Sen SGSSP GC P&i Ps Pro 011 MR Chiller Package - 20mar2023
Sen SGSSP GC P&i Ps Pro 011 MR Chiller Package - 20mar2023
Sen SGSSP GC P&i Ps Pro 011 MR Chiller Package - 20mar2023
PROJECT (SGSI)
MATERIAL REQUISITION
FOR
CHILLER PACKAGE
Document Number
SEN-SGSSP-GC-P&I-PS-PRO-011
Approved
Version Date Description Issued By. Checked By.
By.
13.Mar
A Issued For Review AAB TAH ZAZ
2023
1
INDEX
2
3.3 Inspection and Test Plan (ITP) ................................................................................. 15
3.4 Approval of ITP, QA/QC Procedures ....................................................................... 15
4.0 GENERAL REQUIREMENTS ................................................................................................. 16
4.1 General Note ............................................................................................................. 16
4.2 Design Changes ........................................................................................................ 16
4.3 Marking..................................................................................................................... 16
4.4 Interpretation............................................................................................................. 16
4.5 Preservation .............................................................................................................. 16
4.6 Packing ..................................................................................................................... 16
4.7 Shipping Weights and Volume ................................................................................. 17
4.8 Tagging ..................................................................................................................... 17
4.9 Conflicts, Deviations & Exception ........................................................................... 17
4.10 The Proposal ............................................................................................................. 18
4.11 Inconsistencies .......................................................................................................... 18
4.12 Painting & Coating ................................................................................................... 18
4.13 Environmental Conditions ........................................................................................ 18
4.14 Assistance during Installation ................................................................................... 18
4.15 Assistance during Start-up and Commissioning ....................................................... 18
4.16 Reporting .................................................................................................................. 18
4.17 Alternatives ............................................................................................................... 18
5.0 SCOPE OF SERVICES FOR FIELD SUPERVISION AND TROUBLE SHOOTING ...... 18
5.1 Detailed Scope of Work: .......................................................................................... 18
5.2 Field Services Instruction to Buyer: ......................................................................... 19
6.0 ATTACHMENTS ........................................................................................................................ 19
ATTACHMENT - 1: APPLICABLE DOCUMENTS LIST ............................................ 20
ATTACHMENT - 2: VENDOR / SUPPLIER DATA REQUIREMENT LIST ....... 22
ATTACHMENT - 3: SCOPE OF INSPECTION&TESTING ....................................... 26
ATTACHMENT - 4: COMPLIANCE, DEVIATION & EXCEPTION FORM ....... 28
ATTACHMENT - 5: EQUIPMENT DATA SHEET ......................................................... 29
3
1.0 REVISIONS
4
2.0 VENDOR SCOPE OF SERVICES & SUPPLY
5
performance requirements of ASHRAE standard 90.1 for efficiency. The chillers shall be
suitable for installation in the space provided.
Chiller shall be provided with spring vibration isolator by the Manufacturer.
Total Cooling Capacity required is 1,760,000 Kcal/hr (2046.88 KW)
Installed Capacity configuration shall be as per vendor selection to meet total cooling demand
(“n” working + 01 stand-by). “N” is total number of chillers that shall remain at duty mode and
one Chiller at stand-by or under maintenance mode.
Motors and starters shall be compatible and conform to the Electrical Clauses of this
Requisition.
Full load operation of the motor shall not under any circumstances exceed nameplate KW
rating.
Coupling shall be “non-Lubricated type” and balanced with fully crown half key and coupling
guard shall be Robust and non-sparking type in case of separate driver motor.
Condensers shall be air cooled / Water cooled design type and shall include, but not limited to,
propeller exhaust fans, motors, refrigerant coil and refrigerant specialties.
Condenser shall have aluminum fins mechanically bonded to seamless copper tubing and coil
shall be treated with anti-corrosive treatment. Condenser fans shall have vertical discharge.
Fans shall be statically and dynamically balanced. Three phase condenser fan motors with
permanently lubricated bearings and three-phase thermal overload protection shall be included.
