Lampiran 05 - Safeguards 31 Maret 2023 PMC DGHS
Lampiran 05 - Safeguards 31 Maret 2023 PMC DGHS
Lampiran 05 - Safeguards 31 Maret 2023 PMC DGHS
(RWS 1)
Raw Water Supply Three DPPTs already sent Three LARPs to Balai TA Safeguards was Demobilized, but
Intake and to Balai and PPK, and PPK, currently have coordination with Sub-Con supp
Transmission from currently preparing for preparing for Final by management
2 Dadi Muria System, Final Report presentation Report presentation
Jragung Reservoir
and Bener Reservoir
(RWS 2)
3 Raw Water Supply Kuwil was completed on Kuwil was completed TA Safeguards was Demobilized, but
Intake and 19 Sep, 2022. on 19 Sep, 2022. have coordination with Sub-Con supp
Transmission from by management
Sidan Reservoir, Tukad Unda and Sidan Tukad Unda and
Tukad Unda still have field survey and Sidan still have field
Reservoir, and expected completion by survey and expected
Kuwil Reservoir February 2023 completion by
(RWS 3) February 2023
Progress and Report Status
No Packages Remarks / Issues
Screening IR – IP DPPT LARP DDR IPP SPRSS
4 Preparation of DPPT was completed and LARP was completed LARP specialist already demobilizatio
Rongkong will be sent to PPK this and will be sent to but still have commitment to comple
Multi-Purpose Dam week PPK this week the reports
(West Region)
6 Preparation of - Tondano: DPPT was Tondano: LARP was Mahakam: Social Safeguards Expert
Strategic Planning completed and sent to completed and sent finished, all report will be completed
for Sustainable PPK by Jan 23 to PPK by Jan 23 the Sub Contractor in coordination w
Water Resources PMC and TRTA
Management in Mahakam: Mahakam:
Priority Lakes
DPPT is expected to be LARP is expected to
(East Region) completed by February be completed by
2023 February 2023
`2 Preparation of DPPTs are expected to be LARPs are expected Social Safeguards Expert was
Belawan-Deli completed by Feb 2023 to be completed by Demobilized, but still have
Percut-Padang River Feb 2023 communication with Sub Con for
Basin Flood finalizing the report
Management
Project
3 Preparation of Currently preparing 8 LARP still on revision - Social Safeguards Expert was
Cimanuk DPPT, 5 documents for with TRTA and PMC Demobilized, all report will be compl
Cisanggarung River batch 1 implementation and expected to be by the Sub Contractor in coordination
Basin Flood and 8 documents for completed by Feb with PMC and TRTA
Management batch 2 implementation, 2023
Project and expected to be
completed by Feb 2023
4 Preparation of DPPT is expected to be LARP is expected to
Mahakam River completed by 30 January be completed by 30
Progress and Report Status
No Packages Remarks / Issues
Screening IR – IP DPPT LARP DDR IPP SPRSS
1 Development of DPPTs are expected to be LARPs are expected PPC already closed, all report will be
Irrigation System in completed by Feb 2023 to be completed by completed by the Sub Contractor in
Asahan Phase 1 Feb 2023 coordination with PMC
7 Development of DPPTs are expected to be LARP are expected to PPC already closed, all report will be
Irrigation System in completed by Feb 2023 be completed by Feb completed by the Sub Contractor in
Rongkong & 2023 coordination with PMC
Pelosika
Progress and Report Status
No Packages Remarks / Issues
Screening IR – IP DPPT LARP DDR IPP SPRSS
1 PPC 4
(Construction of south Java link)
Downstream financing by GOI/APBN
a. Panggul – Craken IR: B category NR Completed. NR NR NR
Road, East Java IP: No identified Submitted in Jul.
existing IP 2020
b. Munjungan – IR: B category NR Completed. NR NR NR
Prigi Road, East IP: No identified Submitted in Jul.
Java existing IP 2020
2 PPC 1
b. Access road to
Ujung Jabung Not required
Port, Jambi
d. Rantepao – Bua
Road, South Not required
Sulawesi
indigenous
people
3 PPC 3A
b. Tumbang Hiran-
Tubang Samba
Not required
Road (CK2)
c. Merbau – Tebas IR category B NR Revision Final LARP NR NR NR
Road (WK1) report. To be
IP: C.
completed in
No identified
February . 2023
indigenous people
d. Relokasi Jalan Cancelled
Amuntai – Kelua,
South Kalimantan
e. Tering - Long IR category B NR Revision Final LARP NR NR NR
Bagun & Long report. To be
IP: C.
