P21e1288r1 Pi For 100 TPD Refinery
P21e1288r1 Pi For 100 TPD Refinery
P21e1288r1 Pi For 100 TPD Refinery
Page 1 of 4
IV 100 TPD Deodorization Unit consists of - 1 Set
1 Heat Exchangers
2 De-aerator
4 Deodorizer with Inbuilt Economizer
5 Super Heater
6 Citric Acid Dosing system
7 Polish Filters
8 Scrubber
9 Vacuum System
10 Process pumps with drive and accessories
11 Valves
12 Control Panel
B Supervision charges for Erection and 23,000 23,000
Commissioning activities consists of -
1 Site Engineer for 5 months
1 Commissioning Engineer for 1 month
1 Electrical and Instrumentation Engineer for 2
months
Total Amount on Ex-works Basis in Rs. 813,000
In words Eight Hundred Thirteen Thousand Only
Freight To Be Charged Extra At Actuals at the time of Dispatch
Optional
V Automation with PLC control system for the 1 Set 180,000 180,000
complete refinery plant with Instrumentation
Page 2 of 4
Listof Exclusion
1 All civil works and foundation of equipments and foundation bolts
2 Painting materials and works
3 Insulation Material
4 Steam Generatio & Distribution
5 Chiller & Water Pumping System
6 Thermic Fluid Heater
7 Intermidiate/ Process Tanks
8 Pipes and Fittings
9 Electrical & instrument Cables & Trays
10 Lifting Tackle & Cleaning Table
11 Cooling Tower and cold water circulation
12 Lab Equipments
13 Steel Structure materials for equipment support, railing, ladder, working platform etc
14 Roofing sheet and claddings
15 Bulk Oil Storage Tanks with Pumps, Pipe line etc
16 Main power receiving station and power distribution system
17 Fire extinguishers, fire hydrtants etc
18 Skilled/unskilled labours, Tools, tackles,Workshop equipments and consumables like
welding rods, cutting gas etc for installation of the plant
19 Workshop equipments
20 Oil packing and filling unit
21 By-product storage, disposal
22 Effluent treatment plant
23 Weigh bridge
24 Unloading of the equipments at site
25 Weighing arrangement for oil and chemicals
26 Lubricants, distilled water, refrigerant for refrigeration system
27 Installation of the plant
28 Visa charges, return air fare tickets from Bombay to site and local transport from house to
site for the Supervisors
29 Boarding and Lodging
30 Nominal pocket money of US$ 10/day/person
31 Insurance for all risks and medical cover for the Supervisors to be made before their
32 All other items not specifically mentioned in the offer
Notes:
a) Our supervisors will arrive at site once the civil work and foundations is completed as per our
drawings. Our commissioining engineer will come once the plant is completely installed and
b) ready for commissioning
Supervision charges are based on fixed duration mentioned in our offer. If the stay of the
Supervisors exceeds the estimated days as above, will be charged on Pro-rata basis
c) All goods will be guaranteed against manufacturing defects for one year from date of despatch
d) All layout/foundation drawings etc. will be provided after confirmation of the order and
e) In the event of order cancellation the advance payment received will be non refundable and
interest free
Page 3 of 4
Dispatch Terms:
f) All goods supplied as per Packing list shall be construed as received in total content, quantity
or number of packages & good condition at your delivery site, unless discrepancy, if any, is
notified by an email on “[email protected]” within 15 days of clearance of the goods from
the Port of Discharge or 30 days of date of arrival at destination port whichever is earlier.
g) Any subsequent loss, damage or shortage of material on site would be on your account if the
goods are unpacked in absence of our Company representative.
Confidentiality and Restrictions :
This Proforma Invoice is property of Kumar Metal Industries Pvt Ltd. and is a confidential
presentation to Buyer for its exclusive use in considering the Equipment of Seller and shall
not be disclosed to third parties without prior written consent from the Seller.
DIRECTOR
Page 4 of 4