Condenser fans shall have protective guards. Suction of air shall be from sides of chiller.
The material for Condenser coils should be seamless copper tubes with aluminum fins. Copper
fins, black fins, electro fins can also be used.
Vertical Alignment position screws and Stainless-steel shim packs shall be provided part of
package for alignment.
Materials of Construction for Compressor casing shall be compatible with refrigerant selected
and Gulf saline environment to meet International Standard.
Antifriction Bearings Type and with L10 Life 50000 Hours with continuous operation shall be
considered.
Mechanical seal shall be considered for shaft sealing.
Electric drive (motor) shall be with Name plate rated for 110% of max power including all
losses, exclusive of service factor.
Base Plate shall be Single fabricated steel common for compressor/driver.
Skid shall be with Earthing Lugs.
Skid shall be with Lifting Lugs.
Skid shall be with Leveling Screws.
Complete on-skid piping with necessary valves and fittings terminated to skid edge.
Piping is manifolded with a single tie-in at edge of base plate.
Noise limit is less than 85 dB, Canopy or hood shall be considered accordingly.
Refrigerant Circuit requirements
Refrigerant circuit(s) shall include, but not limited to, a hot gas muffler, combination moisture
indicator and sight glass, refrigerant filter drier, liquid line solenoid valve, thermal
expansion valve and charging valve. All suction lines shall be insulated.
Each chiller shall have at least 2 (Two) independent refrigerant circuits unless otherwise
approved by the purchaser Engineer.
Evaporator shall be of shell and tube type with removable heads and shall contain two direct
expansion refrigerant circuits. Construction shall conform to the ASME Code. The evaporator
6
shall have 2 inch thick polyurethane foam insulation and shall be protected by 20 Gauge steel
jacket.
Evaporator freeze-up can be a concern in the application of air cooled water chillers. To protect
against freeze up, insulation and electric heaters should be furnished.
The material for evaporator should be brazed plate heat exchanger constructed of 316 stainless
steel.
Shell side and tube side fluid shall be decided by Vendor based on pond water circulation rate
(800 m3/hr) and Chilled Water circulation rate to achieve desired cooling.
Design shall be as per ASME Section VIII Div I or TEMA.
All skids of Heat Exchangers shall be complete in all respects, piping, pipe fittings, insulation
and cladding for conservation of energy.
Piping shall be adequately secured from possible damage, properly supported on structural
members, relief valves outlet lines shall be at safe location and properly supported.
Vendor shall assume full responsibility for the entire HX train, including instruments (Sensors,
transmitters, cabling, JBs), all auxiliaries as deemed necessary for safe and uninterrupted
operation of the package. All instrumentation shall be properly wired to Local Control Panel.
Alarm and shutdown logic shall be failed safe.
Controls
The Chiller shall have microprocessor based controls having capacity control shall be either
modular or multi-step, fully automatic with manual option, and shall be fail-safe. Machine
shall shut down for low oil pressure, chilled water low temperature, refrigerant low pressure,
condenser high pressure, low refrigerant temperature, low condenser water temperature,
compressor discharge high temperature and motor high temperature. Controls shall ensure
thorough lubrication of compressor prior to start and during coast down after machine stop.
Motor shall be protected against drawing more than rated full load amperes.
Controls shall prevent machine restart unit after a safe pre-set time.
The control system should be user friendly with full description of current unit status, control
parameters and alarms. Security protection should be available to prevent unauthorized
changing of the set points and unit control parameters.
All controls shall be in weather proof enclosure, and shall include, but not limited to, power
controls for starters, low voltage control power transformers, terminal strips relays, high
pressure and low pressure controls, low temperature controls, motor protection, oil pressure
control and chilled water temperature controller.
Auxiliaries
Suction and discharge gauges, oil pressure gauges.
Safety Features i.e. High & Low Pressure Switches, phase asymmetry and under voltage relays,
compressor starting delay, internal thermal contacts of compressors and fans, compressor
crankcase electric heater, and oil pressure switch.
