The document provides specifications for various construction elements including: 1. Footings, walls, beams, catch basins, and septic tanks with their dimensions and quantities. 2. Estimates of concrete, reinforcement steel, sand and gravel required for columns, footings, beams, slabs and other structures. 3. Breakdowns of masonry works showing wall lengths, heights, quantities of concrete blocks and estimates of mortar and sand needed for various elevations. The document appears to be a quantity survey specifying materials needed for an earthworks and construction project.

Uploaded by

Yra Mae Viluan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
45 views28 pages

ESTIMATE

The document provides specifications for various construction elements including: 1. Footings, walls, beams, catch basins, and septic tanks with their dimensions and quantities. 2. Estimates of concrete, reinforcement steel, sand and gravel required for columns, footings, beams, slabs and other structures. 3. Breakdowns of masonry works showing wall lengths, heights, quantities of concrete blocks and estimates of mortar and sand needed for various elevations. The document appears to be a quantity survey specifying materials needed for an earthworks and construction project.

Uploaded by

Yra Mae Viluan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 28

EARTH WORKS (QU

FOOTING LENGTH WIDTH AREA ( sq.m )


F1 1.20 1.00 1.20

WALL FOOTING LENGTH WIDTH AREA ( sq.m )


WF1 70.05 0.45 31.52
WF2 86.17 0.45 38.78
NOTE: Every 3m need a footing based on PNS
TIE BEAM LENGTH WIDTH AREA ( sq.m )
TB1 32.50 0.30 9.75

CATCH BASIN LENGTH WIDTH AREA ( sq.m )


CB1 1.60 1.60 2.56

SEPTIC TANK LENGTH WIDTH AREA ( sq.m )


ST1 6.40 2.60 16.64
EARTH WORKS (QUANTITY SURVEY)

HEIGHT QUANTITY VOLUME ( cu.m ) BAGS OF CEMENT


1.90 15.00 34.20 307.80
TOTAL 34.20 307.80
HEIGHT QUANTITY VOLUME ( cu.m ) BAGS OF CEMENT
0.30 9.46 85.11
0.30 11.63 104.70
TOTAL 11.63 104.70
HEIGHT QUANTITY VOLUME ( cu.m ) BAGS OF CEMENT
0.40 3.90 35.10
TOTAL 3.90 35.10
HEIGHT QUANTITY VOLUME ( cu.m ) BAGS OF CEMENT
3.20 1.00 8.19 73.73
TOTAL 8.19 73.73
HEIGHT QUANTITY VOLUME ( cu.m ) BAGS OF CEMENT
4.00 66.56 599.04
TOTAL 66.56 599.04
SAND ( cu.m ) GRAVEL ( cu.m )
17.10 34.20
17.10 34.20
SAND ( cu.m ) GRAVEL ( cu.m )
4.73 9.46
5.82 11.63
5.82 11.63
SAND ( cu.m ) GRAVEL ( cu.m )
1.95 3.90
1.95 3.90
SAND ( cu.m ) GRAVEL ( cu.m )
4.10 8.19
4.10 8.19
SAND ( cu.m ) GRAVEL ( cu.m )
33.28 66.56
33.28 66.56
CONCRETE WORKS (QUAN

COLUMN ( CLASS A / 40kgs ) LENGTH WIDTH AREA ( sq.m ) HEIGHT


C 0.20 0.30 0.06 5.00

FOOTING ( CLASS A / 40kgs ) LENGTH WIDTH AREA ( sq.m ) HEIGHT


F 1.00 1.00 1.00 0.30

ROOF BEAM ( CLASS A / 40kgs ) LENGTH WIDTH AREA ( sq.m ) HEIGHT


RB 119.42 0.30 35.82 0.30

ROOF TIE BEAM ( CLASS A / 40kgs ) LENGTH WIDTH AREA ( sq.m ) HEIGHT
RTB 119.42 0.30 35.82 0.40

SLAB ON FILL (CLASS A / 40kgs ) LENGTH WIDTH AREA ( sq.m ) HEIGHT


AREA 1 12.50 3.00 37.50 0.15
AREA 2 3.50 3.50 12.25 0.15
AREA 3 3.00 3.50 10.50 0.15
AREA 4 3.00 3.50 10.50 0.15
AREA 5 3.00 3.50 10.50 0.15

