National Grid: Checklist For Commissioning of Oil-Immersed Power Transformer
National Grid: Checklist For Commissioning of Oil-Immersed Power Transformer
correct.
Check MCBs in marshalling kiosk by current
17.
injection.
Tests on On-Load Tap Changers ─
Operation test
a. check current and voltage ratings of tap
changer motor
b. Raise / Lower Control (Local – Remote)
and indication.
c. End of Tap Travel Control.
d. End of winding travel control (both
ends).
e. Check that the windings are not open
circuit during tap changing.
f. Check OLTC manual operation by hand
18.
crank
g. Check insertion of hand crank
automatically prevent electrical motor
drive operation.
h. Check OLTC tap position indicator&
operation counter
i. OLTC motor load current to be
measured for future reference purposes.
j. Check all transmitters.
k. OLTC operation, checking and testing
shall be done as recommended in OLTC
Manual provided by the manufacturer.
Perform Bushing Current Transformer Tests
29. as per latest revision of WI-NG-6460-002-
023
Perform Neutral Earthing Resistor Tests as
30.
per latest revision of WI-NG-6460-002-022
31. Functional Check of the following:-
a. Liquid Level indicator (alarm/ trip) as
applicable.
b. Oil Temperature Device: Fans / pumps
(stop, start alarm/ trip)
c. Winding Temperature Device (alarm/
trip).
d. Buchholz Relay (alarm/ trip).
e. Oil / Gas Surge (pressure) relay (alarm/
trip)
f. Pressure Relief Device (alarm/ trip) as
per design.
NATIONAL GRID