Problems
Problems
3.29 A small software development project at Krishna Dhir’s firm has five major activities. The times are
estimated and provided in the table below. Find the expected time for completing Dhir’s
project.
Activity Immediate a m b
Predecessor
A — 2 5 8
B — 3 6 9
C A 4 7 10
D B 2 5 14
E C 3 3 3
1
3.31 What is the minimum cost of crashing the following project by 4 days?
3.32 Nicholas Glaskowsky, director of personnel of Glaskowsky Resources, Inc., is in the process of
designing a program that his customers can use in the job-finding process. Some of the
activities include preparing résumés, writing letters, making appointments to see prospective
employers, researching companies and industries, and so on. Some of the information on the
activities appears in the following table:
Time (days) Immediate
Activity a m b
Predecessor(s)
A 8 10 12 —
B 6 7 9 —
C 3 3 4 —
D 10 20 30 A
E 6 7 8 C
F 9 10 11 B, D, E
G 6 7 10 B, D, E
H 14 15 16 F
I 10 11 13 F
J 6 7 8 G, H
K 4 7 8 I, J
L 1 2 4 G, H
a) Construct a network for this problem.
b) Determine the expected times and variances for each activity.
c) Determine ES, EF, LS, LF, and slack for each activity.
d) Determine the critical path and project completion time.
e) Determine the probability that the project will be finished in 70 days.
f) Determine the probability that the project will be finished in 80 days.
g) Determine the probability that the project will be finished in 90 days.
3.33 Getting a degree from a college or university is a long and difficult task. Certain courses must be
completed before other courses may be taken. Develop a network diagram in which every
activity is a particular course that must be taken for a given degree program. The immediate
predecessors will be course prerequisites. Do not forget to include all university, college,
and departmental course requirements. Then try to group these courses into semesters or
quarters for your particular school. Which courses, if not taken in the proper sequence, could
delay your graduation?
2
3.34The Katok Construction Company is involved in constructing municipal buildings and other structures
that are used primarily by city and state municipalities. This requires developing legal documents,
drafting feasibility studies, obtaining bond ratings, and so forth. Recently, Elena Katok was given a
request to submit a proposal for the construction of a municipal building. The first step is to develop
legal documents and to perform all necessary steps before the construction contract is signed. This
requires approximately 20 separate activities that must be completed. These activities, their immediate
predecessors, and time requirements are given in the table shown below. As you can see, optimistic
(a), most likely (m), and pessimistic (b) time estimates have been given for all of the activities
described in the table. Using these data, determine the total project completion time for this
preliminary step, the critical path, and slack time for all activities involved.