SUMMARY
CRETE WORKS (QUANTITY SURVEY)

QUANTITY VOLUME ( cu.m ) BAGS OF CEMENT SAND ( cu.m )


28.00 8.40 75.60 4.20
TOTAL 8.40 75.60 4.20
QUANTITY VOLUME ( cu.m ) BAGS OF CEMENT SAND ( cu.m )
15.00 4.50 40.50 2.25
TOTAL 4.50 40.50 2.25
QUANTITY VOLUME ( cu.m ) BAGS OF CEMENT SAND ( cu.m )
23.00 247.19 2224.70 123.59
TOTAL 247.19 2224.70 123.59
QUANTITY VOLUME ( cu.m ) BAGS OF CEMENT SAND ( cu.m )
23.00 329.59 2966.27 164.79
TOTAL 329.59 2966.27 164.79
QUANTITY VOLUME ( cu.m ) BAGS OF CEMENT SAND ( cu.m )
5.63 50.63 2.81
1.84 16.54 0.92
1.58 14.18 0.79
1.58 14.18 0.79
1.58 14.18 0.79
TOTAL 12.19 109.69 6.09

VOLUME ( cu.m ) BAGS OF CEMENT SAND ( cu.m )


COLUMN 6.00 54.00 3.00
FOOTING 90.00 810.00 45.00
ROOF BEAM 193.20 1738.80 96.60
ROOF TIE BEAM 193.20 1738.80 96.60
SLAB 12.19 109.69 6.09
TOTAL 494.59 4451.29 247.29
GRAVEL ( cu.m )
8.40
8.40
GRAVEL ( cu.m )
4.50
4.50
GRAVEL ( cu.m )
247.19
247.19
GRAVEL ( cu.m )
329.59
329.59
GRAVEL ( cu.m )
5.63
1.84
1.58
1.58
1.58
12.19

GRAVEL ( cu.m )
9.00
90.00
193.20
193.20
1.19
486.59
MASONRY WORKS (QUANTITY SURVEY)

A. FRONT ELEVATION
Cement Cement
Sand
(40kg) (40kg)
(cu.m.)
WALL LENGTH HEIGHT AREA NO. OF CHB (bags) (bags)
W1 2.7 3.5 7.53 94.125 PLASTER MORTAR
W2 2.7 3.5 8.49 106.125 2.89 0.24 3.93
3.26 0.27 4.43
FRONT TOTAL: 200.25 6.15 0.51 8.36
A. RIGHT ELEVATION
Cement Cement
Sand
(40kg) (40kg)
(cu.m.)
WALL LENGTH HEIGHT AREA NO. OF CHB (bags) (bags)
W1 3.2 3.5 9.76 122 PLASTER MORTAR
W2 2.7 3.5 8.01 100.125 3.75 0.31 5.09
W3 2.7 3.5 8.01 100.125 3.08 0.26 4.18
W4 2.7 5.5 13.65 170.625 3.08 0.26 4.18
5.24 0.44 7.13
RIGHT TOTAL: 270.75 8.32 0.69 11.31
A. LEFT ELEVATION
Cement Cement
Sand
(40kg) (40kg)
(cu.m.)
WALL LENGTH HEIGHT AREA NO. OF CHB (bags) (bags)
W1 3.2 3.5 10.84 135.5 PLASTER MORTAR
W2 2.7 3.5 8.01 100.125 4.16 0.35 5.66
W3 2.7 3.5 8.01 100.125 3.08 0.26 4.18
W4 2.7 3.5 8.01 100.125 3.08 0.26 4.18
3.08 0.26 4.18
LEFT TOTAL: 200.25 6.15 0.51 8.36
A. LEFT ELEVATION
Cement Cement
Sand
(40kg) (40kg)
(cu.m.)
WALL LENGTH HEIGHT AREA NO. OF CHB (bags) (bags)
W1 2.7 3.5 9.09 113.625 PLASTER MORTAR
W2 0.5 3.5 0.31 3.875 3.49 0.29 4.74
W3 0.725 3.5 1.0975 13.71875 0.12 0.01 0.16
W4 1.175 3.5 2.6725 33.40625 0.42 0.04 0.57
1.03 0.09 1.40
REAR TOTAL: 47.125 1.45 0.12 1.97
EY)

Sand (cu.m.)

