The document discusses setting the frame size for a cyclic scheduler. It outlines three key considerations when setting the frame size: 1) the frame size must be larger than any task's execution time, 2) the frame size should minimize the size of the schedule table by dividing the major cycle, and 3) there must be a full frame between a task's arrival and its deadline. The document then examines how to satisfy tasks' deadlines given these constraints and derives mathematical conditions for a feasible frame size.

Uploaded by

Aya abu nada
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
14 views13 pages

Lec 5

The document discusses setting the frame size for a cyclic scheduler. It outlines three key considerations when setting the frame size: 1) the frame size must be larger than any task's execution time, 2) the frame size should minimize the size of the schedule table by dividing the major cycle, and 3) there must be a full frame between a task's arrival and its deadline. The document then examines how to satisfy tasks' deadlines given these constraints and derives mathematical conditions for a feasible frame size.

Uploaded by

Aya abu nada
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 13

Real Time Operating System

Prof. Rajib Mall


Department of Computer Science and Engineering
Indian Institute of Technology, Kharagpur

Lecture – 05
Cyclic Scheduler (Contd.)

Welcome back. If you remember over the last few lectures, we are looking at some real
time tasks schedulers. We had looked at very simple schedulers like table driven
schedulers, but then we saw that it has it disadvantage requiring to set a timer again and
again after each tasks execution. We had remapped that time that the cyclic scheduler is
extremely popular, because it does not require stetting a periodic timer again and again; it
just needs to set it once during the initialization. It requires to design tasks is to be done,
one is to sit the major cycle for a set of periodic tasks and then also to set the minor cycle
which is also called as a frame. Major cycle is rather simple to compute if you remember
it is the LCM of the task periods. But then setting the frame size is not that straight
forward it is non-trivial, we need to consider several design alternatives and may have to
iterate between our frame sizes may be we have to split the tasks and so on.

So, setting the frame size is a important design task while using a cyclic scheduler. Let us
see how the frame size is to be set.

(Refer Slide Time: 02:17)


The first consideration is that each frame size must be larger than the execution time of
every task. If you remember why this is so, it is because every frame size must hold the
task or in other words if a task is taken up for execution in a frame, it must complete
within the frame. It should not spill over to the subsequent farms and that is the reason a
frame size should be larger than the largest task execution time.

So, based on this consideration, we get a lower bound for the frame. The frame if it
become lower than the largest tasks size, then that is not a good schedule it will have
problems as we will see. The second consideration is minimisation of the schedule table
that we have to store. From this consideration, we require that the frame size that is
chosen should squarely divide the major cycle or it must be a factor of the major cycle.
Based on this consideration we can select only few discrete frame sizes. If the frame size
does not squarely divide the major cycle, then we have to store the schedule for several
major cycles. If the frame squarely divides the major cycle then after the major cycle the
same tasks sequence will repeat. So, we need to store only the tasks schedule for one
major cycle.

The third consideration is every task must meet it is deadline, and for this to happen there
must be one full frame between the arrival of a task and it is deadline. To see why it is so,
we need to consider that if a task arrives just after a frame has started, then the task
cannot be taken up in that frame and if it is deadline also is within the frame, then the
task execution cannot be started before it is deadline.

So, you must have at least one clear frame between a tasks starting and it is deadline. A
corollary of this third condition is that the frame size has to be greater than every task
period. So, this sets an upper bound for the frame size. So, a frame size must be less than
every task period.
(Refer Slide Time: 05:54)

So, let us see we will get more explanation on this as we proceed. So, the first condition
is that the frame size must be chosen such that every task must be able to execute in the
frame size because if that does not happen then we have to run the task across multiple
frames. So, in that case other tasks may run in between and then you use the partial
results obtained by executing a task halfway or may be a partially and then that may lead
to inconsistency.

So, normally we would need that frame size should be larger than the execution time of
every task the second condition. So, the first condition we just saw that, that the selected
frame size should be larger than execution time of each task.
(Refer Slide Time: 07:07)

The second condition is minimisation of the table size. So, this is the schedule table
which we need to store the schedule table if you remember is for every frame, which task
is to be run. So, as the task as the frame interrupts come the scheduler just takes up the
task by consulting the table.

So, a first frame we took up the green task, the second frame the red task, third frame
yellow task and so on. And after the major cycle the same sequence repeats, that is
because the frame last frame boundary coincided with the major cycle and by this time
all the tasks are run. So, this is the LCM of all the task period and therefore, every task
period also has the ending of that has coincided here, but if the frame boundary does not
coincide with the major cycle boundary it spills over then we have to run for we have to
store the schedule table for many major cycles. And from this consideration we get the
condition that the frame size should divide the major cycle, it should be a factor of the
major cycle and that gives us only few discrete choices to select the frame size.
(Refer Slide Time: 08:51)

Now, let us look at the third condition, which says that the frame size should be chosen
such that every task deadline must be met. So, let us see; what is the implication of this
condition, let us say we have this frame boundary starting at this point. So, we have the
frame boundary starting at this point. Now let us assume that after a delta time after some
time the task instance t i arrived at this point.

