0% found this document useful (0 votes)
88 views8 pages

CV-MMM - C

This document provides a summary of Muhammad Mudassir Mirza's skills and experience. He has over 20 years of experience as a senior electrical engineer, including 6 years of overseas experience in project management consultancy. His skills include inspection, project management, engineering design, progress monitoring, and experience in the oil and gas industry. He currently works as a senior project engineer providing engineering design, project management, and consultancy services.

Uploaded by

Mudassir
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
88 views8 pages

CV-MMM - C

This document provides a summary of Muhammad Mudassir Mirza's skills and experience. He has over 20 years of experience as a senior electrical engineer, including 6 years of overseas experience in project management consultancy. His skills include inspection, project management, engineering design, progress monitoring, and experience in the oil and gas industry. He currently works as a senior project engineer providing engineering design, project management, and consultancy services.

Uploaded by

Mudassir
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 8

MUHAMMAD MUDASSIR MIRZA

R-960, Block-16, Dastagir, Tel: +922136370056, +923212423631,


F.B Area, Karachi, Pakistan +923112511105.
Email:[email protected]
Skype id:mudassir160

OBJECTIVE

Seeking a career position in an organization where I can fully utilize and enhance my
knowledge and skills to contribute to the growth of the organization.

WORK PREFERENCES

Availability 4-6 weeks

Desired Job Type Any

Highest Education Bachelor of Engineering in Electrical Technology


Level

Relocation Yes

SKILLSET

• Inspection
• Project Management Consultancy (PMC)
• Engineering Design Consultancy for both FEED & Detailed design
• Progress Monitoring, Measurement & verification
• Oil & Gas Industry
• Construction Supervision
• Review of Engineering Documents (Vendor Prints)
• Procurement Assistance & Bid Evaulation

EXPERIENCE SUMMARY

• Over Twenty (20) years as a Senior Engineer (Electrical Projects) including 6 years of
Overseas Experience engaged in PMC job.

INSPECTION

• Have Experience of equipment on-site inspection for verification of the package list
• Verify installation, selection & condition of equipment with respect to Classified
Hazardous & Non-Hazardous Area & applicable international industrial Standards

Page 1 of 8
PROJECT MANAGEMENT CONSULTANCY (PMC)

• Ensure that the erection is in full compliance to the design and Industrial codes and
standards and the design documents
• Full Compliance of the tender & contract agreed terms & conditions
• Identification of deviations either from the tender or the contract

ENGINEERING DESIGN REVIEW

• Ensure that the erection is in full compliance to the design and Engineering codes and
standards
• Full compliance of the Technical conditions & limitations as per the tender and the
contract
• Verification of the submitted engineering documents through the parent document

PROGRESS MONITORING, MEASUREMENT & VERIFICATION

• Submission of the Progress Report to the client periodically, as performed by the


contractor on site subsequent to its monitoring & measurement
• Verification of Contractor submitted progress reports

TECHNICAL EXPERIENCE

• Electrical design including Selection and Sizing of Electrical equipments including


sizing of cables Switchgear design and selection along with control schematics /
philosophies, Logic diagrams, Electrical equipment data sheets, control wiring &
cabling, Electrical specification, Material take off, BOQ etc.

• Designing of Lighting system including formulation of basic philosophies, equipment


and system specification, layout drawings, related cables etc.

• Lead and manage a project team & interact with other departments for relevant
inputs/requirements.

• Technical Evaluation of vendor supplied Equipment such as Motors, switches,


Explosion proof and Non-Explosion Lights etc.

• Basic Design / Conceptual Engineering including participation in preparation of


Electrical Network Hierarchy.

• Maintain/ trouble shoots the different control like problems.

• Coordination with Clients, Contractors, Manufacturers and Vendors.

• Invoicing and follow-up.

• Preparation of Engineering Reports & Conceptual Design Reports.

