SCHEDULE OF QUANTITIES

VALVE SHOP BOQ

ITEM PAYMENT DESCRIPTION UNIT QUANTITY RATE AMOUNT

1 SANS 1200 A SECTION 1: PRELIMINARY & GENERAL

1.1 8.3 FIXED-CHARGE AND VALUE-RELATED ITEMS

1.1.1 8.3.1 Contractual Requirements Sum 1.00 12400.00 12400.00

1.1.2 8.3.2 Establishment of Facilities on the Site Sum 1.00 80000.00 80000.00

1.13 Facilities for Contractor Sum 1.00 25000.00 25000.00

1.1.4 Offices and storage shed Sum 1.00 35000.00 35000.00

1.1.5 Workshops Sum 1.00 10000.00 10000.00

1.1.6 Ablution and latrine facilities Sum 1.00 36000.00 36000.00

1.1.7 Tools and equipment Sum 1.00 18500.00 18500.00

1.1.8 Water supplies, electric power and communications


Sum 1.00 55000.00 55000.00

1.1.9 Plant Sum 1.00 22500.00 22500.00

1.1.10 8.3.3 Other Fixed-charge Obligations Sum 1.00 8500.00 8500.00

1.1.11 8.3.4 Removal of Site Establishment Sum 1.00 30000.00 30000.00

Occupational Health and Safety

1.1.12 Compliance with Occupational Health and Safety


Act (Act 85 of 1993) and its regulations and with the Sum 1.00 30000.00 30000.00
Employers Health and Safety Specification

Environmental Management

1.1.13 Compliance with Employer's Environmental


Sum 1.00 25000.00 25000.00
Management Plan
SCHEDULE OF QUANTITIES
VALVE SHOP BOQ

1.2 8.4 TIME RELATED ITEMS

1.2.1 8.4.1 Contractual Requirements Sum 1.00 15000.00 15000.00

Operation and Maintenance of facilities on site, for


1.2.2 8.4.2 duration of construction, except where otherwise Sum 1.00 10000.00 10000.00
stated

8.4.2.2 Facilities for Contractor:

1.2.3 Offices and storage shed Sum 1.00 20000.00 20000.00

1.2.4 Workshops Sum 1.00 25000.00 25000.00

1.2.5 Ablution and latrine facilities Sum 1.00 36000.00 36000.00

1.2.6 Tools and equipment Sum 1.00 12000.00 12000.00

1.2.7 Water supplies, electric power and communications


Sum 1.00 30000.00 30000.00

1.2.8 Plant (Mobile Hoisters, Concrete Breaker, Concrete


Sum 1.00 40000.00 40000.00
mixer, Welding Machines, LDV etc)

1.2.9 8.3.3 Other Fixed-charge Obligations Sum 1.00 8500.00 8500.00

1.2.10 8.4.3 Supervision for Duration of Construction Sum 1.00 70000.00 70000.00

1.2.11 Company and Head Office Overhead Costs for the


8.4.4 Sum 1.00 295000.00 295000.00
Duration of the Contract

1.2.12 8.4.5 Other Time-related Obligations Sum 1.00 8500.00 8500.00

Occupational Health and Safety

1.2.13 Compliance with Occupational Health and Safety


Act (Act 85 of 1993) and its regulations and with the
Employers Health and Safety Specification - Sum 1.00 30000.00 30000.00
Hazardous Material PPE

Environmental Management Sum 1.00 25000.00 25000.00

TOTAL CARRIED FORWARD TO SUMMARY R 1,012,900.00


SCHEDULE OF QUANTITIES
VALVE SHOP BOQ

ITEM PAYMENT DESCRIPTION UNIT QUANTITY RATE AMOUNT

SANS 1200 C SECTION 2: SITE CLEARANCE

2.1 Demolish and remove off site to an approved dump


8.2.8
site, existing:

2.1.1 Demolish Existing Concrete Slab (150mm thick) m3 2.50 2320.00 5800.00

2.1.2 GPR Scanning (2000mm x 2000mm). Sum 1.00 6250.00 6250.00

TOTAL CARRIED FORWARD TO SUMMARY R 12,050.00

ITEM PAYMENT DESCRIPTION UNIT QUANTITY RATE AMOUNT

3 SANS 1200 D SECTION 3: EARTHWORKS

3.1 EARTHWORKS

3.1.1 8.3.2 Excavation

Excavation for foundations (2000mm x 1850mm x


3.1.1.1 m3 17.00 180.00 3060.00
1050mm)