MORTAR
0.33
0.37
0.70

Sand (cu.m.)

MORTAR
0.42
0.35
0.35
0.59
0.94

Sand (cu.m.)

MORTAR
0.47
0.35
0.35
0.35
0.70

Sand (cu.m.)

MORTAR
0.40
0.01
0.05
0.12
0.16
METAL REINFORCEMENT WOR

A. CONCRETE HOLLOW BLOCK AREA

243.75

1. TIRE WIRE FOR CHB REINFORCEMENT 243.75

B. FOOTING REINFORCEMENT
FR

1. FOOTING TIRE WIRE

C. POST AND COLUMN REINFORCEMENT

1. LATERAL TIES HEIGHT


a. C1 5.35

2. TIE WIRE
D. BEAM AND GRIDDER REINFORCMENT

RB

1. STIRRUPS
RB1
RB2

2. TIRE WIRE

E. FLOOR SLAB REINFORCEMENT


1. SLAB FLOOR
AREA 1
AREA 2
AREA 3
AREA 4
AREA 5
AREA 6
METAL REINFORCEMENT WORKS (QUANTITY SURVEY)

VERTICAL REINFORCEMENT HORIZONTAL REINFORCEMENT

519.1875 524.0625

NET LENGTH NO. OF CUT BARS


1.05 12

INTERSECTIONS TIES
30 450

LENGTH (meters) NO. OF BARS


5.35 90

SPACING NO. OF LATERAL TIES


18 19

INTERSECTION/COLUMN TOTAL INTERSECTIONS


113 1695
LENGTH (meters) NO. OF BARS

119.42 5

LENGTH NO. OF STIRRUPS


119.42 22
119.42 24

126.00 1890

WIDTH LENGTH

5.83 3.5
5 3.5
5 3
5 3
5 3
5 9
TOTAL REINFORCEMENT TOTAL NO. OF BARS

1043.25 174
TOTAL: 174
AREA TIES (KG)
243.75 8
TOTAL: 8
TOTAL NO. OF CUT BARS TOTAL NO. OF BARS
180 30
TOTAL: 30
TOTAL TIES TIES(KG)
135 2.547
TOTAL: 2.547
TOTAL LENGTH (meters) TOTAL NO. OF BARS
482 80
TOTAL: 80
TOTAL TIES TIES (pcs.)
283 57
TOTAL: 57
TOTAL TIES TIES(KG)
678 13
TOTAL LENGTH(meters) TOTAL NO. OF BARS

597 100
TOTAL: 100
TOTAL STIRRUPS TOTAL NO. OF BARS
308 51
192 32
TOTAL: 83
TOTAL WIRE: TIES(KG)
1890 36
TOTAL: 36
AREA TOTAL NO. OF BARS

20.42 53
17.50 45
15.00 39
15.00 39
15 39
45 116
TOTAL: 55
55 pcs. Of 10 mmØ
LUMBER WORKS (QUANTITY SURVEY)

A. WOOD TRUSS
1. TRUSS
BOTTOM CHORD (m.) TOP CHORD (m.)
a. TRUSS-1 30.00 34.00

1. CEE PURLINS

TOP CHORD (m.) PURLINS SPACING (m.)

