Lecture 6 - ABC Costing Revised
Lecture 6 - ABC Costing Revised
Lecture 6 - ABC Costing Revised
UG027
SEMESTER 4
LECTURE 6
Undergraduate Department
Learning objectives
▪ Dinner of 4 persons
▪ Waleed $38, Fatima $32, Ahmed $25, Joan $27
▪ Total = $122
▪ Split the bill in 4 and everyone pays = $30.50 (W1)
W1= (38+32+25+27) = 122 ÷ 4 = $30.5
➢ Objective is to measure and then price out all the resources used
for activities that support the production and delivery of products.
Example: Lens manufacturing
(Absorption Costing Method- traditional costing)
NL CL
Quantity produced 80,000 20,000
Total setup-hours 640 2,000
❖ The main limitations of ABC are the measurements necessary to implement the system.
❖ ABC systems require management to estimate costs of activity pools and to identify and measure
cost drivers for these pools.
❖ Very detailed ABC systems are costly to operate and difficult to understand.
Practice Question -6 ABC Costing
Bradford plc manufactures product A and B. The following information is available from the company:
Product A Product B
Units produced 5,000 20,000
Selling price 400 200
Direct materials and labour per unit 200 80
Direct labour hours 25,000 75,000
Direct labour hours per unit 5 3.75
The company has a total budgeted overhead of £2 million. The following details are also available about overheads:
Budgeted cost Cost Driver A B
Engineering £ 125,000 Engineering hours 5,000 7,500
Set-ups 300,000 Number of set-ups 200 100
Machine running 1,500,000 Machine hours 50,000 100,000
Packing 75,000 Number of packing orders 5,000 10,000
Total 2,000,000
1. Calculate the overhead rate per direct labour hour (predetermined absorption rate)
1 2 3 = 1÷2
Activity Cost £ Cost Driver Total Number of Cost Cost Driver
Drivers Rate £
Engineering
Product A=5000 x10=50,000 50,000 75000
Product B=7500x10= 75,000
Set Up:
Product A=200 x1000=200,000 200,000 100,000
Product B= 100x1000= 100,000
Machine Running :
Product A=50,000x10=500,000 500,000 1000,000
Product B= 100,000x10= 1000,000
Packeging :
Product A=5,000x5=25,000 25,000 50,000
Product B= 10,000x5= 50,000
Total 775000 1225,000
÷ Number of units ÷ 5000 ÷ 20000
Product A Product B
Absorption costing 100 75
ABC costing 155 61.25
Diffference 55 under costed 13.75 overcosted