3.1.1.2 Rip & compact insitu layer


Level and compact disturbed surface for foundations to
93% MOD AASHTO density at OMC m2 16.00 295.00 4720.00

Import G6 selected fill and place to lines and levels


3.1.1.3 compacted to 95% MOD AASHTO in 150mm layers:
m³ 5.00 865.00 4325.00

Main-fill on the sides of the concrete foundation


3.1.1.4 compacted in 150mm layers. m³ 15.00 95.00 1425.00

TOTAL CARRIED FORWARD TO SUMMARY R 13,530.00

ITEM PAYMENT DESCRIPTION UNIT QUANTITY RATE AMOUNT

4 SANS 1200G SECTION 4: CONCRETE (STRUCTURAL)

4.1 CONCRETE SUPPLY AND ERECT PRECAST


8.6
ELEMENTS

4.1.1 8.4.2 Blinding layer 15MPa concrete

4.1.1.1 50mm min thickness (Cast-in situ) m3 0.40 2980.00 1192.00

30Mpa Strength Concrete for foundation and plinth


4.1.2 m3 3.50 3360.00 11760.00

4.2 8.2.2 FORMWORK

4.2.1 Smooth vertical plane to: 0.00

4.2.2 Concrete Foundation and Plinth m2 4.00 680.00 2720.00

4.3 8.3.1 REINFORCEMENT

4.3.1 Reinforcement for Foundation and Plinth


High-tensile and mild steel bars
8-Y20 t 0.11 69491.64 7644.08
Y12-200-T1 t 0.06 377485.33 22649.12
Y12-200-B1 t 0.06 377485.33 22649.12
R10-300 t 0.03 95220.00 2856.60

4.4 UNFORMED SURFACE FINISHES

4.4.1 Wood-floated finish m2 2.00 85.00 170.00

4.5 8.7 GROUTING

Grout beneath base plates m3 0.08 8000.00 640.00


SCHEDULE OF QUANTITIES
VALVE SHOP BOQ
SCHEDULE OF QUANTITIES
VALVE SHOP BOQ

TOTAL CARRIED FORWARD TO SUMMARY R 72,280.92


SCHEDULE OF QUANTITIES
VALVE SHOP BOQ

ITEM PAYMENT DESCRIPTION UNIT QUANTITY RATE AMOUNT

5 SANS 1200H SECTION 5: STRUCTURAL STEELWORK

Remove existing sliding door, girts and cladding to


5.1
create open plan.
M16 connection bolt No. 80.00 10.50 840.00
Connection plate (200mm x 150mm) No. 20.00 13.50 270.00
Girt (150mm x 150mm x 20mm x 2mm) m 63.00 85.00 5355.00
Cladding m2 87.00 95.00 8265.00
Sliding door No. 1.00 480.00 480.00

5.2 8.3.1 SUPPLY AND FABRICATION

5.2.1 8.3.1.1 Preparation of shop detail drawings Sum 1.00 0.00 0.00

5.2.2 8.3.1.2 Using steel to EN 10025 Grade S355JR

5.2.3 I-Section Columns (305mm x 165mm x 40kg/m) t 1.03 28590.00 29447.70

5.2.4 I-Section Jib (200mm x 100mm x 22.4kg/m) t 0.27 20890.00 5640.30

5.2.5 I-Section Brace (140mm x 73mm x 12.9kg/m) t 0.16 19760.00 3161.60

5.2.6 I-Section Rafter (305mm x 165mm x 40kg/m) t 0.80 28590.00 22872.00

Beam Hinge [Angle Equal-leg] (200mm x 200mm x


5.2.7 t 0.13 25980.00 3377.40
48.1kg/m)

5.2.8 Stopper [Angle Equal-leg] (75mm x 75mm x 17kg/m) t 0.02 30897.00 617.94

5.2.9 Cleat [Angle Equal-leg] (150mm x 150mm x 10kg/m) t 0.05 65765.00 3288.25

Reinstall existing connection plate (200mm x 150mm) No. 20.00 220.00 4400.00

Purlin and girt [Lip-Channel] (175mm x 75mm x 20mm m


5.2.10 110.00 295.00 32450.00
x 2.2mm)
Reinstall exsiting girt (150mm x 150mm x 20mm x m 63.00 125.00 7875.00
2mm)