4.00 0.6

B. CEILING JOIST LENGTH


4.80
7.55
8.53
5.25

C. CEILING BOARD LENGTH


4.80
7.55
8.53
5.25
UANTITY SURVEY)

WEB MEMBERS (m.) TOTAL LENGTH (m.) NO. OF ANGLE BARS (pcs)
13.68 64.00 11

TOTAL 11

TOTAL ROWS OF
TOTAL LENGTH NO. OF CEE PURLINS
PURLINS

13 167 28
TOTAL 28

WIDTH AREA NO. OF PIECES


10.00 48.00 306.19
9.56 72.18 460.42
7.74 66.02 421.16
7.15 37.54 239.45
TOTAL: 1427.22
WIDTH AREA NO. OF PIECES
10.00 48.00
9.56 72.18
7.74 66.02
7.15 37.54
223.74 78
TOTAL: 78
QUANTITY OF FORM,SCAFFOLDING & STA

LATERAL
A. FORMS A B HEIGHT
PERIMETER
1. COLUMN
a. C1 0.20 0.40 1.4 3.5

LATERAL
2. BEAM A B LENGTH
PERIMETER
a. RB 0.30 0.40 1.5 58.00

NO. OF
B. SCAFFOLDING HEIGHT TOTAL HEIGHT
COLUMNS
1. COLUMN
a. C1 5.35 15.00 80.25
TOTAL:
2. BEAM LENGTH NO. OF BEAMS
a. RB 58.00 1.00
ITY OF FORM,SCAFFOLDING & STAGING

NO. OF PCS AREA NO. OF PLYWOOD

15.00 73.5 26
TOTAL: 26

NO. OF PCS AREA NO. OF PLYWOOD


1.00 87 30
TOTAL: 30

VERTICAL
HORIZONTAL SUPPORT BRACES
SUPPORT

561.75 1685.25 938.925


561.75 1685.25 938.925
TOTAL LENGTH VERTICAL SUPPORT HORIZONTAL SUPPORT
58.00 348 272.6
TOTAL: 348 272.6
QUANTITY OF ROOFING MATERIALS

A. CORRUGATED G.I. SHEET

LENGTH OF GUTTER EFFECTIVE WIDTH


38.00 0.70
TOTAL
B. RIVETS
NO. OF SHEETS (one
NO. OF RIVETS
row)
54.29 1194.29
TOTAL
C. G.I. WASHER
NO. OF G.I. WASHER
2388.57
TOTAL
D. PLAIN G.I. STRAP ON 2" X 3"
PURLINS
NO. OF RIVETS
1194.29
TOTAL
E. LEAD WASHERS
NO. OF LEAD WASHER
1194.29
TOTAL
F. ROOF GUTTER
LENGTH OF GUTTER TOTAL NO. OF GUTTER
38.00 16.17
TOTAL 16.17
MATERIALS

NO. OF SHEETS (one row)


54.29
54.29

TOTAL RIVETS (kg)

6.63
7

TOTAL G.I. WASHER (kg)


18.66
19

TOTAL G.I. SHEETS (pcs)


3.11
2.3

TOTAL LEAD WASHER (kg)


15.92
15.92

TOTAL NO. OF ROOF FLASHING


7.35
7.35
QUANTITY OF TILEWORKS

A. GLAZED TILES TILE DIMENSION


FLOOR AREA (sq.m.) LENGTH (m) WIDTH (m)
81.25 0.3 0.3

B. UNGLAZED TILES(WALL) TILE DIMENSION


FLOOR AREA (sq.m.) LENGTH (m) WIDTH (m)
81.25 0.2 0.2

CEMENT MORTAR AND JOINT


FILLER

FLOOR AREA

162.5
TOTAL
LEWORKS

AREA (sq.m.) NO. TILES (pcs)


0.09 903
TOTAL 903

AREA (sq.m.) NO. TILES (pcs)


0.04 2031.25
TOTAL 2031.25

CEMENT MORTAR (bags) WHITE CEMENT (kgs)

13.98 81.25
13.98 81.25
QUANTITY OF PAINTING WORKS

A. FINE TO SMOOTH SURFACE


WALL AREA COVERAGE PER
GALLONS (gallons)
206.98 17
TOTAL 17
TING WORKS

FINAL COAT NEUTRILIZER(liters)