Bagun Long completed in
Pahangai (include No identified
February. 2023
8 bridges), South indigenous people
Kalimantan
Downstream financing by ADB
Kalimantan completed in
(EKM-3) February 2023
4 PPC 3B
5 PPC 5
Sumatera indigenous
people
h. Jembatan Sei Not required
Rambut, Jambi
6 PPC 7
Downstream financing by GOI/APBN
a. FO Joglo (Solo), NR Not Required/LARP Cancelled
Central Java
b. FO Karanganyar, IR: B category NR Completed. NR NR NR
Central Java IP: C. No Submitted in Apr.
identified 2022
indigenous
people
c. FO Kutowinangun IR: B category NR Completed. NR NR NR
Central Java IP: C: No Submitted in Apr.
identified 2022
indigenous
people
d. FO Kawasan IR: B category Not Required/LARP Cancelled
Gamping (Yogya) IP: C: No
identified
indigenous
people
e. FO Aloha IR: B category NR Completed. NR NR NR
(Surabaya) East IP: C: No Submitted in June
Java identified 2021
indigenous
people
f. FO Kartini IR: B category NR Completed. NR NR NR
(Klaten), Central IP: C: No Submitted in March
Java identified 2022
indigenous
Progress and Report Status
No Packages Remarks / Issues
Screening IR – IP DPPT LARP DDR IPP SPRSS
people
Note: 1) DPPT, IPP, DDR & SPRSS are not required (NR) or not accommodated in TOR
2) Poverty and social impact analysis are included in chapter of LARP document as social economic profile and Income Restoration program
1 Benteng Kobema IR: B category PPC doesn’t compile LARP has been Not Required Not Required Not Required
Regional Water IP: No identified DPPT completed and
Supply existing IP submitted to PMC on
18 Nov 2021
2 Polewali Mandar- IR: B category PPC doesn’t compile LARP has been Not Required Not Required Not Required
Majene Regional IP: No identified DPPT completed and
Water Supply existing IP submitted to PMC on
17 Feb 2022
3 Central Sulawesi IR: B category DPPT has completed LARP has been Not Required IPP has been Not Required
Progress and Report Status Remarks / Issues
No Packages
Screening IR – IP DPPT LARP DDR IPP SPRSS
4 West Indonesia IR: B category DPPT Document is on LARP Document is on DDR Document is on Not Required Not Required
(Serdang Bedagai – IP: No identified legalization process, the finalisation process, finalisation process, the
Tebing Tinggi existing IP target is 4th Week of the target is 4th Week target 4th Week of
Regional Water March 2023 of March 2023 March 2023
Supply in North 24 affected people 24 affected people 2,058 m2 Land
Sumatera) Land requirement is Land requirement owned by PTPN
2.320,1 m2 is 2,301 Ha Tiga Rambutan
DPPT in the Cut-Off Date has Final DDR is on
approval process of not been signed yet revision based
the CKTR SDA office Land acquisition workshop
will be budgeted
for 2023
Final LARP is on
revision based
workshop
5 West Indonesia IR: B category DPPT Document is on LARP Document is on DDR Document is on Not Required Not Required
(Agam – Bukit IP: No identified legalization process, the finalisation process, finalisation process, the
Tinggi Regional existing IP target is 4th Week of the target is 4th Week target is 4th Week of
Water Supply in March 2023 of March 2023 March 2023
West Sumatera) 39 affected people 39 affected people Protected Forest
Land requirement The required land Land
13.617,37 m2 area is 1,2 Ha (intake) is 1.000 m2
The Appraisal Team ( 11,966 m2); Offtake
has finished assessing Land acquisition Mandiangin,
the assets of the will be budgeted on Bukittinggi is 2,558
affected people 2023 (5 M) m2
DPPT Document and Cut Off Date has DDR still need
Cut Off Date have not not been signed yet revision as a whole
been signed yet by by Local Technical and need to be re-
Local Technical Team Team discuss
Progress and Report Status Remarks / Issues
No Packages
Screening IR – IP DPPT LARP DDR IPP SPRSS
6 West Indonesia IR: B category DPPT has been LARP has finished, Not Required Not Required Not Required
(Karian Timur Non- IP: No identified completed and submitted February 2023.