5.2.11 Connection Plate


(412mm x 470mm x 10mm) No. 10.00 885.00 8850.00
(470mm x 200mm x 10mm) No. 6.00 875.00 5250.00

5.2.12 Flat Bar (500mmx 90mm x 16mm) No. 5.00 520.00 2600.00

5.2.13 Flat Bar (400mmx 90mm x 16mm) No. 5.00 448.50 2242.50

5.2.14 Flat Bar (130mmx 120mm x 16mm) No. 9.00 398.70 3588.30

5.2.15 Stiffener Plates (305mm x 100mm x 10mm) No. 84.00 308.80 25939.20

5.2.16 Stiffener Plates (285mm x 80mm x 10mm) No. 18.00 297.60 5356.80

5.2.17 Web Connection Plates (400mm x200mm x 8mm) No. 10.00 635.00 6350.00

5.2.18 Flage Connection Plates (400mm x 160mm x 12mm) No. 10.00 658.00 6580.00

5.2.19 Base plate (470mm x 329mm x 30mm) No. 5.00 2280.00 11400.00

5.2.20 HD Bolts Footing Cage No. 5.00 145.00 725.00

5.2.21 8.8 M24 HD Galvanized Bolts(Grade 8.8) 700mm in length No. 18.00 75.00 1350.00

Washer for M24 bolts No. 36.00 4.50 162.00

M30 Hinge Beam Bolts with a total length of 330mm


5.2.22 No. 9.00 95.00 855.00
and 65mm threads
Washer for M30 bolts No. 18.00 7.50 135.00

5.2.23 M20 Galvanized Connection Bolts (Grade 8.8) No. 18.00 65.00 1170.00
Washer for M20 bolts No. 36.00 2.25 81.00
SCHEDULE OF QUANTITIES
VALVE SHOP BOQ

5.2.24 M16 Galvanized Connection Bolts (Grade 8.8) No. 186.00 35.00 6510.00
Washer for M16 bolts No. 372.00 2.15 799.80

5.2.25 IBR Sheeting m2 163.00 178.00 29014.00


Reinstall existing IBR sheeting (Cladding) m2 71.00 168.00 11928.00

5.2.26 Reinstall existing sladding door No. 1.00 985.00 985.00

5.3 8.3.10 NON DESTRUCTIVE TESTING

10% of welds Sum 1.00 35800.00 35800.00

TOTAL CARRIED FORWARD TO SUMMARY R 280,801.79

ITEM PAYMENT DESCRIPTION UNIT QUANTITY RATE AMOUNT

6 SECTION 6: CORROSION PROTECTION OF


SANS 1200HC
STRUCTURAL STEELWORK

6.1 8.2.3 Surface Preparation as per SP 80-02


6.1.1 Surface preparation and coating application in shop
m2 221.00 120.00 26520.00
(Primer, intermediate and final)
6.1.2 Surface preparation and touch-up coating on site m2 221.00 280.00 3094.00

TOTAL CARRIED FORWARD TO SUMMARY R 29,614.00


SCHEDULE OF QUANTITIES
VALVE SHOP BOQ

ITEM PAYMENT DESCRIPTION UNIT QUANTITY RATE AMOUNT

7 SECTION 7: ACCESS REQUIREMENTS

7.1 Scaffolding to clients requirements and SANS10085-


Sum 1.00 60000.00 60000.00
Provisional Allowance

TOTAL CARRIED FORWARD TO SUMMARY R 60,000.00

SECTION 1: PRELIMINARIES AND GENERALS R 1,012,900.00


SECTION 2: SITE CLEARANCE R 12,050.00
SECTION 3: EARTHWORKS R 13,530.00
SECTION 4: CONCRETE (STRUCTURAL) R 72,280.92
SECTION 5: STRUCTURAL STEELWORK R 280,801.79
SECTION 6: CORROSION PROTECTION OF STRUCTURAL STEELWORK R 29,614.00
SECTION 7: ACCESS REQUIREMENTS R 60,000.00

SUB-TOTAL (A) R 1,481,176.71


CONTINGENCY (20%) R 74,058.84
SUB-TOTAL (A + CONTINGENCY) R 1,555,235.55
VAT (15%) R 233,285.33

TOTAL R 1,788,520.88