17 6.8
17 7
SUMMARY OF QUANTITIES

QUANTITY OF EARTHWORKS COMPONEN


VOLUME ( cu.m )
FOOTING ( CLASS A / 40kgs ) 34.20
WALL FOOTING ( CLASS A / 40kgs ) 6.75
TIE BEAM ( CLASS A / 40kgs ) 3.90
CATCH BASIN ( CLASS A / 40kgs ) 8.19
SEPTIC TANK ( CLASS A / 40kgs ) 66.65
QUANTITY OF CONCRETE COMPONENT
VOLUME ( cu.m )
COLUMN 6.00
FOOTING 90.00
ROOF BEAM 193.20
ROOF TIE BEAM 193.20
SLAB 12.19
QUANTITY OF MASONRY COMPONENT

A. CONCRETE HOLLOW BLOCKS


B. CEMENT MORTAR
C. CEMENT MORTAR FOR PLASTERING

QUANTITY OF METAL REINFORCEMEN

A. CONCRETE HOLLOW BLOCK REINFORCEMENT


1. TIE WIRE FOR CHB REINFORCEMENT
B. FOOTING REINFORCEMENT
1. FOOTING TIE WIRE
C. POST AND COLUMN REINFORCEMENT
1. LATERAL TIES
2. TIE WIRE
D. BEAM AND GIRDER REINFORCEMENT
1. STIRRUPS
2. TIRE WIRE
E. FLOOR SLAB REINFORCEMENT
QUANTITY OF STEEL AND LUMBER COMPON

A. WOOD TRUSS
1. TRUSS
2. CEE PURLINS
B. CEILING JOIST
C. CEILING BOARD
QUANTITY OF FORM, SCAFFOLDING AND ST
VERTICAL SUPPORT
A. FORMS
1. COLUMN
2. BEAM
B. SCAFFOLDING
1. COLUMN 561.75
2. BEAM 348.00

QUANTITY OF ROOFING MATERIALS


A. CORRUGATED G.I. SHEET
B. RIVETS
C. G.I. WASHER
D. PLAIN G.I. STRAP ON 2" X 3" PURLINS
E. LEAD WASHERS
F. ROOF GUTTER
QUANTITY OF TILEWORKS

A. GLAZED TILES
B. UNGLAZED TILES
C. CEMENT MORTAR AND JOINT FILLER
QUANTITY OF PAINTING WORKS

A. FINE TO SMOOTH SURFACE


MARY OF QUANTITIES

RTHWORKS COMPONENTS
BAGS OF CEMENT SAND ( cu.m ) GRAVEL ( cu.m )
307.80 17.10 34.20
60.75 3.38 6.75
35.10 1.95 3.90
73.71 4.10 8.19
599.85 33.33 66.65
ONCRETE COMPONENTS
BAGS OF CEMENT SAND ( cu.m ) GRAVEL ( cu.m )
54.00 3.00 9.00
810.00 45.00 90.00
1738.80 96.60 193.20
1738.80 96.60 193.20
109.69 6.09 1.19
MASONRY COMPONENTS
CEMENT (bags) SAND (cu. m.) QUANTITY OF CHB
718.38
30 2
22 2

ETAL REINFORCEMENT
TOTAL NO. OF BARS TIES (kg)
174
7.80
30
2.55
80
57
13
100
83
36
55
AND LUMBER COMPONENTS
NO. OF PIECES

NO. OF PIECES
1427
78
0
SCAFFOLDING AND STAGING
HORIZONTAL SUPPORT BRACES NO. OF PLYWOOD

26
30

1685.25 938.925
272.60 620.60

ROOFING MATERIALS
54
7
18.66
2.29
15.92
7.35
Y OF TILEWORKS
CEMENT MORTAR (bags) WHITE CEMENT (kgs.) NO. OF TILES (pcs.)
903
2031.25
13.98 81.25 95.23
OF PAINTING WORKS
COVERAGE PER GALLON
FINAL COAT NEUTRALIZER (liters)
(gallons)
17 17 7