Obviously, the task cannot be taken up during this frame because the if you remember
the scheduler code that it just executes the task and then the scheduler ends the scheduler
comes up just before every frame, starts execution of the task consults the schedule table
finds out which task to run it runs and then it stops. So, it can only run a start at the
starting of a frame boundary, but here the task has arrived just after the frame boundary;
obviously, it cannot run on this frame, and then it can only be taken up in the next frame
next frame boundary.

But then when the task is started to execute at the next frame boundary, the deadline is
very near it cannot meet it is deadline. And this condition requires that we must have at
least one full frame between the arrival of the task and the deadline, because if there is
full frame existing here let us say we have frame here then if the task arrives here then it
can at least be taken up execution in the next frame, and we know that the frame size is
larger than every task execution time. And therefore, it will complete within the frame
and it is deadline is after that.
So, the third condition requires that we must have one clear frame existing between the
arrival of a task and it is deadline.

(Refer Slide Time: 11:49)

So, let us look at the satisfaction of the task deadline, we just saw that the worse case for
a task occurs when the task arrives just after the frame has started. Because if the task
arrives towards the end of a frame, then the next frame it can be taken up. So, the worst
case occurs if a frame has just started and the task arrives. Now let us compute how
much is this, what is the worst case scenario because every task if it arrives anywhere
towards the end of a frame that is not a worst case, because it can immediately be taken
up in the next frame.

So, the maximum time a task would have wait if it arrives just after a frame boundary.
(Refer Slide Time: 13:05)

So, we need to do a little bit of mathematical derivation and we will not really go into
derivation it is there in the book, here we just look at the result, the result is GCD the
frame size and the period of the task. So, the greatest common devisor between the frame
size and task period that gives the worst case situation of how much after the frame starts
can a task arrive.

So, if the GCD is one then at most after one time unit the task can occur. So, from this
consideration considering the worst case situation, then we have F minus GCD, F minus
p i is the waiting time here. Because it cannot be taken up for scheduling during this
duration and therefore, it must wait for F minus GCD minus GCD F, p i and then we
must have another clear frame. So, as long as 2 F minus GCD F comma p i is less than
equal to d i, then we have a clear frame available between the tasks arrival and the
deadline even in the worst case situation.

So, the third condition we can the write in this expression and we will see given a tasks
set whether it satisfies these and then if it satisfies, then we can take the frame size as
feasible otherwise we have to discard that frame size.
(Refer Slide Time: 15:04)

So, written down the 3 conditions here, the first condition is that the frame size f must be
greater than the execution time of every task. So, the maximum execution time of the
tasks, even that that f should be greater than even the maximum execution time of a task.

The condition that there must be a clear frame between the arrival and the deadline gives
us this condition, the worst case 2f minus GCD p i comma f the task period and f it
should be equal to the deadline of the task, that must be satisfied for every task i. The
third condition is that the frame size must squarely divide the major cycle. The major we
have written the LCM p i and this is the integer division f and when multiplied by f if we
get back the LCM p i, then you can say that the frame size squarely divides the major
cycle.
(Refer Slide Time: 16:27)

Now, let us consider the design trade ups, we find that there may be several frame sizes
which may become feasible we call that as plausible frames, but when just because the
they satisfied the 3 conditions and have got a plausible frame, does not mean that we
have found a schedule, we have to check other things. The first thing we need to check
whether the number of frames that we require to schedule the task exists. Let us say the
task would not runs 3 times in the major cycle. So, the period of the task is one third of
the frames of the major cycle, and the second task it runs 2 times during the major cycle.
So, it is period is half the major cycle. So, we need five frames for these 2 tasks.

So, the frame size must be chosen such that there must be five frames, within the major
cycle. Let us look at as we look the example it will become clear. If I find that multiple
frame sizes become possible, then we need to choose the largest of those frame sizes; let
us say the frame size 5 and 8 both of these are possible they satisfy all the 3 conditions
and also they give rise to enough frames where all the instances arising during the major
cycle can be scheduled, then we need to choose the larger of the frame size that is 8 why
is that. Why do we need to choose the larger of the frame size a little thinking will show
that at every frame boundary, the scheduler needs to run?