Flow switches and water strainer shall be provided in the optimum locations.
Materials
The material for Condenser coils should be seamless copper tubes with aluminum fins. Copper
fins, black fins, electro fins can also be used.
7
The material for evaporator should be brazed plate heat exchanger constructed of 316 stainless
steel.
Circulation pumps shall be API 610 compliant or end suction type pumps as per ASME B 73.1.
Pumps shall be with suction strainers, isolation valves, drains either studded or flanged, sensors
and pressure gauges for proper monitoring and control
Pumps shall meet desired flow duty and head requirements, i.e; 800 m3/hr pond water
circulation rate, 50 m head to circulate pond water to heat exchanger and then back to pond
Circulation pumps shall be API 610 compliant or end suction type pumps as per ASME B 73.1.
Pumps shall be with suction strainers, isolation valves, drains either studded or flanged, sensors
and pressure gauges for proper monitoring and control
Pumps shall meet desired flow duty and head requirements, i.e; Chilled water circulation to
Chilled water / Chiller refrigerant heat exchanger. Pump flow duty and head shall be by
package vendor.
Chilled water system shall be closed loop system with provision for make-up and chemical
addition for microbes or corrosion control.
Electrical Requirements
The unit shall be suitable for operation on 400 ± 10% volts, 50 Hz, 3-phase 3-wire electric
power and the control circuits. The enclosure shall be NEMA-1 and shall house the following
components; motor starters complete with thermal overload protection, for solution pump(s),
refrigerant pump & purge pumps, etc.
8
Copper tube and copper fins type
Condenser design is preferable choice
Preferable design is air cooled type
Compressor and Condenser
Integral lube oil system
As per data sheet
With Space Heater
Suitable for continuous operation
Designed for max ambient
3 Electric Motor Drive temperature
Name plate rating for 110% of max power
including all losses, exclusive of service
factor.
4
Pond Water Rated Flow duty 800 m3/hr, head 25 m circulate water to
Circulation Pumps 1W + 1S chilled water/Pond
Preferable choice centrifugal pump water cooler for heat
rejection.
Chilled Water
Vendor Scope of supplies
5 Rated Flow duty & head is by vendor
Circulation Pumps
1W + 1S
Preferable choice centrifugal pump
Vendor scope of supplies as
applicable.
Shell & Tube heat exchanger.
Chilled Water / Pond Total Pond Water circulation rate: 800 No of heat exchangers
m3/hr, Chilled Water circulation
6 Water Cooler (Heat depends upon vendor
capacity by vendor based on total
Exchanger) cooling duty desired design and selection
With support saddles/legs, all
associated nozzles, earthing lugs,
cleats for insulation etc. temperature
and pressure sensors
Vendor scope of supplies as
applicable No of heat
Refrigerant
7 Vaporizer / Chilled
Shell & Tube heat exchanger exchangers/coolers
With support saddles/legs, all depends upon vendor
Water Cooler associated nozzles, earthing lugs, design and selection
cleats for insulation etc. temperature
and pressure sensors
Closed system for
chilled water Vendor scope of supplies as
applicable.
8 storage/circulation
Vendor Standard.
with chemical Corrosion inhibitor / microbes control
injection dosing shall be considered
9
Screws
18 Anchor Bolts
Vendor Scope
19 Instrumentation
As per Compressor Package data sheet
Commissioning and Start-up
20 Spare Parts
2 Years Spare Parts List
Recommendation of Capital Spares
Surface Preparation
21 Manufacturer’s Standard, submitted
and Testing for review and approval
All materials shall comply with applicable local, International Standards and piping material
specification. Design life of the assembled skid shall be for 20 years minimum.