Page 2 of 8
• Basic and Detailed Engineering, Design Vetting of oil & gas, refinery, transportation
& marketing, process & power industries, expansion & revamping with a focus on
project specifications, budget, quality & schedule.

• Prepare technical data sheets for Motorised, Non-Motorised and Lighting equipments.

• Coordination with QA/QC department in order to develop inspection and test plans.

• Involvement in planning, costing, design, procurement, scheduling and installation


reviews.

• Progress monitoring and reporting to the client and resolve technical and commercial
issues.

• Field engineering support, Construction Monitoring, Involvement in Pre-


commissioning and Commissioning support.

• Classification of Hazardous Areas and Selection of Electrical Enclosures to be


specified in the data sheets and specifications as per NEC / NFPA Standards.

• Familiar with API RP500, Relevant IEC, NEC / NFPA Standards.

EMPLOYMENT HISTORY

Zishan Engineers (Pvt.) Ltd. (2007 till Date)

Zishan Engineers (Pvt.) Ltd. (ZEL), incorporated in 1981, is an engineering consultancy firm
which provides Detailed and Basic Engineering, Project Management, Procurement
Assistance and Construction Supervision services to Oil & Gas Sector, Petroleum and Process
Industries. www.zishanengineers.com
Serving as Sr. Project Engineer, responsible for Design & Detailed Engineering Works as
summarized below:

• Preparation of Engineering Reports & Conceptual Design Reports.

• Preparation of BOQs, Material Requisitions, Specifications and Data Sheets.


• Preparation of Tender and Contract / Bid Documents.

• Reviews of P & IDs.

• Short Circuit Analysis and design of Low Voltage Industrial Systems.

• Sizing of Cables (LV and MV), Transformers and Standby Generators.

• Designing of Single Line Diagrams of Switchgears & Power and Lighting Distribution
Boards.

• Preparation of detailed drawings and Layouts (Relating to Cables, Lighting and


Earthing).
Page 3 of 8
• Planning and Project Management.

• Evaluation of Bids and Pre-Qualification of Contractors.

• Coordination with Clients, Contractors, Manufacturers and Vendors.

• Design Vetting.

• Invoicing and follow-up.

PROJECTS HIGHLIGHTS

Engineering Design Works of the Apical Oil Terminal (Pvt.) Ltd., (AOT) Edible Oil
Storage Terminals at Port Qasim Karachi. The job involved complete Detailed
Engineering Design works for the Electrical System of the oil terminals & preparation of
BOQ’s along with the Drawings, Specifications / Datasheets & typical installation details.

Engineering Design Works of the Attock Petroleum Ltd. (APL) Oil Storage Terminals at
different locations in Pakistan i.e., Mehmoodkot, Shikarpur & Sahiwal. The job involved
complete Detailed Engineering Design works for the Electrical System of the oil terminals
& preparation of BOQ’s along with the Drawings, Specifications / Datasheets & typical
installation details.

Project Management Consultancy of GASCO Saudia Arabia. The project was upgradation
of the LPG filling plants in seven cities of Saudia Arabia viz., Dammam, Riyadh, Jeddah,
Abha, Taif, Madinah and Qassim. The upgradation works was mainly done by M/s.
KOSAN CRISPLANT and partly done by M/s. SIRAGA on EPC basis. The job included
review of the Engineering documents submitted and inspection of the materials supplied
on site and monitor erection activities as per governing international industrial standards
and preparation of the Progress reports.

Design review of M/s K-Electric 10 MW Power Plants for Korangi & Site Plants each.
The scope included the review of design of 132 kV Grid & 11 kV Generation.

Engineering Procurement Management of existing 800 TPD & new 200 TPD Edible Oil
Refinery Expansion Project of M/S IFFCO Pakistan (Pvt.) Ltd. at Port Qasim Karachi.
The expansion includes New 200 TPD Edible Oil Refinery, Margarine Producing Unit,
Hydrogen Generation Unit and Packaging of the Products. The Electrical Works included
the design of Low Voltage Electrical Network which involved Power Transmission on 11
KV Network at both the source end receiving end. The job was mainly based on
producing Construction and Procurement Packages of different electrical items namely,
Transformers, Standby Diesel Generators, Power (LV & MV) and Control Cables, Cable
Trays, Lighting and Earthing accessories.