PPP Regional existing IP to PMC on 27 Jan 2023 32 affected people
Water Supply in The required land
Banten) area is 85.162 m2
The Cut-Off Date
has not been
determined;
Land acquisition
will be budgeted
for 2023
7 West Indonesia Not required by the Not required by the Not required by the Not required by the Not required by the Not required by
(Jatiluhur I contract contract contract contract contract the contract
Regional Water
Supply in DKI
Jakarta)
8 Ajatappareng IR: B category DPPT has finished and LARP Document is on DDR Document is on Not Required Not Required 2nd PKM and 3rd PKM has bee
Regional Water IP: No identified conducted workshop finalisation process, finalisation process, the conducted on:
Supply in South existing IP 124 affected the target is 4th Week target is 4th Week of - 14 February 2023 in Enreka
Sulawesi households of March 2023 March 2023 Regency
The required land 124 affected Protected Forest - 15 February 2023 in Sidrap
area is 63.966 m2 households Land Regency
Appraisal has finished The required land (WTP) is 9.269 m2. - 16 February 2023 in Papep
affected people’s area is 63.966 m2 520 m2 Land is City
asset assessment The Cut-Off Date owned by PTPN
has not been (Offtake)
determined; 16.787 m2 (Offtake
Land acquisition Supa, Sawito, Inline
Progress and Report Status Remarks / Issues
No Packages
Screening IR – IP DPPT LARP DDR IPP SPRSS
9 Bimatara Regional IR: B category DPPT has finished and LARP Document is on DDR Document is on Not Required Not Required 3rd PKM has been conducte
Water Supply in IP: No identified conducted workshop finalisation process, finalisation process, the March 2023
North Sulawesi existing IP 23 affected people the target is 4th Week target is 4th Week of
The required land of March 2023 March 2023
area is 56.984 m2 23 affected people 550 m2 Land is
The Appraisal Team The required land owned by the
has finished assessing area is 56.984 m2. government of
the assets of the Cut-off date has North Minahasa.
affected people not been 2.653 m2 Land is
56.984 m2land determined owned by PDAM
owned by the citizen Land acquisition Bitung
Land procurement will be budgeted on
schedule is still 2024
tentative
10 Gorontalo Raya IR: B category DPPT has finished and LARP Document is on DDR Document is on Not Required Not Required
Regional Water conducted workshop finalisation process, finalisation process, the
Supply in 28 affected people the target is 4th Week target is 4th Week of
IP: No identified
Gorontalo The required land of March 2023 March 2023
existing IP
area is 60.300,77 m2 28 affected people 1.000 m2 Land is
The Appraisal Team The required land owned by BWS
has finished assessing area is 60.300,77 Sulawesi II (Intake is
the assets of affected m2 on Bulango Ulu
people Land acquisition Dam).
will be budgeted on
2023
11 Kutai Kartanegara – IR: B category DPPT has been LARP Document is on DDR Document is on Not Required Not Required
Bontang Regional completed and submitted finalisation process, finalisation process, the
Water Supply in to PMC on 06 February the target is 1st Week target is is 1st Week of
Progress and Report Status Remarks / Issues
No Packages
Screening IR – IP DPPT LARP DDR IPP SPRSS
Directorate of Sanitation
Pontianak City IR: B category PPC does not compile LARP is on finalization Not Required Not Required Not Required Land acquisition for Mar
12
Wastewater DPPT process and to be WWTP has not been con
IP: No identified
Management existing IP completed on April (7,248 m2)
2023.
Semarang City IR: B category PPC does not compile LARP is on finalization Not Required Not Required Not Required WWTP is located in flood-prone
13
Wastewater DPPT process and to be
IP: No identified
Management existing IP completed on April
2023.
14 Bekasi City IR: B category PPC does not compile PPC does not compile Not Required Not Required Not Required WWTP is located in flooding
Wastewater IP: No identified DPPT LARP constructions cannot be condu
Management existing IP
15 Mataram City IR: B category PPC does not compile LARP is on finalization Not Required Not Required Not Required
Wastewater DPPT process and to be
Management IP: No identified completed on April
existing IP 2023.
d. Directorate General of Infrastructure Financing
Progress and Report Status
No Packages Remarks / Issues
Screening IR – IP DPPT LARP DDR IPP SPRSS
Project Not required by Not required by contract. Not required by Not required by Not required by Not required by
Management contract. contract. contract. contract. contract.