Environmental Conditions
Location: Dhahran
Elevation: 26 m above sea level
Summer Dry Bulb Temperature: 44°C
Summer Wet Bulb Temperature: 23°C
10
Daily Range 12°C
Winter Dry Bulb Temperature 8°C
The COMPANY Project Specifications shall be used in conjunction with this design basis wherever
applicable and mentioned hereafter in the respective discipline section. In case of conflicts in
technical requirements, the following order of precedence shall apply:
While deciding on the order of priority, due consideration shall be given to safety and ease of
operation and maintenance in this order of precedence.
2.7.1 Language
All literature, documentation, correspondence, and other printed matter pertaining to this
Material Requisition shall be in the English Language.
2.7.2 Submission
VENDOR shall submit to Client/Consultant as minimum, all the documents listed in
Attachment – 2: Vendor / Supplier Data Requirement List, OR “Vendor’s Standard
VDRL approved by Client/Consultant” along with quotation.
Vendor to provide minimum details required for the Client/Consultant to understand and
accept VENDOR’s procedure and progress.
Vendor to provide minimum details required to carry out CLIENT’s related procurement
work, construction work etc., in accordance with, but not limited to, the requirement
specified in “Applicable Documents List”.
All documents to be submitted to Client/Consultant shall bear this requisition
number/PO number.
11
Vendor shall submit to Client/Consultant his previous Project experience summary.
All the documents & technical data shall be provided in English language.
Unless otherwise specified, all quantities, dimensions and drawings etc. are to be in SI
units.
Any revision to a document after its first submission shall be clearly identified on the
document in the revision box. Once issued, a document number shall not be changed or
re-used.
All necessary documentation required for the Vendor Data Book shall be submitted.
Vendor Data Book shall include VENDOR’s instructions for installation, operation and
maintenance, cross-section drawings, lubricating and regulating oil schemes, part-
numbered drawings, parts lists, spare parts details, performance curves of Rotating
Equipment(s), FAT reports, etc.
Submission of all documents is an integral part of the Purchase Order Obligation. The
Purchase Order shall only be complete when all document requirements have been
fulfilled and are accepted by Purchaser and Client. For further detail see “Vendor
Documentation Requirement List”
12
Vendor’s Name, Address & Logo :
Purchaser Name, Address & Logo :
The price of the spare parts shall be indicated separately item by item as detailed below.
“Construction & Commissioning Spares” are parts or components used during the
mechanical completion, pre-commissioning and commissioning activities up to the
completion of Performance Tests of Equipment and or Acceptance.
VENDOR may also recommend any other spares as deemed necessary.
VENDOR shall recommend and provide list of spare parts needed for two (02) years of
operation and provide a price list.
CLIENT may purchase the spares listed in the VENDOR’s recommended list.
Parts List and sectional drawings or equivalent showing location of parts quoted and
referenced on data sheets, product manual / brochures etc., shall be provided by
VENDOR.
VENDOR may recommend Insurance Spares which are high value, low turnover, and
any other spares than the above, from the viewpoint of protection against serious or
catastrophic failures of the plant and long lead time in the manufacturing schedule.
13
VENDOR shall recommend quantity and price list of any capital spares as a separate
quote at the time of proposal.
CLIENT may purchase capital spare parts with Equipment/Material after review.
One set of Commissioning Spares, including all the required consumables shall be
provided by the VENDOR along with Insurance Spares, as required.
VENDOR shall provide a list and relevant documentation of special tools, if required for
the purchased item.
VENDOR shall supply one (1) complete set of special tools and devices necessary to
facilitate lifting, erection, testing, start-up and maintenance of the equipment and all
other required accessories.
These shall be easily identified and supplied in a lockable steel cabinet for small tools.
For the equipment/materials that cannot apply single point lifting, spreader bar or lifting
beams shall be provided. Lockable steel cabinet is not required for these big
equipment/materials.
3.0 QA / QC REQUIREMENTS:
Vendor shall meet the technical & Quality Requirements of the WORK. Vendors Quality System
shall meet the appropriate ISO 9001 system requirements. The Vendor shall be evaluated,
approved, and listed as accepted supplier by SENDAN INTERNATIONAL CO. LTD and Saudi
Arabian Industrial Investments Co. (DUSSUR) prior to placing the purchase order.
