°C/2hrs
35.1 33.3 35 / 20.6 23.72 / 16.94 2,500 NA 15 With Humidifier
3 Staging Room 24 56.8 52.3 - - - - 2 1 35.1 33.3 35 / 20.6 23.72 / 16.94 2,500 NA 15 With Humidifier POD-6 Transformer Axial Fan rated at Designed Drawn Checked Scale Date
7 EF-P6-01 to 02 TA-HT-710-150-6-6-32°T, 9.0kW, 2/4P, 415V/50Hz 5797 6,504 450 466 9 14.39 415/3/50 1.02 2 125
35.1 33.3 35 / 20.6 23.72 / 16.94 2,500 NA 15 Room 400°C/2hrs
Patrick BC Shamees Thangaraj N.T.S 19-12-2020

Drawing Number Rev.

HWI-APO3-ME-SDS-1601-01 01

SHEET SIZE = 821 x 574 mm PLOTTING SCALE 1 : 1

You might also like