Qhse-Dosc-Pit Excavation Risk Assessment
Qhse-Dosc-Pit Excavation Risk Assessment
Qhse-Dosc-Pit Excavation Risk Assessment
Pit Excavati on
Department Document Ref. No. Issue Date Revision
QHSE QHSE-DOCS-RA-0000 00-00-0000 00
required.
Locate the position of buried
utilities by referring to plant
drawings.
Start digging manually to
locate the exact position of
buried utilities and thereafter
use mechanical means.
Prevent ingress of water.
Provide ring buoys.
Identify and provide a
suitable size dewatering
pump or well-point system.
Same as above Plus
Obtain prior approval of the
Flooding due to
All technicians, and Can cause a drowning excavation method from local
excessive rain/
tradesmen nearby, situation authorities. Use the under- Project
underground water
may suffer sprains, Building/Structure may pining method. Manager/
Digging in the vicinity
Pit Excavation bruising, or fractures collapse Loss of health & Construct a retaining wall side Engineer
2 of existing 3 5 15 1 2 2
beyond 3.0m if they trip over wealth by side. Project
Building/Structure
objects, such as work May cause cave-in or Barricade the excavated area Supervisor
Movement of
debris, or slip-on slides. with proper lighting QHSE Officer
vehicles/equipment
spillages. Persons may get buried. arrangements.
close to the edge of
Maintain at least a 2m
the cut.
distance from the edge of the
cut and use stop blocks to
prevent over-run.
Strengthen shoring and
strutting.
3 Narrow deep All operatives in the Same as above Plus May cause severe injuries 3 5 15 Prevent ingress of water. 1 2 2 Project
excavations vicinity could suffer Frequent cave-in or or prove fatal Provide ring buoys. Manager/
for pipelines, from smoke inhalation slides May arise drowning Identify and provide a Engineer
etc. or burns. Flooding due to situation suitable size dewatering Project
Hydrostatic testing pump or well-point system. Supervisor
Obtain prior approval of the QHSE Officer
excavation method from local
authorities. Use the under-
pining method.
Page 2 of 4 QHSE-DOSC-RA-0000-EXCAVATION
RISK ASSESSMENT Page 3 of 4
Pit Excavati on
Department Document Ref. No. Issue Date Revision
QHSE QHSE-DOCS-RA-0000 00-00-0000 00
Page 3 of 4 QHSE-DOSC-RA-0000-EXCAVATION
RISK ASSESSMENT Page 4 of 4
Pit Excavati on
Department Document Ref. No. Issue Date Revision
QHSE QHSE-DOCS-RA-0000 00-00-0000 00
Consequence
Probability
Insignificant (1) Minor (2) Moderate (3) Major (4) Catastrophic (5)
Rare (1) 1 2 3 4 5
Possible (2) 2 4 6 8 10
Likely (3) 3 6 9 12 15
Often (4) 4 8 12 16 20
Frequent/Almost Certain (5) 5 10 15 20 25
15 - 25 Extreme Risk Activity or Industry Should Not Proceed in Current Form
Activity or Industry should be modified to include remedial planning and action and be subject
8 - 12 High Risk
to detailed OSH Assessment
4-6 Moderate Risk Activity or industry can operate subject to management & Modification
1-3 Low Risk No Action is Required Unless Escalation of Risk is Possible
Project Engineer:
QHSE Officer:
Page 4 of 4 QHSE-DOSC-RA-0000-EXCAVATION