Vendor shall provide the unpriced P.O. Copy including the sub orders where exist.
Vendor shall submit "Quality Plan" for the purchaser's approval. This quality plan will provide
detail of the Vendor's quality system to the work. The Plan shall specifically provide detail how
each element of the quality standard is applied to the Work and shall also contain below:
a. Vendor's organization chart for the work
b. The List of procedures / Method statement for the work
c. A schedule identifying internal and external audits
14
Supplier and manufacturers of inspectable equipment and material have and maintain acceptable
Quality programs in accordance with the ISO-9001 quality standard. Vendor shall ensure that all
technical and inspection requirements are passed on to sub suppliers.
For Inspection involving Surveillance & above up to Hold and Witness, Vendor shall prepare
Inspection and Test Plan (quality control plan) in accordance with “Attachment-3: Inspection &
Test Plan” to meet client requirements / Purchase Order and shall be submitted to SENDAN for
review and approval prior to Pre-Inspection Meeting and shall be approved prior to start of
fabrication. Review and approval of vendors detailed ITP will be finalized during the Pre-
Inspection Meeting.
15
4.0 GENERAL REQUIREMENTS
4.3 Marking
Marking of the Equipment / Materials shall be as per requirements of the Purchase Orders
and applicable standard. Vendor shall mark each crate with the Purchase Order and Item
Number using 50.8 mm (2 Inch) high painted letters.
4.4 Interpretation
In any instance where the name of a particular manufacturer appears herein, such shall be
interpreted to mean the product of that manufacturer or its equivalent (unless purchase of a
particular manufacturer’s product is shown as mandatory).
4.5 Preservation
Vendor shall state any special requirements for storage at the required site, in order to
comply with local environmental conditions.
Vendor shall specify any conditions, normal or special, to be taken care during the
intermediate storage and transport.
Spare parts shall be preserved from environmental corrosion, and preservation methods shall
be suitable for long term storage (in a marine atmosphere during shipping and storage
according to atmosphere at site).
4.6 Packing
Vendor shall pack material to ensure environmental and transit protection of the equipment
and shall submit packing design and packing details for buyer’s approval.
Packing shall be done as per the below mentioned packing specifications as applicable.
The VENDOR is responsible for preparing the equipment(s) for shipment in such a manner
that it will arrive undamaged and ready for installation.
The VENDOR shall ensure that all deliverables are designed and packed for transit to site
and that packing is suitable for export, seaworthy, transportation with an anticipated 6
months site storage period
The equipment shall not be shipped before CLIENT’s inspector has issued a “Release note
for shipment”.
All exposed machined metal surfaces (such as flange faces and bolting) shall be protected by
applying suitable grease, rust preventive oil or coating.
Equipment shall be marked with the center of gravity location before shipping.
All loose equipment shall be packed separately, clearly and accurately tagged to enable site
assembly to be carried out.
16
All openings shall be provided with temporary enclosures (like metal covers with bolting
arrangement) bolted to the flanges to prevent entry of dirt, other materials and protect the
flange facing.
VENDOR shall recommend, if required, knockdown instructions for
CLIENT/CONSULTANT’s review and approval.
VENDOR shall comply with the export control laws and regulations regarding the export to
foreign countries of any item or related data under the laws and regulations.
Steel shipping saddles (skids) shall be supplied by Vendor.
4.8 Tagging
All instruments shall be Tagged as per Engineering Standards and Procedures. Contractor
shall provide instrument Tag Numbers to the vendor.
All the shipped loose, shall be physically tagged with Stainless Steel Tags by the Vendor.
17
4.10 The Proposal
The Proposal must include a list of exceptions / exclusions to the specifications attached to the
present enquiry.
Any exceptions / exclusions are not indicated in the proposal it will be understood the
proposal is in full agreement/compliance with the specification.
4.11 Inconsistencies
If any inconsistency exists between this requisition, the attached documentation and other
applicable documents, industry standards or drawings, the inconsistency will be solved in
writing.
