Sewage Treatment Plant 350CmD (MBBR)
Sewage Treatment Plant 350CmD (MBBR)
Sewage Treatment Plant 350CmD (MBBR)
Attention :
Project : Proposed Sewage Treatment Plant
Location : Bicol
Owner :
Subject : Proposed Supply and Installation of Electro-Mechanical Sewage Treatment Plant 350CmD
A. SCOPE OF WORKS
UNIT RATE
ITEM NO. ITEM DESCRIPTION UNIT QTY TOTAL AMOUNT
MATERIAL LABOR OTHERS TOTAL
I PRELIMINARIES
Mobilization/Demobilization 1.00 ITEM 150,000.00
Temporary Facilities 1.00 ITEM 60,000.00
Testing and Commissioning 1.00 ITEM 280,000.00
As built design, Project Mngmnt., Supervision 1.00 ITEM 250,000.00
sub-total I 740,000.00
II Electro-Mechanical Works
Bar Screen ,angle bar 1x1x6 mtr length ss 304 1.00 LOT 155,600.00 31,120.00 3,112.00 189,832.00 189,832.00
2 stage barscreen ss 304, round bar 10mm ss 304
Air Blower
Positive displacement Rotary Tri loob Blower 3.00 LOT 385,000.00 77,000.00 7,700.00 469,700.00 1,409,100.00
Discharge pressure: 380 millibars
5.5kw, 220/440V, 60Hz, 3phase
Disc Type Air Diffuser 50.00 UNIT 3,900.00 780.00 78.00 4,758.00 237,900.00
EPDM Material
Digested sludge pump 1.00 UNIT 45,000.00 9,000.00 900.00 54,900.00 54,900.00
Screw or vortex impeller
Capacity: 3 liter per second
TDH: 10 meters
2hp, 220/440V, 60Hz, 3phase
Transfer submersible pump 4.00 UNIT 65,000.00 13,000.00 1,300.00 79,300.00 317,200.00
Screw or vortex impeller
Capacity: 6 liter per second
TDH: 8 meters
3hp, 220/440V, 60Hz, 3phase
Re-circulation pump 2.00 UNIT 45,000.00 9,000.00 900.00 54,900.00 109,800.00
Screw or vortex impeller
Capacity: 6 liter per second
TDH: 8 meters
2hp, 220/440V, 60Hz, 3phase
Chlorinator 1.00 UNIT 85,000.00 17,000.00 1,700.00 103,700.00 103,700.00
Mixer Pump 2.00 UNIT 35,000.00 7,000.00 700.00 42,700.00 85,400.00
1.5hp, 220/440V, 60Hz, 3phase
MBBR Pe o5 1.00 LOT 1,577,052.50 315,410.50 31,541.05 1,924,004.05 1,924,004.05
Electrical Works 1.00 LOT 560,000.00 112,000.00 11,200.00 683,200.00 683,200.00
Motor Control Center
Electrical rough-ins
Hangers and supports
sub-total II 5,115,036.05
III Mechanical Works 1.00 LOT 850,260.00 170,052.00 17,005.20 1,037,317.20 1,037,317.20
2’’x 3/8 stainless expantion bolt
3" (75mm) Diameter x 6 mtr Length Sch .40 G.I pipe
3" (75mm) Diameter x 3 meter Length PVC Pipe
2" (50mm) Diameter x 3 meter Length PVC pipe
3/4" Diameter x 3 meter Length PVC pipe
3" (75mm) Diameter x 90 Degrees ELBOW - PVC
3" x 3" (75mm) Diameter TEE – PVC
3" x 3" (75mm) Diameter TEE - G.I
3" x 2" (75mm x 50mm) Reducer bushing G.I.
2" X 90 degree (50mm) Diameter Elbow - PVC
2" (50mm) Diameter x6 mtr length sch.40 - G.I. pipe
Page 0
Date : January 16, 2023
Attention :
Project : Proposed Sewage Treatment Plant
Location : Bicol
Owner :
Subject : Proposed Supply and Installation of Electro-Mechanical Sewage Treatment Plant 350CmD
A. SCOPE OF WORKS
UNIT RATE
ITEM NO. ITEM DESCRIPTION UNIT QTY TOTAL AMOUNT
MATERIAL LABOR OTHERS TOTAL
SUMMARY:
GENERAL REQUIREMENTS / PRELIMENARIES (I) 740,000.00
INDIRECT COST (II-IV) 6,751,165.85
VAT 12% 898,939.90
TOTAL PROJECT COST PHP 8,390,105.75
B. TOTAL AMOUNT OF THIS OFFER: PHP 8,390,105.75
C. AMOUNT IN WORDS: Eight million, three hundred ninety thousand, one hundred five pesos and 75/100 only.
D. TERMS OF PAYMENT: 40% DOWN-PAYMENT, BALANCE SHALL BE PAID IN PROGRESS BILLING BASED ON ACCOMPLISHMENT.
E. WARRANTY: ONE YEAR WARRANTY ON WORKMANSHIP AND EQUIPMENTS UPON PROJECT COMPLETION
Note:
1 Client should provide area for control room
2 Civil / architectural works for control room are excluded in this quotation.
3 Electricity and water consumption shoulder by the client.
4 Sub-feeder line for control room shall not exceed in 5meters length
Prepared by : Conformed:
Page 1