Network Models - Part 9
Network Models - Part 9
Network Models
Part 9
Subject: PMOR
Faculty: Prof. Y. M. Khan
Asst. Professor,
Dept. of Mechanical Engineering, ICEEM,
Aurangabad
PERT
0 - 0 -0
2-2-8 4-6-8
1 2 5 6
3
Activity (σ)2 te
(i-j) to tm tp ((tp-to)/6)2 (to+4tm+tp)/6
1-2
2 2 8 1 3
2-3
1 1.5 11 2.8 3
2-4
0.5 2.5 7.5 1.36 3
3-4
0 0 0 0.0 0
3-5
1 2.5 7 1 3
3-6
1 2 3 0.11 2
4-5
6 7 8 0.11 7
4-6
3 4 11 1.78 5
5-6
4 6 8 0.44 6
E=6 𝑇−𝑇𝑐𝑝
Z= ( ) 𝑇=20 𝑇𝑐𝑝=19 σcp= ∑σ2𝒊𝒋
L=6 σcp
σcp1= 𝟏 + 𝟐. 𝟖 + 𝟎 + 𝟎. 𝟏𝟏 + 𝟎. 𝟒𝟒 = 𝟐. 𝟎𝟖
4 σcp2= 𝟏 + 𝟏. 𝟑𝟔 + 𝟎. 𝟏𝟏 + 𝟎. 𝟒𝟒 = 𝟏. 𝟕𝟎
E=0 E=3 E=19
L=0 L=3 L=19
1-4-7 2 - 5 - 14 3 - 6 - 15
1 3 5 6
Path 1: 1 - 2 – 5 – 6
Path 2: 1 - 3 – 5 – 6
Path 3: 1 – 4 – 6
4
2. Determine expected project length
Activity to tm tp (σ)2 te Activity to tm tp (σ)2 te
(i-j) (i-j)
1-2 1 1 7 1 2 3-5 2 5 14 4 6
1-3 1 4 7 1 4 4-6 2 5 8 1 5
1-4 2 2 8 1 3 5-6 3 6 15 4 7
2-5 1 1 1 0 1
2
Project Duration
Path 1: 1 - 2 – 5 – 6 = 2+1+7=10
1-4-7 2 - 5 - 14 3 - 6 - 15
Path 2: 1 - 3 – 5 – 6 = 4+6+7=17
1 te=4
3 5 te=7
6
Path 3: 1 – 4 – 6 = 3+5=8 te=6
1-4-7 2 - 5 - 14 3 - 6 - 15
1 3 5 σ2 =4
6
σ2 =1 σ2 =4
4
4. What is the probability that the project will be completed :
a) at least 4 weeks earlier than expected?
b) No more than 4 weeks later than expected time?
Z= (
𝑇−𝑇𝑐𝑝
) Z= (
13−17
) Z= -1.33 P=1-0.9082
σcp 3
Since Z is negative Subtracting value of p obtained from C2 table for Z= 1.33 from 1
So, the Probability of completing the project 4 weeks earlier is = 0.0918= 9.18%
b) No more than 4 weeks later than expected time
Z= (
𝑇−𝑇𝑐𝑝
) Z= (
21−17
) Z= 1.33 P=0.9082
σcp 3
So, the Probability of completing the project at most 4 weeks later is = 0.9082=
90.82%
5) If the project due date is 19 weeks
Tcp=Expected time = 17 weeks
T= scheduled time = 19 weeks
Z= (
𝑇−𝑇𝑐𝑝
) Z= (
19−17
) Z= 0.67 P=0.7486
σcp 3
Z= (
𝑇−𝑇𝑐𝑝
) Z= (
20−17
) Z= 1 P=0.8413
σcp 3
Stay At Home
Stop gathering
Stay Safe