Electrical Design Works of M/s. Bosicor Pakistan Limited. The project involved the
revamping of the existing facility at Mozakund, Hub.

Designing of Low Voltage Electrical System for M/s. Overseas Oil Trading Company
(OOTC) Machike Terminal. The design works was mainly comprising of Sizing of
Equipments like WAPDA Connection Transformers, Standby Diesel Generators, LV

Page 4 of 8
Motors Output Power required to maintain respective BHP at input of Pumps, Low
Voltage Power and Control Cables and Layouts of Cables, Lighting and Earthing. Also
Preparation of Procurement Packages for different electrical items comprising of relevant
BOQ’s, Specifications and Data sheets.

Preparation of Construction and Procurement Package of Power (LV & MV) and Control
Cables for M/s. Bosicor Oil Pakistan Limited (BOPL), Mozakund, Hub Plant. The
procurement package was based on Cable Schedule, Respective BOQ and Extensive
Cable Layout comprising mainly on cable trenches.

Preparation of Construction and Procurement Package for M/s. Bosicor Chemical Pakistan
Limited (BCPL) of Power (LV & MV) and Control Cables, Plant Area Lighting,
Grounding of Equipments. The Packages consist of Specifications and Data sheets and
relevant BOQ’s.

Designing of Low Voltage Electrical System for M/s. Hascombe Storage Limited (HSL)
Shikarpur, Terminal. The design works was mainly comprising of Sizing of Equipments
like WAPDA Connection Transformers, Standby Diesel Generators, LV Motors Output
Power required to maintain respective BHP at input of Pumps, Low Voltage Power and
Control Cables and Layouts of Cables, Lighting and Earthing. Also Preparation of
Procurement Packages for different electrical items comprising of relevant BOQ’s,
Specifications and Data sheets.

Preparation of Procurement and Construction Package for Low Voltage Electrical Systems
for M/s. Port Of Fujairah. The scope of works was to develop network for Power circuits
for Motorized and Non-Motorized loads, Lighting Circuits, Grounding of Electrical and
Non-Electrical Equipments (i.e., piping, structures, etc., ).

Detailed Engineering Works for Catalyst Recovery Unit Project of M/s. LOTTE Pakistan
PTA Limited. The scope of work included the detailed engineering works required for the
integration of catalyst Recovery Unit with the existing system. Preparation of Construction
and Procurement packages and Tender which included related documents like cable schedule,
Lighting and Earthing system, Cable tray layouts. System adequacy checks of the existing
system for integration with Catalyst Recovery Unit and preparation of tie-in reports.

Feed for Expansion and Modification of Truck Loading for M/s. OMAN Refineries and
Petrochemicals Company LLC in Sultanate of OMAN. The scope of work was to perform
Front End Engineering and Design Works for EPC Contractor. Preparation of proposals
for tie-ins of the New system to the existing system. Existing System Adequacy checks to
integrate the New Truck Loading system to the Existing. Preparation of preliminary
documents like Cable Schedule, Electrical Load List, Cable layouts, Earthing and Lighting
Layouts in accordance with the Existing ORPC Philosophy.

Karachi Electric Supply Corporation (KESC) (2003 to 2007)

Worked in KESC as Assistant Manager (CSC_SIMZ_II), First with the Army Management
and then, after Management Change over due to privatization policy of the government, with
the Private Management and assisted the Manager (CSC_SIMZ_II) on top of all other
Assistant Managers in the Center. The job responsibilities were:

Page 5 of 8
- Organize and perform the Meter Reading in the days of the monthly billing i.e., First
two weeks of every month

- Monitoring the Consumption trends of both LV & HV consumers

- Surveys of different industries to perform,

(a) the Load Analysis as per recent load scenario of the consumer, it involved the
check for the load above the 40 KW mostly.