Consultant (PMC)
Firm
2 To Support the DGIF
with
Implementation of
ESP
IEE AMDAL
IEE AMDAL
IEE AMDAL
IEE AMDAL
IEE AMDAL
IEE AMDAL
IEE AMDAL
4 PPC 3B
Downstream financing by ADB:
- - Addendum ANDAL RKL and RPL Waiting for discussion with
a. Semamu – Long Bawan Road,
- The document has been validated on 6 October KLHK/PDLUK
North Kalimantan
2022.
Downstream financing by
GOI/APBN:
- - Addendum ANDAL RKL and RPL Waiting for discussion with
a. Long Boh – Metulang Road, North
- The document has been validated on 6 October KLHK/PDLUK
Kalimantan
2022
- - AMDAL - Prepare of draft ANDAL, RKL and
- Term of Reference has been discussed with RPL
b. Long Nawang-Data Dian Road, KLHK/PDLUK on 12 October 2022
North Kalimantan - The revision of TOR document was submitted to
PDULK on 17 November 2022
IEE AMDAL
Sumatera
- UKL UPL -
- The document has been validated on 9 - Waiting for input document
August 2022 revision from PDLUK and
d. FO Duku-BIM, West Sumatera - The document has been discussion with PKKPR/ATR BPN Padang
PDULK/KLHK on 26 october 2022 Pariaman.
- The revision have been submitted to
PDLUK/KLHK on 1 November 2022.
e. FO Koto Baru (Padang Panjang), Completed. - -
West Sumatera
f. Duplikasi Jembatan Air Ogan III, Completed. - -
South Sumatera
g. Pembangunan Underpass Sp. RS Completed. -
Charitas, South Sumatera
h. Jembatan Sei Rambut, Jambi NR NR -
2 PPC 7
Downstream financing by GOI/APBN
a. FO Joglo (Solo), Central Java NR NR -
b. FO Karanganyar, Central Java Completed. -
c. FO Kutowinangun Central Java Completed. -
d. FO Kawasan Gamping (Yogya) Cancelled -
e. FO Aloha (Surabaya) East Java NR NR -
- UKL UPL - Revision of UKL UPL documents
- The document has been validated on 21 while waiting for PPKPR from
f. FO Kartini (Klaten), Central Java Juli 2022. ATR/BPN from central Jawa
- Document UKL UPL has been discussed on Province.
16 December 2022.
g. Overpass Balaraja Barat, NR NR
Tangerang Banten
Downstream financing by WB
a. FO Canguk (Magelang) Completed. - -
c. Directorate General of Human Settlements
Progress and Report Status
No Package Remarks / Issues
IEE AMDAL
Directorate of Water Supply
1 Benteng Kobema Regional Water Not required by the contract AMDAL has completed on 24 Nov 2020
Supply
2 Polewali Mandar- Majene Regional Not required by the contract AMDAL has completed on 13 Oct 2022
Water Supply
3 Central Sulawesi Regional Water IEE has been completed on 22 Maret AMDAL has completed on 22 March 2022
Supply 2022
4 West Indonesia (Serdang Not required by the contract AMDAL has completed on 02 October 2022
Bedagai – Tebing Tinggi
Regional Water Supply in North
Sumatera)
5 West Indonesia (Agam – Bukit Not required by the contract AMDAL documents are on process of:
Tinggi Regional Water Supply in • Indication Map to Halt New Permit (PIPPIB)
West Sumatera) has not yet been signed by the Governor
• Technical Standard has been discussed on
18 November 2022 and on 2nd revision and
has been delivered to Environmental
Official on 9 January 2023.
• Based on letter of direction from
Transportation Official of West Sumatera
Province, ANDALALIN analysis is not
required. No.:
551.11/123/DISHU-SB/II/2022, dated 10
February 2022
• ANDAL, RKL-RPL Hearing has been
conducted on 16-17 March 2023
•
6 West Indonesia (Karian Timur Not required by the contract AMDAL documents are on process of:
Non-PPP Regional Water • ANDAL RKL-RPL hearing has been
Supply in Banten) conducted on 28 December 2022 at
Progress and Report Status
No Package Remarks / Issues
IEE AMDAL
Environmental Official.