18
contracted for by the construction contractor. The services detailed above will only be used on
an emergency basis. In the event they are not used, the incidental services line item shall be
cancelled from the purchase order.
5.2 Field Services Instruction to Buyer:
Incidental services will be required during commissioning. Services requires include
Supervision where required during commissioning and trouble shooting in the event problem are
experienced during Start-up & initial operation. Vendor / Manufacturer shall provide production
schedule, the required quantities and manufacturer’s capacity should be specified.
6.0 ATTACHMENTS
19
ATTACHMENT - 1: APPLICABLE DOCUMENTS LIST
20
ASME Sec VIII Rules for Construction of Pressure Vessels Latest edition
ASME Sec IX Welding & Brazing Qualifications Latest edition
ASME B 16.11 Forged Steel Fittings, Socket-welded and Latest edition
threaded
ASME B 16.20 Metallic Gaskets for Pipe Flanges – Ring- Latest edition
ASME B 16.21 Nonmetallic Gaskets for Pipe Flanges Latest edition
ASME B 16.5 Pipe Flanges and Flanged Fittings up to & Latest edition
including NPS 24 inch
ABMA std-9 Load Ratings and Fatigue Life for Ball Latest edition
bearings
ABMA std-11 Load Ratings and Fatigue Life for Roller Latest edition
Bearings
ABMA std-20 Metric Bearings Boundary Dimensions Latest edition
PIP VEFV1100M Vessels/S&T Heat Exchanger Standard Latest edition
Details
PIP VESS M001 Specification for Small Pressure Vessels and Latest edition
Heat Exchangers with Limited Design
Conditions
WRC 297 Welding Research Council Bulletin - Local Latest edition
Stresses in Cylindrical Shells due to External
Loadings on Nozzles
NFPA 70 National Electrical Codes Latest edition
NEC-250 National Electrical Code for Grounding & Latest edition
Bounding
AGMA Gear Manufacturers Association Latest edition
TEMA Tubular Exchanger Manufacturers Latest edition
Association for shell and tube type heat
exchangers
IEC – 60034 Rotating Electric Machines Latest edition
IEC-60529 Classification of Degrees of Protection Latest edition
NEMA MG-1 Motors and Generators Latest edition
ASHRAE American Society for Heating, Refrigeration
and Air Conditioning Engineers
SMACNA Sheet Metal and Air Conditioning
Contractors National Association
AHRI Air Conditioning, Heating and Refrigeration
Institute
API 610 Centrifugal Pumps for Petroleum,
Petrochemical and Natural Gas Industries
ASME B73.1 Specification for Horizontal End Suction
Centrifugal Pumps for Chemical Process
21
ATTACHMENT - 2: VENDOR / SUPPLIER DATA REQUIREMENT LIST
SUBMIT FOR
SUBMIT INFORMATION /
VDRL
DOCUMENT TITLE WITH AS BUILT
REVIEW / APPROVAL
CODE TENDER
DATE REQ’D FR/FA/FI
GI GENERAL& INTERFACE
4 Sub-Vendor list E FA
TD TECHNICAL DOCUMENTS
22
views (plan, elevation, side view)
QA/QC
QA
All QAQC procedures shall be approved before its
application
23
NDE/NDT procedures
Notes:
Documents required dates are preliminary and shall be finalized in KOM after P.O as per
client’s requirements.
Apart from the above, VENDOR shall ensure that documentation as stated in the respective
equipment applicable standards shall be included as part of VDRL.
All documents issued to CLIENT/CONSULTANT must be issued via a transmittal or as
mutually agreed.
Drawings and documentation are accepted by Purchaser when signed by Vendor. All revised
editions of drawings or documents shall show the revisions and revisions marks clearly
indicated.
24
As Built copies of documents to be included in Manufacturing Data Record Book.
CLIENT documentation template & numbering system is to be used for all VENDOR
documents.