(b) Slowness detection of the Energy meters due to low consumption of the
particular consumer.

(c) All possible checks for theft i.e., verifying the C.T Ratio as per billing record
& etc.

(d) Check for Original KESC seals on the Energy Meter Enclosures

(e) Check for the seals of P.T on the 11 KV Consumers

(f) Verification for the correct billing tariff as per recent billing record

(g) Verification of the correct multiplying factor as per billing record

- Assessment of the supplementary bills or undercharge bills raised due to any one of
the above findings or the other

- Update the findings of the consumers in the billing record and also direct all other
Assistant Managers to update the changes for their respective consumers due to
change of Energy Meter or the other finding evaluated during the site visit.

- Organize the activities for the recovery of the revenue raised due to monthly billing

- Physically check the status of the consumer as stated in his application and verifying
that status through consumption trend of Sui Gas Bill or other possible / available
alternative i.e., Income Tax or GST submittals etc.

- Calling for the Testing of Energy Meters through Mobile Testing Van.

- Attending the staff complaints being faced during the execution of the routine
activities and offering them the best possible solutions.

- Managing the Meter Reading and Survey Staff.

- Attending the Consumers in the absence of the Manager.

Page 6 of 8
Sheikh Wilayat Ahmed & Sons (SWAS) (2001 to 2003)

Performed as Sales and Support Engineer for the Low Voltage Switchgear Products. The
responsibilities involved to present the product line of different switchgear items and convince
the clients on the brands like; Fuji, LG, MG, ABB. Further responsibilities included:

- Cost Estimation as per the company price lists and policy discounts over multiple
projects.

- Offer the client with technical proposals customized according to their needs and
requirements.

- Target the market of upcoming and current projects, maintenance and revamp
solutions.

Systematic Engineering Services (1998 to 2001)

Served as E & I Engineer for the organization. And involved in construction activities on the
E & I part. Responsible for Supervision and Coordination of Contractors during different
installation and construction activities for Industrial Electrical Networks in oil and gas fields
related to Low Voltage applications as per relevant drawings, Specification, Distribution
layouts and relevant Standards for Oil and Gas Industry. Also involved in the designing for
modification of existing electrical systems.

PROJECTS HIGHLIGHTS

Construction Supervision of the Installation works for the Electrical Network for the
Metering System on one of the Keamari Oil Terminal (KTC) of M/s. Pakistan State Oil
Company Ltd., The scope was inclusive of installation of equipment as per relevant
drawings specification and standards, excavation of cable trench and cable laying.

Supervision & Coordination for the Installation of the Radar Tank Level Gauging System
on different terminals of M/s. Shell Pakistan Ltd., namely Sheikhpura, Rawalpindi etc.

Construction Supervision and Coordination of Contractors during Installation activities


related to Industrial Electrical System for the Storage Tank Facility at Korangi and
Keamari of M/s. Pak Arab Refinery Company Ltd., The scope of work included the
supervision for installation of Low Voltage MCC / Switchgear, replacement of 500 KVA
Transformer with 1500 KVA Transformer, Excavation of Cable Trenches and Cable
Laying as per relevant drawings and Cable layouts. The scope was to supervise the
installation of lighting system, earthing system, Cathodic Protection System etc.,

Construction Supervision for the installation of Radar Tank Level Gauging System
comprising of 76 Nos. of Tank Gauges on premises of M/s. Attock Refinery Ltd., The
scope of supervision including installation of Gauges, Cabling System.

Page 7 of 8
EDUCATIONAL QUALIFICATION

B.Eng. (Electrical): N.E.D University of Engineering & Tech., Pakistan in 1998

PROFESSIONAL AFFILIATION

• Registered professional engineer from Pakistan Engineering Council, Pakistan.

REFERENECE:

• Furnished upon request