• Has discussed Technical of Content
Assessment for Technical Permit to Use
Wastewater to be Applicated to The
Ground, on 22 February 2023 at
Environmental and Forestry Official of
Banten Province
7 West Indonesia (Jatiluhur I Not required by the contract Not required by the contract
Regional Water Supply in DKI
Jakarta)
8 Ajatappareng Regional Water Not required by the contract AMDAL documents are on process of:
Supply in South Sulawesi • ANDAL, RKL RPL Hearing is planned on 10-
11 April 2023 from Environmental Official of
South Sulawesi
• Administration trial and B3 Waste Storage
Technical Details (Rintek) evaluation
(Producer) on 2 December 2022 at
Environmental Official of South Sulawesi
• Liquid Waste Technical Standards have been
discussed on March 2, 2023 at the DPLH of
South Sulawesi Province
• Andalalin is not mandatory, based on
Direction Letter from Ministry of
Transportation Indonesian Republic Number:
UM.209/13/18/LLJ/II/2023 dated 16 February
2023
9 Bimatara Regional Water Not required by the contract AMDAL has finished on 2 February 2023
Supply in North Sulawesi
10 Gorontalo Raya Regional Water Not required by the contract AMDAL has finished on 13 March 2023
Supply in Gorontalo
11 Kutai Kartanegara – Bontang Not required by the contract AMDAL documents are on process of:
Regional Water Supply in East • SKKLH publishing process DPMPTSP of
Kalimantan East Kalimantan Prov.
• Recommendation from Environmental Official
of East Kalimantan Prov, Number :
KAKT/024/KOMDAL-PROV/III/2023, on 28
March 2023
• ANDAL, RKL & RPL Hearing has been
conducted on 23-24 November 2022.
• Based on letter of direction from
Progress and Report Status
No Package Remarks / Issues
IEE AMDAL
Environmental Official of East Kalimantan
Province, ANDALALIN is not required. Letter
No.: 660.2/2313/B.1.2/DLH/2022, dated 25
October 2022
• Based on letter of direction from
Transportation Official of Bontang City, East
Kalimantan Province ANDALALIN is not
required on 14 December 2022, No:
551/1264/DISHUB
• Based on letter of direction from
Transportation Official of Kutai Kartanegara
Regency, ANDALALIN is not required. Letter
No:P.1290/ADL-LL/DISHUB/500.11.6/12/
2022 on 21 December 2022 with obligation to
maintain order, security, and smooth traffic
flow (RKL-RPL)
• Recommendation process from
Environmental Official of East Kalimantan
Directorate of Sanitation
12 Pontianak City Wastewater Has been completed. • AMDAL has finished 100% with SKKLH
Management publication on 10 December 2020, No:
1124/ /DLH/Year 2022
• Technical Standard for Wastewater has
finished 100% on 14 September 2022
• ANDALALIN has finished 100% with
ANDALALIN approval from Mayor of
Pontianak City on 25 November 2022, No:
551/925/Dishub/2022.
• Draft IEE and EMP are on revision based
on ADB’s review
13 Semarang City Wastewater Draft of IEE and EMP are being reviewed • AMDAL has finished 100% with SKKLH
Management on 28 March 2023 publication on 27 June 2021, No: 660-1/554
Year 2022
• Technical Standard for Wastewater has
finished 100% on 25 November 2021.
• ANDALALIN has finished 100% with approval
for ANDALALIN recommendation from
Semarang City Transportation Official on 4
November 2022, No: 551.1/14.335
• Draft IEE and EMP has been prepared and
Progress and Report Status
No Package Remarks / Issues
IEE AMDAL
on process of review by ADB
14 Bekasi City Wastewater Not required by the contract Not required by the contract
Management
15 Mataram City Wastewater Draft of IEE and EMP are being reviewed AMDAL has finished 100 %.
Management on 28 March 2023 SKKLH of Mataram City WWTP Development - SKKLH publication’s date has
No: 060/KLH/DLH/IX/2022 not been attached yet
IEE AMDAL
IEE AMDAL
a technical
consideration letter
that can be used for
the KKPR process.
- AMDAL team will
submit KA ANDAL in
February 2023.
- KA ANDAL progress
until now the AMDAL
team already met the
KLHK representative
to get the information
about status of
direction letter from
KLHK for Tuban-
Gresik Toll Road. The
status is still awaiting
disposition in KLHK
- ANDALALIN team
should check the WTP,
ATP, economic
analysis, and traffic
forecasting volume.
- There is issue that Tuban
Gresik toll road can not
go to transaction without
Environmental Permit,
which ANDALALIN is part
of the permit.This is due
to that FBC only consist
of Basic design, while
ANDALALIN needs DED.
This issue will benefited
from DGIF discussion
with Ministry of
Transportation
- Transportation, Ministry
of transportation would
No Package Progress and Report Status Remarks / Issues
IEE AMDAL