25
ATTACHMENT - 3: SCOPE OF INSPECTION&TESTING
Equipment: Air Receiver, Refrigeration Air Dryer (Condenser, Vaporizer), Pre & After Filters
Piping and Complete Compressor Unit
Test and Inspection Inspected by Record Remarks
Vendor Contr. Comp.
PIM Pre-Inspection Meeting H H R
Material Test Certificate (Type….) R R R OR
Identification of Materials W W R IR
Materials Transfer of Material Marking (Material,
W S R IR
Heat No., etc.)
Sub-Orders R R R OR
Welders / Operators Qualifications W W R
Welding Procedure Specification (WPS) +
R R R OR
Repair Procedure
Procedure/ Welding Procedure Qualification Record W: New
H W R OR
Qualifications (PQR) PQR
NDT Procedures R R R OR
NDT Operators Qualifications R R R OR
Manufacturing Procedures R R R OR
Liquid Penetrant / Magnetic Particle
W W R OR
Examination
Ultrasonic Examination W W R OR
Film
Non Destructive Radiographic Examinations R R R OR
Review
Testing
Gasket seating surface W S R OR
Hardness Checks W S R OR
Confirmation of Chemical analysis for R R R OR
materials
Production Test Coupons H W R OR
Destructive Impact test H W R OR
Testing Hardness Checks W S R OR
Positive Material identification W S R OR
Welding Consumable Control W S -
Bevel Preparation / Fit up IW S -
Back Gouging before Welding Reverse
W S R IR
Side
Welding Parameters / Operation + Repairs W S R IR
Forming/Manufacturing IW R R IR
With
PWHT (Location Thermocouples Review
W R R OR recording
Fabrication of Records)
chart
Dimensional / Visual Check H H R OR
Leak Test for Pad Plate and nozzle sleeve H R R OR
Hydrostatic or Pneumatic Test for H H H OR
Compressor Casing
Hydrostatic or Pneumatic Test for Vessel, H H H OR
Heat Exchanger/Condenser
Alloy verification W S R OR
26
Test and Inspection Inspected by Record Remarks
Vendor Contr. Comp.
Mechanical W W S OR
Complete Compressor unit + Refrigeration
running test &
Dryer Unit
Performance Test
Leakage Test Vessels, Condenser, Compressor Casing W W S OR
Complete Compressor unit + Refrigeration W W S OR
Sound Level Test
Dryer Unit
Painting Shot Blasting (Surface preparation) /
W IW R OR
Inspection Painting
With
Preparation for Drying / Preservation W W R OR
certificate
Shipment
Packing / Marking W W -
Confirmation of Completion for All
H H W
Final Inspection Required Test and Inspection
Inspection Record Book (IRB) H/R H R OR
Site Acceptance H/R H H OR
Site Acceptance Test
Test (SAT)
Legends:
H-Hold, R-Doc Review, W-Witness, IW-Initial Witness, S-Surveillance, OR-Official Record, IR-Internal
Record
27
ATTACHMENT - 4: COMPLIANCE, DEVIATION & EXCEPTION FORM
Compliance
Sr. Accepted (A) /
Specific Requirement Deviation Exception Remarks
No. Not Accepted
(NA)
28
ATTACHMENT - 5: EQUIPMENT DATA SHEET
29
SeAH GULF SPECIAL STEEL INDUSTRIES PROJECT (SGSSP) KING SALMAN
PROJ NO. & TITLE
ENERGY PARK (SPARK),DAMMAN KSA
REFERENCE DOCUMENTS
S/N DESCRIPTION REMARKS
DESIGN BASIS FOR INSTRUMENTATION & CONTROL
1
SEN-SGSSP-GC-P&I-IN-PRO-002
PROCESS DESCRIPTION & DESIGN BASIS (UTILITY SYSTEMS)
2 SEN-SGSSP-GC-P&I-PS-PRO-001
DESIGN PARAMETERS
Sr. No Description Units Requirement Rev.