So, if we choose 5 as the frame size then there will be many frame boundaries compared
to when we choose 8 as the frame size. So that means, the scheduler runs more
frequently if we choose a smaller frame size compared to a larger frame size or in other
words the overhead of the tasks scheduler becomes more when we choose a smaller
frame size and therefore, we always choose a the largest frame size that is possible. So,
the scheduler overhead is lower when we choose a large frame size.

(Refer Slide Time: 19:40)

Now, let us take a few examples the first example we have 2 tasks A, B and the first
element is here is 1 is the computation time. So, a takes one unit of computation it is
period and deadline are the same. So, that a deadline occurs exactly at the period. So, it
repeats after every 6 time units and before it repeats before the next instance comes, the
first instance must have been over that is the implication of the relative deadline. The
second task b execution time is 2 the period and deadline are both 8.

Now, our task is to choose the major cycle and the minor cycle choosing the major cycle
is rather straight forward you just take LCM of 6 and 8, and I find that the least common
multiple of 6 and 8 is 24. 24 holds an integral number of a task A and task B. So, we can
see that there are 4 instances of task A, 3 instances of task B within one major cycle. So,
within one major cycle we will have 7 instances altogether considering both A and B.

Now, let us try to choose the frame size. If you remember that the frame size must
squarely divide the major cycle, that we get from the schedule table consideration
minimising the size of the schedule table and therefore, we can get 24 12 6 4 3 2 these
are the frame sizes that are that we can consider for the other conditions. Why not one we
have not written one here because the size of the task B is 2 and every frame size must
hold must be greater than or equal to the largest task size and therefore, one we have not
considered consider 2, 3, 4, 6, 12, 24.

Now, let us see we start with a smallest frame size and see if that becomes possible to
satisfy the other conditions. So, let us check F equal to 2 and we will check if there is a
full frame existing between the arrival of the task and it is completion in the worst case
and I had expressed it in the formula 2 into F minus GCD f comma the task period. So, 2
into f, f is 2 and therefore, 2 into 2 minus the GCD of f is 2 and the period is 6.

So, the GCD of 2 and 6 is 2 and therefore, we get 4 minus 2 is 2 and 2 is less than equal
to 6. So, this is fine similarly we can check for the second task n. So, 2 into F minus
GCD f comma the period of the second task, 2 into 2 and GCD of 2 and 8 is 2 which is
equal to 4 minus 2 is 2, 2 is less than equal to 8. So, frame size 2 is and also the number
of frames that it can give us is 24 by 2 is 12. So, 12 frames to 7 of those frames we can
assign an instance of A or B as required and 5 frames will remain unutilised.

(Refer Slide Time: 24:57)

Now, let us look at frame size 3. So, again we apply the similar conditions here 2 into F
minus GCD f comma p i we find that it is check for the second task also we find. So,
even frame size 3 is and we have 24 by 3 which is 8 frames available in one major cycle
and we have 7 task instances in a major cycle and therefore, even this is acceptable now
let us look at F equal to 4. In F equal to 4 again we use these 2 expressions and we find
that both of these again become acceptable, but then the number of frames become in
available is 6, 24 by 4 is 6 frames and we cannot schedule 7 task instances in 6 frames.

So, not enough frames are available and therefore, F equal to 4 we cannot choose and no
point in looking further ahead 6 8 etcetera, because the number of frames becomes still
smaller and therefore, 3 is the largest frame size for which we can have a possible
schedule and based on this our design choice will be the frame size equal to 3.

(Refer Slide Time: 26:38)

Now, let us look at another example we have 4 tasks sets A, B, C, D with execution time
of 1, 3, 2, 8 and their periods are 10, 10 20, 20. Now how do we find the major cycle?
The major cycle is the LCM of the task periods and here there are only 2 periods 10 and
20. So, the LCM of 10 and 20 is 20. Now the next thing is to choose the frame size. So,
the frame size must be larger than the execution time of all tasks greater than or equal to
all tasks and also it has to satisfy the other conditions.

So, you find that it must divide the major cycle and based on that condition we get 1 2 4
5 10 and 20, but then it must be larger than 8 and therefore, we have only 10 and 20 is
the possible frame size. So, in none of these cases, the frame size can be either 10 or 20.
So, if it is 20 we have just one frame and if it 10 we have just 2 frames. So, in none of
the cases we can have a schedule worked out, because we have 2 instances of these 2
instances of these and one of these and one of these in one major cycle. So, that gives us
6 instances and we need at least 6 frames, but then we are getting only either 1 or 2
frames.

We cannot schedule these tasks set, if you can see the major culprit here is this 8 here. As
we proceed we will see how to handle this situation this task set is becoming un-
schedulable, how do we make it schedulable on a cyclic scheduler. We will stop here and
we will continue in the next lecture at from this point.