1 Chiller Type - Air Cooled Electrical Screw Type
2 Refrigeration Capacity (Each Unit) Kcal/hr 1,760,000
3 Quantity Nos. n + 1 ("n" numbers Working+1 Stand by)
4 Refrigerant Used - V.T.S
5 Refrigerant Flow Control - V.T.S
6 Make - V.T.S
7 Model - V.T.S
8 Operation - Continuous
9 Installation (Indoor/Outdoor) - Outdoor
Location - Dhahran
Summer Dry Bulb Temperature ⁰C 44
Site Summer Wet Bulb Temperature ⁰C 23
10
Conditions Daily Range ⁰C 12
Winter Dry Bulb Temperature ⁰C 8
Altitude above sea level m 26
Evaporator Type - Shell & Tube HX/ V.T.C
Inlet Temperature of Chilled Water ⁰C VTS
Outlet Temperature of Chilled Water ⁰C VTS
(Evaporator)
Chilled USGPM VTS
Chilled Water Flow Rate
Water/Refrige m3/hr VTS
11
rant Heat
Max. Allowable Pressure Drop for chilled
Exchanger
water (Tube Side) /Refrigerant (Shell bar 0.50 / 0.35
(HX)
Side)
Inlet / Outlet Connection DN V.T.S
Tie-In Point (Size/Rating/Face) - V.T.S
Refrigerant Inlet Temperature ⁰C V.T.S
Refrigerant Outlet Temperature ⁰C V.T.S
Tubes and fins material - Copper Tubes with Aluminum Fins / V.T.C
Pond Water 800 (10% design margin to be considered both on flow n head by
Pond Water Flow Rate
15 Circulation vendor)
Pump Pump head meter 25
Pump power consumption V.T.S
16 Power Supply 400 V±10%, 3-phase, 50 Hz
17 Total Power Consumption kW V.T.S
18 Starter Type - V.T.S
19 Type of Controls - Microprocessor based Controller
Length (L) mm V.T.S
Overall
20 Width (W) mm V.T.S
Dimensions
Height (H) mm V.T.S
DATA SHEET FOR AIR COOLED CHILLER Rev.: A
PACKAGE Date: 07-Mar-2023
SEN-SGSSP-GC-P&I-IN-DS-005 Page No. 5 of 5
NOTES:
1- Refrigerant should be Non-CFC.
2- Chillers shall be Careeir/York/Zammil/Eurovent Certified
3- Vendor to specify the requirement of water treatment in Chilled water circuit.
4- RO Type water is used in Chilled Water circuit and will circulate in closed loop in Chilled water / Refrigerant gas heat exchager .RO water parameters are
attached with the MR. RO Water shall be used for Make-up as well.
While Pond water will be used for getting cooling and it will circulate in open loop.
5- V.T.S stands for Vendor to Specify. Vendor shall furnish all the missing information in the data sheet and submit along
with the offer.
6- One Refrigeration Ton (USRT) = 3.517 kW = 12,000 Btu/hr.
7- Each Chiller shall have its own microporcessor controller for controlling its own funtions. It shall also communicate with
the main plant room controller as well as the remote monitoring host terminal for visualizing its functions/parameters and
further changing the set point value when required.
8- Chillers shall be provided with suitable Controls and Safety System features necessary for safe and continuous trouble
free operation of the chillers . All Chillers will be controlled through Microprocessor based control system installed with Chillers.
9- Each Chiller shall have its own controller which will control the operation of Chiller.
10- The Chillers shall also have a master controller which will optimize start/stop of chillers and associated chilled water pumps
11- All required peripheral instrumentation needed for the chiller and associated pumps optimizatioin should be hooked up with this master
controller.
12- Soft type starters shall be provided with Chillers by the vendor.
Control system provided with Chillers shall control both Water Pumps & Air Condensers operation and their capacity control.
13- Tie-In connection details shall be provided after finalization of P&ID's
14- Vendor to specify the sound level for Chillers
15- RO Water specifications:
Electrical Conductivity: 10 Us/cm @ 25 0C